PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 04/20/26 EST. NO. 010 TIME 01:01 PM R.E. NAME: MOSALLAI MOJTABA 01-0P9604 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0508 76,836.56 E.W. @ F.A.(+) 031726 N 0508.0 0509 508.20 112125 N 0509.0 77,344.76 TOTAL THIS ESTIMATE 7,920,920.79 TOTAL PREVIOUS ESTIMATE 7,998,265.55 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 04/20/26 EST. NO. 010 TIME 01:01 PM R.E. NAME: MOSALLAI MOJTABA 01-0P9604 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- LABOR COMPLIANCE VIOLATION DEDUCT LTTR 8/25 -1,000.00 002 RTN DEDUCT LTR 8/25 1,000.00 003 DEDUCT LTTR 11/25 -1,000.00 005 PER 12/25 LTR DEDUCT -10,000.00 006 DEDUCT LTTR 1/26 -4,000.00 007 RTN DEDUCT LTR 11/25 1,000.00 007 PER 2/26 LTR DEDUCT -2,000.00 008 PER 3/26 LTR DEDUCT -1,000.00 009 RELEASE 1/26 DEDUCT 4,000.00 009 RELEASE 2/26 DEDUCT 2,000.00 009 RELEASE 3/26 DEDUCT 1,000.00 010 1,000.00 -10,000.00 TOTAL DEDUCTIONS 1,000.00 -10,000.00 PROGRAM CAS145 PAGE 1 DATE 04/20/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 01-0P9604 TIME 01:01 PM ESTIMATE NO. 010 BID OPENING 04/04/25 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 04/20/26 R.E. NAME: MOSALLAI MOJTABA DATE OF THIS ESTIMATE 04/20/26 LOCATION PROGRESS ESTIMATE 01-MEN-1-6.0/0.6 ----------------- WYLATTI RESOURCE MANAGEMENT REPAIR STORM DAMAGE P.O. BOX 575 MEN COUNTY NEW GUALALA AT OLD STATE HWWY COVELO CA 95428 REPAIR ROADWAY AND DRAINAGE DIR'S EMERGENCY ORDER F.A. FED. AID NO. N O N E PAVEMENT REPAIRS ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 PAVEMENT REPAIRS (BOND PREMIUM) LS 49,325.0000 49,325.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 04/20/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 01-0P9604 TIME 01:01 PM ESTIMATE NO. 010 BID OPENING 04/04/25 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 04/20/26 R.E. NAME: MOSALLAI MOJTABA DATE OF THIS ESTIMATE 04/20/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 77,344.76 7,998,265.55 SUBTOTAL AMOUNT EARNED 77,344.76 7,998,265.55 ORIGINAL CONTRACT AMOUNT 49,325.00 TOTAL WORK COMPLETED 77,344.76 7,998,265.55 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 1,000.00 -10,000.00 TOTAL 78,344.76 7,988,265.55 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 05/06/25 180 05/12/25 05/12/25 05/21/26 157 76 0 0 81% 87% PROGRESS IS SATISFACTORY MOSALLAI MOJTABA RESIDENT ENGINEER