PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 06/19/02 EST. NO.08 TIME 02:16 PM R.E. NAME: WHEELER, JOHN 01-310404 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 005 0006 570.52 E.W. @ F.A.(+) 041502 Y 9-1050 006 0001 1,054.24 E.W. @ F.A.(+) 032602 N 9-1060 0002 507.26 032702 N 9-1020 007 0001 15,966.17 A.C. @ U.P.(+) 061702 Y 0001 0 008 0003 281.36 E.W. @ F.A.(+) 042602 Y 0003 0 0004 110.54 041702 Y 0004 0 0005 211.02 041802 Y 0005 0 0006 281.36 041902 Y 0006 0 0007 345.04 052802 Y 0007 0 0008 378.37 053002 Y 0008 0 19,705.88 TOTAL THIS ESTIMATE 6,368.67 TOTAL PREVIOUS ESTIMATE 26,074.55 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 06/19/02 EST. NO.08 TIME 02:16 PM R.E. NAME: WHEELER, JOHN 01-310404 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- EQUAL EMPLOYMENT OPPORTUNITY SUBCONTR SUBSTITUTE -20,700.00 04 RET DED LTR DATE 4/9 20,700.00 05 0.00 0.00 TOTAL DEDUCTIONS 0.00 0.00 PROGRAM CAS145 PAGE 1 DATE 06/19/02 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 01-310404 TIME 02:16 PM ESTIMATE NO. 08 BID OPENING 07/31/01 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/20/02 R.E. NAME: WHEELER, JOHN DATE OF THIS ESTIMATE 06/19/02 LOCATION RERUN PROGRESS ESTIMATE 01-HUM-283-0.1/0.4 ----------------------- F D THOMAS INC IN HUMBOLDT COUNTY IN AND NEAR RIO P O BOX 4663 DELL AT EEL RIVER BRIDGE OVERHEAD MEDFORD OR 97501 FED. AID NO. STP-S283(1)E ,ACBH-S283(1)E REHABILITATE EXISTING BRIDGE ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 001 CONSTRUCTION AREA SIGNS LS 4,400.0000 4,400.00 0.800 3,520.00 (S) 002 TRAFFIC CONTROL SYSTEM LS 24,200.0000 24,200.00 0.340 8,228.00 (S) 003 TYPE III BARRICADE EA 220.0000 1,760.00 4.000 880.00 (S) 004 TEMPORARY PAVEMENT MARKING (TAPE) M2 220.0000 3,740.00 17.040 3,748.80 005 CHANNELIZER (SURFACE MOUNTED) EA 48.0000 3,120.00 55.000 2,640.00 006 TEMPORARY SIGNAL SYSTEM LS 9,350.0000 9,350.00 0.800 7,480.00 (S) 007 PORTABLE CHANGEABLE MESSAGE SIGN EA 3,850.0000 7,700.00 2.000 7,700.00 008 REMOVE METAL BEAM GUARD RAILING M 33.3000 399.60 0.000 0.00 009 REMOVE YELLOW THERMOPLASTIC TRAFFIC M 55.0000 9,900.00 242.000 13,310.00 STRIPE 010 RECONSTRUCT METAL BEAM GUARD RAILING M 542.0000 6,504.00 0.000 0.00 (S) 011 RECONSTRUCT TERMINAL SECTION (TYPE C) LS 170.0000 170.00 0.000 0.00 (S) 012 BRIDGE REMOVAL (PORTION) LS 108,100.0000 108,100.00 0.450 48,645.00 013 GUARD RAILING WEED CONTROL MAT M 132.0000 3,300.00 0.000 0.00 (S) 014 CLEAN STRUCTURAL STEEL (EXISTING BRIDGE) LS 280,000.0000 280,000.00 0.022 6,160.00 0.415 116,200.00 015 PAINT STRUCTURAL STEEL (EXISTING BRIDGE) LS 1054,960.0000 1,054,960.00 0.148 156,134.08 0.365 385,060.40 016 SPOT BLAST CLEAN AND PAINT UNDERCOAT M2 194.0000 512,160.00 947.160 183,749.04 2,619.730 508,227.62 017 WORK AREA MONITORING LS 15,000.0000 15,000.00 0.167 2,505.00 (S) 018 AIR MONITORING INSIDE CONTAINMENT LS 20,000.0000 20,000.00 0.248 4,960.00 0.448 8,960.00 (S) SYSTEM 019 MISCELLANEOUS METAL (BRIDGE) KG 7.6700 553,774.00 0.000 0.00 (SF) 020 TERMINAL SYSTEM (TYPE SRT) EA 3,300.0000 3,300.00 0.000 0.00 (S) 021 100 MM THERMOPLASTIC TRAFFIC STRIPE M 3.3000 4,554.00 0.000 0.00 (S) 022 PAVEMENT MARKER (NON-REFLECTIVE) EA 5.5000 2,750.00 0.000 0.00 (S) PROGRAM CAS145 PAGE 2 DATE 06/19/02 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 01-310404 TIME 02:16 PM ESTIMATE NO. 08 BID OPENING 07/31/01 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/20/02 R.E. NAME: WHEELER, JOHN DATE OF THIS ESTIMATE 06/19/02 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 023 PAVEMENT MARKER (RETROREFLECTIVE) EA 6.6600 999.00 0.000 0.00 (S) 024 TRAFFIC MONITORING STATION (COUNT) LS 3,850.0000 3,850.00 0.450 1,732.50 (S) 025 BRIDGE LIGHTING AND ELECTRICAL WORK LS 107,800.0000 107,800.00 0.060 6,468.00 (S) PROGRAM CAS145 PAGE 3 DATE 06/19/02 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 01-310404 TIME 02:16 PM ESTIMATE NO. 08 BID OPENING 07/31/01 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/20/02 R.E. NAME: WHEELER, JOHN DATE OF THIS ESTIMATE 06/19/02 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION 351,003.12 1,125,305.32 ADJUSTMENT OF COMPENSATION 15,966.17 15,966.17 EXTRA WORK 3,739.71 10,108.38 SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION 370,709.00 1,151,379.87 026 MOBILIZATION LS 194,000.0000 194,000.00 0.950 184,300.00 ORIGINAL CONTRACT AMOUNT 2,935,790.60 TOTAL WORK COMPLETED 370,709.00 1,335,679.87 MATERIALS ON HAND ON SITE 136,683.32 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 370,709.00 1,472,363.19 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 09/06/01 240 11/05/01 09/21/01 10/08/02 172 13 4 3 44% 69% PROGRESS IS SATISFACTORY UNSATIS PROGRESS OVERRIDEN BECAU PENDING CCO DAYS WHEELER, JOHN RESIDENT ENGINEER PROGRAM CAS145 DATE 06/19/02