PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 05/20/25 EST. NO. 003 TIME 03:57 PM R.E. NAME: HIGGINS KYLE 02-1K4004 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0053 2,165.06 E.W. @ F.A.(+) 031525 N 0053 0054 6,393.00 031525 N 0054 0067 4,418.20 033125 N 0067 0071 107.86 040625 N 0071 0072 17,348.53 040725 N 0072 0073 9,968.30 040825 N 0073 0074 11,435.27 040925 N 0074 0075 8,663.18 041025 N 0075 0076 12,881.17 041125 N 0076 0077 5,032.02 041425 N 0077 0078 2,270.09 041525 N 0078 0079 10,899.29 041625 N 0079 0080 9,223.74 041725 N 0080 0082 1,801.05 042525 N 0082 102,606.76 TOTAL THIS ESTIMATE 499,451.13 TOTAL PREVIOUS ESTIMATE 602,057.89 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 05/20/25 EST. NO. 003 TIME 03:57 PM R.E. NAME: HIGGINS KYLE 02-1K4004 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- LABOR COMPLIANCE VIOLATION DEDUCT LTTR 4/25 -10,000.00 002 0.00 -10,000.00 TOTAL DEDUCTIONS 0.00 -10,000.00 PROGRAM CAS145 PAGE 1 DATE 05/20/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 02-1K4004 TIME 03:57 PM ESTIMATE NO. 003 BID OPENING 06/19/24 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/20/25 R.E. NAME: HIGGINS KYLE DATE OF THIS ESTIMATE 05/20/25 LOCATION RERUN PROGRESS ESTIMATE 02-SIS-0-0.0 ----------------------- ROBERT J FRANK CONSTRUCTION SECURITY MEASURES AT MAINTENANCE STATIONS 2806 TARMAC RD 22 MAINTENANCE STATIONS IN DISTRICT 2 REDDING CA 96003 SCOPE OF WORK INCLUDES INSTALL OF FENCING DIR'S EMERGENCY L.B. FED. AID NO. N O N E PAVEMENT REPAIRS ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 PAVEMENT REPAIRS (BOND PREMIUM) LS 17,475.0000 17,475.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 05/20/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 02-1K4004 TIME 03:57 PM ESTIMATE NO. 003 BID OPENING 06/19/24 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/20/25 R.E. NAME: HIGGINS KYLE DATE OF THIS ESTIMATE 05/20/25 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 102,606.76 602,057.89 SUBTOTAL AMOUNT EARNED 102,606.76 602,057.89 ORIGINAL CONTRACT AMOUNT 17,475.00 TOTAL WORK COMPLETED 102,606.76 602,057.89 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 -10,000.00 TOTAL 102,606.76 592,057.89 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 02/25/25 180 01/22/25 01/22/25 10/24/25 74 11 0 0 22% 41% PROGRESS IS SATISFACTORY HIGGINS KYLE RESIDENT ENGINEER