PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 08/21/06 EST. NO.06 TIME 02:38 PM R.E. NAME: PASCAL, ANTHONY 02-381114 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0006 1,121.45 E.W. @ F.A.(+) 050206 N 004 0 0008 1,688.50 052606 N 006 0 0013 625.22 042606 N TSI003 0015 969.94 060206 N 012 0 0016 376.83 062706 N 013 0 0018 1,053.36 062806 N 015 0 0021 709.03 062906 N 014A 0 003 0003 372.60 E.W. @ F.A.(+) 053106 N 008 0 0004 78.20 060206 N 003 0 0007 1,134.38 060206 N 006 0 8,129.51 TOTAL THIS ESTIMATE 67,467.81 TOTAL PREVIOUS ESTIMATE 75,597.32 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 08/21/06 EST. NO.06 TIME 02:38 PM R.E. NAME: PASCAL, ANTHONY 02-381114 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- EQUAL EMPLOYMENT OPPORTUNITY NON-SUBM FHWA 1391 -10,000.00 06 -10,000.00 -10,000.00 LABOR COMPLIANCE VIOLATION PER LTR DATED 06/06 -1,000.00 04 0.00 -1,000.00 OVERBID ITEMS OVERBID ITEM NO. 032 -78,300.00 03 0.00 -78,300.00 TOTAL DEDUCTIONS -10,000.00 -89,300.00 PROGRAM CAS145 PAGE 1 DATE 08/21/06 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 02-381114 TIME 02:38 PM ESTIMATE NO. 06 BID OPENING 10/19/05 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 08/18/06 R.E. NAME: PASCAL, ANTHONY DATE OF THIS ESTIMATE 08/21/06 LOCATION PROGRESS ESTIMATE 02-SIS-5-R11.4/R16.0 ----------------- J F SHEA CONSTRUCTION INC IN SISKIYOU COUNTY NEAR P O BOX 494519 MOUNT SHASTA FROM 0.4 KM NORTH OF REDDING CA 960494519 LASSEN LANE OVERCROSSING TO BLACK BUTTE OVERHEAD FED. AID NO. ACIM-005 -9(164)E REHABILITATE EXISTING PAVEMENT ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 PROGRESS SCHEDULE (CRITICAL PATH METHOD) LS 9,000.0000 9,000.00 0.250 2,250.00 0.750 6,750.00 02 TIME-RELATED OVERHEAD WDAY 500.0000 60,000.00 21.000 10,500.00 69.000 34,500.00 03 TEMPORARY FENCE (TYPE ESA) M 8.0000 4,960.00 620.000 4,960.00 04 PREPARE STORM WATER POLLUTION LS 4,000.0000 4,000.00 0.750 3,000.00 PREVENTION PLAN 05 WATER POLLUTION CONTROL LS 8,100.0000 8,100.00 0.783 6,342.30 06 TEMPORARY CONCRETE WASHOUT FACILITY EA 2,600.0000 2,600.00 0.800 2,080.00 07 CONSTRUCTION AREA SIGNS LS 117,000.0000 117,000.00 0.190 22,230.00 0.895 104,715.00 S) 08 TRAFFIC CONTROL SYSTEM LS 174,000.0000 174,000.00 0.158 27,492.00 0.580 100,920.00 S) 09 TRAFFIC CONTROL SURVEILLANCE LS 103,684.0000 103,684.00 0.100 10,368.40 0.850 88,131.40 S) 10 TEMPORARY TRAFFIC STRIPE (TAPE) M 4.5000 125,100.00 6,305.000 28,372.50 6,305.000 28,372.50 S) 11 TEMPORARY PAVEMENT MARKING (TAPE) M2 75.0000 30,750.00 35.100 2,632.50 93.600 7,020.00 S) 12 CHANNELIZER (SURFACE MOUNTED) EA 37.0000 65,860.00 275.000 10,175.00 917.000 33,929.00 S) 13 PORTABLE CHANGEABLE MESSAGE SIGN LS 18,700.0000 18,700.00 0.163 3,048.10 0.580 10,846.00 S) 14 TEMPORARY FLASHING ARROW SIGN LS 22,000.0000 22,000.00 0.500 11,000.00 1.000 22,000.00 S) 15 TEMPORARY FLASHING BEACON LS 17,250.0000 17,250.00 0.500 8,625.00 1.000 17,250.00 S) 16 ABANDON CULVERT EA 5,400.0000 10,800.00 2.000 10,800.00 17 REMOVE MARKER (TEXT STRIP) EA 115.0000 3,565.00 31.000 3,565.00 18 REMOVE METAL BEAM GUARD RAILING M 23.0000 7,360.00 316.000 7,268.00 S) 19 REMOVE YELLOW THERMOPLASTIC TRAFFIC M 5.0000 52,000.00 0.000 0.00 S) STRIPE 20 REMOVE THERMOPLASTIC TRAFFIC STRIPE M 4.0000 10,680.00 0.000 0.00 S) 21 REMOVE THERMOPLASTIC PAVEMENT MARKING M2 87.0000 2,088.00 0.000 0.00 S) 22 REMOVE PAVEMENT MARKER EA 24.0000 21,600.00 205.000 4,920.00 640.000 15,360.00 S) PROGRAM CAS145 PAGE 2 DATE 08/21/06 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 02-381114 TIME 02:38 PM ESTIMATE NO. 06 BID OPENING 10/19/05 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 08/18/06 R.E. NAME: PASCAL, ANTHONY DATE OF THIS ESTIMATE 08/21/06 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 23 REMOVE ROADSIDE SIGN EA 87.0000 4,263.00 13.000 1,131.00 13.000 1,131.00 24 REMOVE SIGN PANEL EA 1,725.0000 3,450.00 0.000 0.00 25 REMOVE ASPHALT CONCRETE DIKE M 52.0000 34,320.00 659.000 34,268.00 26 REMOVE INLET EA 1,150.0000 4,600.00 4.000 4,600.00 27 RESET ROADSIDE SIGN (SPECIAL METAL POST) EA 1,725.0000 3,450.00 0.000 0.00 28 MODIFY DOWNDRAIN ENTRANCE TAPER EA 920.0000 3,680.00 0.000 0.00 29 REPLACE SIGN PANEL (OVERHEAD SIGN) EA 2,200.0000 2,200.00 1.000 2,200.00 1.000 2,200.00 30 REPLACE SIGN PANEL (ROADSIDE SIGN) EA 1,500.0000 52,500.00 2.000 3,000.00 20.000 30,000.00 31 COLD PLANE ASPHALT CONCRETE PAVEMENT M2 7.0000 419,300.00 9,320.000 65,240.00 47,099.590 329,697.13 S) 32 CLEARING AND GRUBBING LS 98,000.0000 98,000.00 0.900 88,200.00 33 DEVELOP WATER SUPPLY LS 6,000.0000 6,000.00 0.130 780.00 34 ROADWAY EXCAVATION M3 52.0000 535,600.00 237.760 12,363.52 10,354.500 538,434.00 35 LEAD COMPLIANCE PLAN LS 3,000.0000 3,000.00 0.750 2,250.00 36 IMPORTED MATERIAL (SHOULDER BACKING) TONN 23.0000 74,520.00 0.000 0.00 37 STRAW (EROSION CONTROL) TONN 700.0000 12,600.00 0.000 0.00 S) 38 FIBER (EROSION CONTROL) KG 1.3000 8,190.00 0.000 0.00 S) 39 COMPOST (EROSION CONTROL) M3 345.0000 13,110.00 0.000 0.00 S) 40 PURE LIVE SEED (EROSION CONTROL) KG 200.0000 66,000.00 0.000 0.00 S) 41 COMMERCIAL FERTILIZER (EROSION CONTROL) KG 2.3000 12,420.00 0.000 0.00 S) 42 STABILIZING EMULSION (EROSION CONTROL) KG 10.0000 6,800.00 0.000 0.00 S) 43 CLASS 2 AGGREGATE BASE M3 69.0000 262,200.00 3,997.640 275,837.16 44 SEAL RANDOM CRACKS LNKM 4,600.0000 6,900.00 1.600 7,360.00 1.600 7,360.00 45 REPLACE ASPHALT CONCRETE SURFACING M3 380.0000 387,600.00 430.270 163,502.60 960.240 364,891.20 46 ASPHALT CONCRETE (TYPE A) TONN 117.0000 4,516,200.00 2,739.480 320,519.16 5,376.310 629,028.27 47 ASPHALT CONCRETE (TYPE A, 37.5-MM TONN 118.0000 2,773,000.00 3,402.440 401,487.92 19,562.550 2,308,380.90 MAXIMUM GRADING) 48 PLACE ASPHALT CONCRETE DIKE M 6.0000 10,080.00 0.000 0.00 49 PLACE ASPHALT CONCRETE (MISCELLANEOUS M2 8.5000 168,300.00 7,914.000 67,269.00 7,914.000 67,269.00 AREA) PROGRAM CAS145 PAGE 3 DATE 08/21/06 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 02-381114 TIME 02:38 PM ESTIMATE NO. 06 BID OPENING 10/19/05 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 08/18/06 R.E. NAME: PASCAL, ANTHONY DATE OF THIS ESTIMATE 08/21/06 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 50 SHOULDER RUMBLE STRIP STA 138.0000 24,840.00 32.100 4,429.80 32.100 4,429.80 (AC, GROUND-IN INDENTATIONS) 51 CRACK EXISTING CONCRETE PAVEMENT M2 1.2000 47,880.00 9,118.530 10,942.24 39,324.220 47,189.06 52 MINOR CONCRETE (MINOR STRUCTURE) M3 1,800.0000 5,220.00 2.930 5,274.00 F) 53 ROADSIDE SIGN (METAL POST) EA 520.0000 21,320.00 14.000 7,280.00 14.000 7,280.00 54 ROADSIDE SIGN - ONE POST EA 520.0000 5,200.00 0.000 0.00 55 600 MM CORRUGATED STEEL PIPE M 736.0000 61,824.00 83.300 61,308.80 (2.77 MM THICK) 56 FLUSH 80 MM EDGE DRAIN M 4.1500 39,923.00 340.000 1,411.00 7,812.240 32,420.80 57 80 MM PLASTIC PIPE (EDGE DRAIN) M 94.3000 609,178.00 6,158.000 580,699.40 6,158.000 580,699.40 58 100 MM PLASTIC PIPE (EDGE DRAIN) M 103.5000 180,090.00 1,740.000 180,090.00 1,740.000 180,090.00 59 80 MM PLASTIC PIPE (EDGE DRAIN OUTLET) M 103.5000 137,655.00 1,480.700 153,252.45 1,480.700 153,252.45 60 100 MM PLASTIC PIPE M 126.5000 29,095.00 233.400 29,525.10 233.400 29,525.10 (EDGE DRAIN OUTLET) 61 PULL BOX (TYPE 3 1/2 T) EA 230.0000 8,740.00 0.000 0.00 62 900 MM CORRUGATED STEEL PIPE INLET M 1,308.0000 5,232.00 3.950 5,166.60 (2.77 MM THICK) 63 ROCK SLOPE PROTECTION M3 575.0000 109,250.00 -4.320 -2,484.00 216.000 124,200.00 (75 MM, METHOD B) 64 ROCK SLOPE PROTECTION (LIGHT, METHOD B) M3 460.0000 16,560.00 35.300 16,238.00 65 ROCK SLOPE PROTECTION FABRIC M2 3.0000 273.00 90.600 271.80 66 MINOR CONCRETE (MISCELLANEOUS M3 1,130.0000 14,690.00 16.020 18,102.60 CONSTRUCTION) 67 MINOR CONCRETE (WEED BARRIER) M3 1,377.0000 275,400.00 0.000 0.00 68 MISCELLANEOUS IRON AND STEEL KG 6.0000 3,702.00 617.000 3,702.00 F) 69 DELINEATOR (CLASS 2) EA 52.0000 2,028.00 0.000 0.00 70 HIGHWAY POST MARKER EA 75.0000 675.00 0.000 0.00 71 MARKER (CULVERT) EA 64.0000 960.00 0.000 0.00 72 OBJECT MARKER (TYPE L-1) EA 64.0000 256.00 0.000 0.00 73 METAL BEAM GUARD RAILING M 115.0000 33,350.00 0.000 0.00 S) 74 DOUBLE METAL BEAM GUARD RAILING M 161.0000 8,694.00 0.000 0.00 S) (WOOD POST) 75 TRANSITION RAILING (TYPE WB) EA 4,025.0000 12,075.00 0.000 0.00 S) 76 TERMINAL ANCHOR ASSEMBLY (TYPE SFT) EA 805.0000 3,220.00 0.000 0.00 S) PROGRAM CAS145 PAGE 4 DATE 08/21/06 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 02-381114 TIME 02:38 PM ESTIMATE NO. 06 BID OPENING 10/19/05 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 08/18/06 R.E. NAME: PASCAL, ANTHONY DATE OF THIS ESTIMATE 08/21/06 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 77 ALTERNATIVE FLARED TERMINAL SYSTEM EA 2,185.0000 4,370.00 0.000 0.00 S) 78 CRASH CUSHION (TYPE CAT) EA 6,325.0000 18,975.00 0.000 0.00 S) 79 CRASH CUSHION (TYPE CAT) BACKUP EA 575.0000 1,725.00 0.000 0.00 S) 80 THERMOPLASTIC PAVEMENT MARKING M2 104.0000 3,016.00 0.000 0.00 S) 81 THERMOPLASTIC TRAFFIC STRIPE M 0.7000 25,480.00 0.000 0.00 S) (SPRAYABLE) 82 PAVEMENT MARKER EA 15.0000 28,800.00 0.000 0.00 S) (RETROREFLECTIVE-RECESSED) 83 LIGHTING (AREA) LS 200,000.0000 200,000.00 0.318 63,600.00 0.921 184,200.00 S) 84 LIGHTING (LOCATION 1) LS 75,000.0000 75,000.00 0.177 13,275.00 0.846 63,450.00 S) 85 LIGHTING (LOCATION 2) LS 58,000.0000 58,000.00 0.261 15,138.00 0.647 37,526.00 S) 86 LIGHTING (LOCATION 3) LS 62,000.0000 62,000.00 0.145 8,990.00 S) 87 TRAFFIC MONITORING STATION (COUNT) LS 29,000.0000 29,000.00 0.109 3,161.00 S) 88 ROADSIDE WEATHER INFORMATION SYSTEM LS 19,000.0000 19,000.00 0.000 0.00 S) PROGRAM CAS145 PAGE 5 DATE 08/21/06 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 02-381114 TIME 02:38 PM ESTIMATE NO. 06 BID OPENING 10/19/05 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 08/18/06 R.E. NAME: PASCAL, ANTHONY DATE OF THIS ESTIMATE 08/21/06 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION 2,242,845.69 6,758,613.27 ADJUSTMENT OF COMPENSATION 0.00 -15,099.09 EXTRA WORK 8,129.51 90,696.41 SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION 2,250,975.20 6,834,210.59 89 MOBILIZATION LS 900,000.0000 900,000.00 0.050 45,000.00 1.000 900,000.00 ORIGINAL CONTRACT AMOUNT 13,442,076.00 TOTAL WORK COMPLETED 2,295,975.20 7,734,210.59 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS -10,000.00 -89,300.00 TOTAL 2,285,975.20 7,644,910.59 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE MAXIMUM CONTRACT OVERBID VALUE PRICE AMOUNT 032 CLEARING AND GRUBBING 11,000.00 98,000.00 87,000.00 DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 01/10/06 120 04/19/06 01/25/06 08/20/06 69 74 -3 0 57% 59% PROGRESS IS SATISFACTORY PASCAL, ANTHONY RESIDENT ENGINEER PROGRAM CAS145 DATE 08/21/06