PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 07/23/10 EST. NO.01 TIME 10:52 AM R.E. NAME: PETERSON, DALE 03-0F7704 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- *** THERE ARE NO EXTRA WORK PAYMENTS THIS ESTIMATE *** PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 07/23/10 EST. NO.01 TIME 10:52 AM R.E. NAME: PETERSON, DALE 03-0F7704 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 07/23/10 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 03-0F7704 TIME 10:52 AM ESTIMATE NO. 01 BID OPENING 03/30/10 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 07/20/10 R.E. NAME: PETERSON, DALE DATE OF THIS ESTIMATE 07/23/10 LOCATION RERUN PROGRESS ESTIMATE 03-BUT-191-8.1/8.2 ----------------------- MEYERS EARTHWORK INC IN BUTTE, EL DORADO AND PLACER P O BOX 493730 COUNTIES AT VARIOUS LOCATIONS REDDING CA 96049 FED. AID NO. HSST-000C(314)E ,P-000C(314)E INSTALL METAL BEAM GUARD RAIL ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 SMALL BUSINESS UTILIZATION REPORT EA 250.0000 250.00 0.000 0.00 02 CONSTRUCTION SITE MANAGEMENT LS 7,200.0000 7,200.00 0.133 957.60 0.133 957.60 03 PREPARE WATER POLLUTION CONTROL LS 1,800.0000 1,800.00 0.850 1,530.00 0.850 1,530.00 PROGRAM 04 TEMPORARY CONCRETE WASHOUT FACILITY EA 1,800.0000 7,200.00 0.533 959.40 0.533 959.40 05 STREET SWEEPING LS 15,000.0000 15,000.00 0.067 1,005.00 0.067 1,005.00 06 CONSTRUCTION AREA SIGNS LS 7,500.0000 7,500.00 0.453 3,397.50 0.453 3,397.50 07 TRAFFIC CONTROL SYSTEM LS 55,000.0000 55,000.00 0.133 7,315.00 0.133 7,315.00 08 PORTABLE CHANGEABLE MESSAGE SIGN LS 12,000.0000 12,000.00 0.133 1,596.00 0.133 1,596.00 09 REMOVE ASPHALT CONCRETE DIKE LF 5.0000 4,400.00 340.000 1,700.00 340.000 1,700.00 10 MODIFY METAL BEAM GUARD RAILING LF 13.0000 3,900.00 0.000 0.00 11 MODIFY METAL BEAM GUARD RAILING LF 13.0000 4,550.00 0.000 0.00 (7' POST) 12 MODIFY METAL BEAM GUARD RAILING LF 13.0000 5,200.00 0.000 0.00 (SPECIAL) 13 COLD PLANE ASPHALT CONCRETE PAVEMENT SQYD 12.0000 11,640.00 0.000 0.00 14 CLEARING AND GRUBBING LS 15,000.0000 15,000.00 0.000 0.00 15 ROADWAY EXCAVATION CY 250.0000 2,500.00 10.000 2,500.00 10.000 2,500.00 16 LEAD COMPLIANCE PLAN LS 4,000.0000 4,000.00 1.000 4,000.00 1.000 4,000.00 17 ASBESTOS COMPLIANCE PLAN LS 4,000.0000 4,000.00 1.000 4,000.00 1.000 4,000.00 18 DUST CONTROL PLAN LS 1,000.0000 1,000.00 1.000 1,000.00 1.000 1,000.00 19 HOT MIX ASPHALT (TYPE A) TON 250.0000 42,500.00 0.000 0.00 20 PLACE HOT MIX ASPHALT DIKE (TYPE A) LF 6.0000 5,280.00 0.000 0.00 21 DELINEATOR (CLASS 1) EA 50.0000 600.00 0.000 0.00 22 DELINEATOR (CLASS 2) EA 50.0000 350.00 0.000 0.00 PROGRAM CAS145 PAGE 2 DATE 07/23/10 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 03-0F7704 TIME 10:52 AM ESTIMATE NO. 01 BID OPENING 03/30/10 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 07/20/10 R.E. NAME: PETERSON, DALE DATE OF THIS ESTIMATE 07/23/10 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 23 OBJECT MARKER (TYPE L-1) EA 50.0000 100.00 0.000 0.00 24 METAL BEAM GUARD RAILING LF 46.0000 105,800.00 1,493.000 68,678.00 1,493.000 68,678.00 25 METAL BEAM GUARD RAILING (SPECIAL) LF 46.0000 26,680.00 32.000 1,472.00 32.000 1,472.00 26 METAL BEAM GUARD RAILING (7' POST) LF 25.0000 8,750.00 0.000 0.00 27 ALTERNATIVE IN-LINE TERMINAL SYSTEM EA 3,600.0000 7,200.00 0.000 0.00 28 ALTERNATIVE FLARED TERMINAL SYSTEM EA 2,400.0000 7,200.00 1.000 2,400.00 1.000 2,400.00 29 PAINT TRAFFIC STRIPE (2-COAT) LF 4.0000 2,320.00 0.000 0.00 PROGRAM CAS145 PAGE 3 DATE 07/23/10 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 03-0F7704 TIME 10:52 AM ESTIMATE NO. 01 BID OPENING 03/30/10 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 07/20/10 R.E. NAME: PETERSON, DALE DATE OF THIS ESTIMATE 07/23/10 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 102,510.50 102,510.50 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 0.00 0.00 SUBTOTAL AMOUNT EARNED 102,510.50 102,510.50 ORIGINAL CONTRACT AMOUNT 368,920.00 TOTAL WORK COMPLETED 102,510.50 102,510.50 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 102,510.50 102,510.50 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 06/09/10 30 07/15/10 06/24/10 08/26/10 17 1 0 0 28% 57% PROGRESS IS SATISFACTORY PER RE REQUEST PETERSON, DALE RESIDENT ENGINEER PROGRAM CAS145 DATE 07/23/10