PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 02/21/25 EST. NO. 009 TIME 09:05 AM R.E. NAME: JOHNSON, JEFF 03-2H6214 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0241 14,832.05 E.W. @ F.A.(+) 091324 N 0211.0 0461 3,884.23 121024 N 0429.0 0462 3,884.23 121124 N 0430.0 0463 3,461.09 012325 N 0431.0 0464 11,281.58 110524 N 0432.0 0465 5,546.57 092624 N 0433.0 0466 3,139.21 112124 N 0434.0 0467 12,738.08 120524 N 0435.0 0468 22,892.10 083024 N 0436.0 81,659.14 TOTAL THIS ESTIMATE 5,161,373.49 TOTAL PREVIOUS ESTIMATE 5,243,032.63 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 02/21/25 EST. NO. 009 TIME 09:05 AM R.E. NAME: JOHNSON, JEFF 03-2H6214 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- LABOR COMPLIANCE VIOLATION DEDUCT LETTER 7/24 -2,000.00 002 DEDUCT LETTER 8/24 -8,000.00 003 DEDUCT LETTER 10/24 -10,000.00 005 DEDUCT LETTER 12/24 -1,000.00 007 RETURN LETTER 8/24 8,000.00 007 RETURN LETTER 10/24 10,000.00 008 RETURN LETTER 12/24 1,000.00 008 0.00 -2,000.00 TOTAL DEDUCTIONS 0.00 -2,000.00 PROGRAM CAS145 PAGE 1 DATE 02/21/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 03-2H6214 TIME 09:05 AM ESTIMATE NO. 009 BID OPENING 04/01/24 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 02/20/25 R.E. NAME: JOHNSON, JEFF DATE OF THIS ESTIMATE 02/21/25 LOCATION PROGRESS ESTIMATE 03-NEV-20-301.0/30.1 ----------------- GRANITE CONSTRUCTION COMPANY MOBILIZATION, STABILIZE SLOPE, PLACE RSP PO BOX 742478 REMOVE SLIDE MATERIAL, TRAFFIC CONTROL, LOS ANGELES, CA 90074 AND INCIDENTAL WORK. DIR'S EMERGENCY L.B. FED. AID NO. N O N E WHITE CLOUD SLIP OUT ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 WHITE CLOUD SLIP OUT (BOND PREMIUM) LS 7,700.0000 7,700.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 02/21/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 03-2H6214 TIME 09:05 AM ESTIMATE NO. 009 BID OPENING 04/01/24 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 02/20/25 R.E. NAME: JOHNSON, JEFF DATE OF THIS ESTIMATE 02/21/25 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 81,659.14 5,243,032.63 SUBTOTAL AMOUNT EARNED 81,659.14 5,243,032.63 ORIGINAL CONTRACT AMOUNT 7,700.00 TOTAL WORK COMPLETED 81,659.14 5,243,032.63 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 -2,000.00 TOTAL 81,659.14 5,241,032.63 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 06/06/24 200 05/03/24 05/03/24 06/13/25 122 77 0 0 75% 61% PROGRESS IS SATISFACTORY JOHNSON, JEFF RESIDENT ENGINEER