PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 11/20/20 EST. NO. 013 TIME 11:32 AM R.E. NAME: SUSHMA LEE 03-3F5504 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 003 0003 1,000.00 E.W. @ F.A.(+) 093020 N 0055.0 004 0039 284.50 E.W. @ F.A.(+) 073019 Y 0045.0 0040 284.50 073119 N 0046.0 0041 962.28 080319 N 0047.0 0042 855.58 080419 N 0048.0 0043 786.32 080919 N 0049.0 0044 1,273.10 081019 N 0050.0 0045 224.66 081319 N 0051.0 0046 112.38 081419 N 0052.0 0047 449.33 081619 N 0053.0 0048 337.04 081719 N 0054.0 0049 374.44 080219 N 055 0 0050 1,347.98 080719 N 056 0 0051 589.84 081119 N 057 0 0052 712.98 082719 N 058 0 0053 524.22 090619 N 059 0 0054 599.10 090919 N 060 0 10,718.25 TOTAL THIS ESTIMATE 361,662.92 TOTAL PREVIOUS ESTIMATE 372,381.17 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 11/20/20 EST. NO. 013 TIME 11:32 AM R.E. NAME: SUSHMA LEE 03-3F5504 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 11/20/20 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 03-3F5504 TIME 11:32 AM ESTIMATE NO. 013 BID OPENING 10/16/18 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 11/20/20 R.E. NAME: SUSHMA LEE DATE OF THIS ESTIMATE 11/20/20 LOCATION PROGRESS ESTIMATE 03-YOL-275-13.0/ .0 ----------------- GOLDEN STATE BRIDGE, INC. IN WEST SACRAMENTO AT SACRAMENTO 3701 MALLARD DRIVE RIVER BRIDGE 22-0021 BENICIA CA 945101195 FED. AID NO. B1NH-P275(6)E SUB-NAV PROTECTION ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 LEAD COMPLIANCE PLAN LS 4,000.0000 4,000.00 1.000 4,000 002 PROGRESS SCHEDULE (CRITICAL PATH METHOD) LS 15,000.0000 15,000.00 0.750 11,250 003 TIME-RELATED OVERHEAD (LS) LS 1,185,000.0000 1,185,000.00 0.030 35,550.00 0.970 1,149,450 004 JOB SITE MANAGEMENT LS 70,000.0000 70,000.00 0.910 63,700 005 PREPARE WATER POLLUTION CONTROL PROGRAM LS 4,000.0000 4,000.00 0.250 1,000.00 1.000 4,000 006 WATER QUALITY SAMPLING AND ANALYSIS DAY EA 450.0000 108,000.00 3.000 1,350.00 178.000 80,100 007 WATER QUALITY MONITORING REPORT EA 300.0000 72,000.00 3.000 900.00 178.000 53,400 008 WATER QUALITY ANNUAL REPORT EA 1,250.0000 3,750.00 1.000 1,250 009 TREATED WOOD WASTE LB 0.1000 168,000.00 1,680,000.060 168,000 010 CONTRACTOR-SUPPLIED BIOLOGIST (LS) LS 75,000.0000 75,000.00 0.150 11,250.00 0.970 72,750 011 NATURAL RESOURCE PROTECTION PLAN LS 7,500.0000 7,500.00 1.000 7,500 012 FIBERGLASS REINFORCED GRATING SQFT 24.0000 54,720.00 2,280.000 54,720 (F) 013 FURNISH 24" STEEL PIPE PILING LF 175.0000 1,680,000.00 9,600.000 1,680,000 014 FURNISH 36" STEEL PIPE PILING LF 335.0000 294,800.00 880.000 294,800 015 INSTALL 24" STEEL PIPE PILE EA 15,000.0000 1,440,000.00 96.000 1,440,000 016 INSTALL 36" STEEL PIPE PILE EA 7,500.0000 60,000.00 8.000 60,000 017 STRUCTURAL STEEL (BRIDGE) LB 16.0000 3,437,600.00 214,850.000 3,437,600 (F) 018 PLASTIC LUMBER MFBM 9,999.0000 559,944.00 56.000 559,944 (F) 019 SPOT BLAST CLEAN AND PAINT UNDERCOAT SQFT 650.0000 2,600.00 0.000 0 020 BRIDGE REMOVAL (PORTION) LS 410,000.0000 410,000.00 1.000 410,000 021 MISCELLANEOUS METAL (BRIDGE) LB 19.0000 241,034.00 12,686.000 241,034 (F) 022 ELECTRICAL WORK LS 75,000.0000 75,000.00 0.200 15,000.00 1.000 75,000 PROGRAM CAS145 PAGE 2 DATE 11/20/20 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 03-3F5504 TIME 11:32 AM ESTIMATE NO. 013 BID OPENING 10/16/18 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 11/20/20 R.E. NAME: SUSHMA LEE DATE OF THIS ESTIMATE 11/20/20 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION 65,050.00 9,868,498.01 ADJUSTMENT OF COMPENSATION 0.00 16,265.82 EXTRA WORK 10,718.25 356,115.35 SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION 75,768.25 10,240,879.18 023 MOBILIZATION LS 1,000,000.0000 1,000,000.00 1.000 1,000,000 ORIGINAL CONTRACT AMOUNT 10,967,948.00 TOTAL WORK COMPLETED 75,768.25 11,240,879.18 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 75,768.25 11,240,879.18 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 12/17/18 170 03/18/19 03/18/19 11/23/20 169 253 0 0 98% 99% PROGRESS IS SATISFACTORY SUSHMA LEE RESIDENT ENGINEER PROGRAM CAS145 DATE 11/20/20