PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 09/30/13 EST. NO.01 TIME 10:53 AM R.E. NAME: CHOHAN, MOHAN 03-4F0104 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0001 3,905.14 E.W. @ F.A.(+) 081213 N 1 0 0002 6,690.49 081313 N 2 0 0003 2,696.11 081413 N 3 0 0004 3,789.31 081613 N 5 0 0005 4,778.44 081913 N 6 0 0006 4,952.66 082013 N 7 0 0007 3,273.72 082113 N 8 0 0008 4,804.85 082213 N 9 0 0009 5,199.79 082313 N 10 0 0010 5,498.83 082613 N 11 0 0011 4,189.41 082713 N 12 0 0012 4,682.56 082813 N 13 0 0013 5,717.06 082913 N 14 0 0014 3,575.13 083013 N 15 0 0016 4,926.64 090313 N 16 0 0017 5,036.98 090413 N 17 0 0018 3,784.97 090513 N 18 0 0019 4,850.78 090613 N 19 0 0020 3,303.28 090913 N 20 0 0021 4,683.02 091013 N 21 0 0022 2,365.94 081513 N 04 0 0023 4,724.77 091113 N 22 0 0024 3,984.57 091213 N 23 0 0025 4,280.63 091313 N 24 0 0026 3,030.71 091613 N 25 0 0027 1,960.74 092613 N 26 0 0028 1,928.23 091813 N 27 0 0029 2,849.99 091913 N 28 0 0030 3,468.40 092013 N 29 0 0031 2,330.20 092313 N 30 0 0032 1,761.16 092413 N 31 0 123,024.51 TOTAL THIS ESTIMATE 0.00 TOTAL PREVIOUS ESTIMATE 123,024.51 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 09/30/13 EST. NO.01 TIME 10:53 AM R.E. NAME: CHOHAN, MOHAN 03-4F0104 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 09/30/13 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 03-4F0104 TIME 10:53 AM ESTIMATE NO. 01 BID OPENING 08/01/13 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/24/13 R.E. NAME: CHOHAN, MOHAN DATE OF THIS ESTIMATE 09/30/13 LOCATION RERUN PROGRESS ESTIMATE 03-VAR ----------------------- STUDEBAKER BROWN ELECTRIC, INC IN EL DORADO, NEVADA, PLACER AND 2008 OPPORTUNITY DRIVE, #140 SACRAMENTO COUNTIES, ON VARIOUS ROUTES AND ROSEVILLE, CA 95678 AT VARIOUS POST MILES DIR'S EMERGENCY L.B. FED. AID NO. NHS- ( ) REPLACE DAMAGED WIRING FOR LIGHTING ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 REPAIR STORM DAMAGE (BOND PREMIUM) LS 21,832.0000 21,832.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 09/30/13 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 03-4F0104 TIME 10:53 AM ESTIMATE NO. 01 BID OPENING 08/01/13 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/24/13 R.E. NAME: CHOHAN, MOHAN DATE OF THIS ESTIMATE 09/30/13 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 123,024.51 123,024.51 SUBTOTAL AMOUNT EARNED 123,024.51 123,024.51 ORIGINAL CONTRACT AMOUNT 21,832.00 TOTAL WORK COMPLETED 123,024.51 123,024.51 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 123,024.51 123,024.51 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 09/04/13 100 08/12/13 08/12/13 01/03/14 31 0 0 0 16% 31% PROGRESS IS SATISFACTORY PER RE REQUEST CHOHAN, MOHAN RESIDENT ENGINEER PROGRAM CAS145 DATE 09/30/13