PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 02/06/20 EST. NO. 022 TIME 09:45 AM R.E. NAME: JOHNSON, RYAN 03-4H8304 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 1920 2,142.47 E.W. @ F.A.(+) 051519 N 1706.0 1994 2,365.81 061819 N 1795.0 2082 49,639.63 060619 N 1877.0 2184 112.44 111719 N 1964.0 2185 112.44 111819 N 1965.0 2186 112.44 111919 N 1966.0 2187 112.44 112019 N 1967.0 2188 112.44 112119 N 1968.0 2189 112.44 112219 N 1969.0 2190 112.44 112319 N 1970.0 2191 112.44 112419 N 1971.0 2192 112.44 112519 N 1972.0 2193 112.44 112619 N 1973.0 2194 112.44 112719 N 1974.0 2195 112.44 112819 N 1975.0 2196 112.44 112919 N 1976.0 2197 112.44 113019 N 1977.0 2198 112.44 120119 N 1978.0 2199 112.44 120219 N 1979.0 2200 112.44 120319 N 1980.0 2201 112.44 120419 N 1981.0 2202 112.44 120519 N 1982.0 2203 446.68 120619 N 1983.0 56,730.95 TOTAL THIS ESTIMATE 21,006,298.58 TOTAL PREVIOUS ESTIMATE 21,063,029.53 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 02/06/20 EST. NO. 022 TIME 09:45 AM R.E. NAME: JOHNSON, RYAN 03-4H8304 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- LABOR COMPLIANCE VIOLATION PER LTR DATED 2/19 -10,000.00 001 PER LTR DATED 3/8/19 -10,000.00 002 PER LTR DATED 3/19 -10,000.00 003 PER LTR DATED 4/5/19 -10,000.00 004 RETURN DEDUCT 2/19 10,000.00 005 RETURN DEDUCT 3/19 10,000.00 005 RETURN DEDUCT 3/19 10,000.00 005 PER LTR DATED 5/19 -10,000.00 006 PER LTR DATED 6/7/19 -7,000.00 007 RETURN DEDUCT 4/19 10,000.00 007 PER LTR DATED 6/19 -5,000.00 008 PER LTR DATED 7/2/19 -4,000.00 009 RETURN DEDUCT 5/19 10,000.00 009 PER LTR DATED 7/19 -10,000.00 010 RETURN DEDUCT 6/19 5,000.00 010 RETURN DEDUCT 7/19 4,000.00 010 PER LTR DATED 8/19 -10,000.00 012 RETURN DEDUCT 6/7/19 7,000.00 012 RETURN DEDUCT 7/19 10,000.00 012 RETURN DEDUCT 8/19 10,000.00 013 PER LTR DATED 12/19 -8,000.00 020 PER LTR DATED 1/20 -3,000.00 021 RETURN DEDUCT 12/19 8,000.00 022 RETURN DEDUCT 1/20 3,000.00 022 11,000.00 0.00 TOTAL DEDUCTIONS 11,000.00 0.00 PROGRAM CAS145 PAGE 1 DATE 02/06/20 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 03-4H8304 TIME 09:45 AM ESTIMATE NO. 022 BID OPENING 11/10/18 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 02/06/20 R.E. NAME: JOHNSON, RYAN DATE OF THIS ESTIMATE 02/06/20 LOCATION PROGRESS ESTIMATE 03-BUT-32-0.0 ----------------- BALDWIN CONTRACTING CO., INC. IN BUTTE AND PLUMAS DBA KNIFE RIVER CONSTRUCTION COUNTIES AT 1764 SKYWAY VARIOUS LOCATIONS CHICO, CA 95928 DIR'S EMERGENCY F.A. FED. AID NO. N O N E REMOVE/CHIP TREES AND DEBRIS ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 REMOVE/CHIP TREES & DEBRIS(BOND PREMIUM) LS 49,600.0000 49,600.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 02/06/20 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 03-4H8304 TIME 09:45 AM ESTIMATE NO. 022 BID OPENING 11/10/18 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 02/06/20 R.E. NAME: JOHNSON, RYAN DATE OF THIS ESTIMATE 02/06/20 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 -256,165.50 EXTRA WORK 56,730.95 21,319,195.03 SUBTOTAL AMOUNT EARNED 56,730.95 21,063,029.53 ORIGINAL CONTRACT AMOUNT 49,600.00 TOTAL WORK COMPLETED 56,730.95 21,063,029.53 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 11,000.00 0.00 TOTAL 67,730.95 21,063,029.53 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 01/09/19 200 11/12/18 11/12/18 07/29/20 0 0 0 0 96% 0% PROGRESS IS SATISFACTORY JOHNSON, RYAN RESIDENT ENGINEER PROGRAM CAS145 DATE 02/06/20