PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 03/21/25 EST. NO. 013 TIME 10:09 AM R.E. NAME: TECLE, DANIEL 03-4J6804 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- *** THERE ARE NO EXTRA WORK PAYMENTS THIS ESTIMATE *** PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 03/21/25 EST. NO. 013 TIME 10:09 AM R.E. NAME: TECLE, DANIEL 03-4J6804 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- EQUAL EMPLOYMENT OPPORTUNITY MSSG CEM-2402 -10,000.00 011 RTN CEM-2402 10,000.00 013 10,000.00 0.00 LABOR COMPLIANCE VIOLATION DEDUCT LTTR 9/23 -10,000.00 002 DEDUCT LTTR 10/23 -10,000.00 003 DEDUCT LTTR 11/23 -10,000.00 004 RTN LTTR 9/23 10,000.00 004 RTN LTTR 10/23 10,000.00 004 DEDUCT LTTR 1/24 -2,000.00 005 RTN LTTR 11/23 10,000.00 005 DEDUCT LTTR 2/24 -1,000.00 006 RTN LTTR 1/24 2,000.00 006 DEDUCT LTTR 3/24 -1,000.00 008 RTN LTTR 2/24 1,000.00 008 RTN LTTR 3/24 1,000.00 010 0.00 0.00 TOTAL DEDUCTIONS 10,000.00 0.00 PROGRAM CAS145 PAGE 1 DATE 03/21/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 03-4J6804 TIME 10:09 AM ESTIMATE NO. 013 BID OPENING 04/01/23 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/06/24 R.E. NAME: TECLE, DANIEL DATE OF THIS ESTIMATE 03/21/25 LOCATION SEMI-FINAL ESTIMATE 03-YOL-128-10.0/6.0 ------------------- TEICHERT & SON INC. DBA SITE PREP, EARTHWORK, ROCK SLOPE PROTECTIO TEICHERT CONSTRUCTION N, TEMP SHORING SYSTEM, SOLDIER PILE TIE PO BOX 13557 BACK WALL, HMA DIKE, GUARDRAIL SACRAMENTO, CA 95853 DIR'S EMERGENCY F.A. FED. AID NO. N O N E 128 SLIPOUTS ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 128 SLIPOUTS (BOND PREMIUM) LS 3,000.0000 3,000.00 1.000 3,000 PROGRAM CAS145 PAGE 2 DATE 03/21/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 03-4J6804 TIME 10:09 AM ESTIMATE NO. 013 BID OPENING 04/01/23 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/06/24 R.E. NAME: TECLE, DANIEL DATE OF THIS ESTIMATE 03/21/25 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 3,000.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 0.00 4,865,311.18 SUBTOTAL AMOUNT EARNED 0.00 4,868,311.18 ORIGINAL CONTRACT AMOUNT 3,000.00 TOTAL WORK COMPLETED 0.00 4,868,311.18 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 10,000.00 0.00 TOTAL 10,000.00 4,868,311.18 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN JOB COM- WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR PLETED ON DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 05/11/23 90 04/01/23 04/01/23 12/06/24 247 174 0 0 100% 100% TECLE, DANIEL RESIDENT ENGINEER