PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 06/16/26 EST. NO. 002 TIME 02:52 PM R.E. NAME: SINGH, JASMANINDER 04-0P9004 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- *** THERE ARE NO EXTRA WORK PAYMENTS THIS ESTIMATE *** PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 06/16/26 EST. NO. 002 TIME 02:52 PM R.E. NAME: SINGH, JASMANINDER 04-0P9004 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 06/16/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-0P9004 TIME 02:52 PM ESTIMATE NO. 002 BID OPENING 12/10/25 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/20/26 R.E. NAME: SINGH, JASMANINDER DATE OF THIS ESTIMATE 06/16/26 LOCATION RERUN PROGRESS ESTIMATE 04-ALA-580-R41.3/44.8 ----------------------- GOLDEN STATE BRIDGE, INC. ALAMEDA COUNTY IN OAKLAND FROM 0.1 MILE 3701 MALLARD DRIVE WEST OF WEBSTER STREET UNDERCROSSING TO BENICIA CA 94510 0.1 MILE EAST OF FRUITVALE AVENUE UNDERCROSSING FED. AID NO. BFIM-5801(985)E BR REMOVAL, COL CASING, CB, COLD PLANE AC ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 LEAD COMPLIANCE PLAN LS 4,000.0000 4,000.00 0.750 3,000.00 0.750 3,000 002 LEVEL 2 CRITICAL PATH METHOD SCHEDULE LS 25,000.0000 25,000.00 0.250 6,250.00 0.250 6,250 003 TIME-RELATED OVERHEAD (WDAY) WDAY 2,000.0000 600,000.00 29.000 58,000.00 29.000 58,000 004 DISPUTE RESOLUTION BOARD ON-SITE MEETING EA 6,000.0000 42,000.00 0.000 0 005 HOURLY OFF-SITE HR 200.0000 4,000.00 0.000 0 DISPUTE-RESOLUTION-BOARD-RELATED TASKS 006 CONSTRUCTION AREA SIGNS LS 22,500.0000 22,500.00 0.500 11,250 007 TRAFFIC CONTROL SYSTEM LS 125,000.0000 125,000.00 0.097 12,125.00 0.097 12,125 008 TEMPORARY TRAFFIC STRIPE (TAPE) LF 1.5000 36,600.00 0.000 0 009 CHANNELIZER (SURFACE MOUNTED) EA 66.0000 2,376.00 0.000 0 010 TEMPORARY BARRIER SYSTEM LF 35.0000 279,300.00 0.000 0 011 TEMPORARY PEDESTRIAN ACCESS ROUTE LS 10,000.0000 10,000.00 0.000 0 012 PORTABLE CHANGEABLE MESSAGE SIGN (EA) EA 8,000.0000 96,000.00 0.000 0 013 TEMPORARY CRASH CUSHION TL-2 EA 6,000.0000 54,000.00 0.000 0 014 TEMPORARY CRASH CUSHION TL-3 EA 6,000.0000 30,000.00 0.000 0 015 TEMPORARY TRAFFIC SCREEN LF 10.0000 15,650.00 0.000 0 016 JOB SITE MANAGEMENT LS 90,000.0000 90,000.00 0.097 8,730.00 0.097 8,730 017 WATER POLLUTION CONTROL PROGRAM LS 4,000.0000 4,000.00 0.097 388.00 0.097 388 018 TEMPORARY HYDRAULIC MULCH (BONDED FIBER SQYD 3.0000 480.00 0.000 0 MATRIX) 019 TEMPORARY COVER SQYD 3.0000 2,250.00 0.000 0 020 TEMPORARY CHECK DAM LF 15.0000 900.00 0.000 0 021 TEMPORARY DRAINAGE INLET PROTECTION EA 300.0000 15,300.00 0.000 0 022 TEMPORARY FIBER ROLL LF 6.0000 2,400.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 06/16/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-0P9004 TIME 02:52 PM ESTIMATE NO. 002 BID OPENING 12/10/25 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/20/26 R.E. NAME: SINGH, JASMANINDER DATE OF THIS ESTIMATE 06/16/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 023 TEMPORARY GRAVEL BAG BERM LF 17.0000 12,750.00 0.000 0 024 TEMPORARY REINFORCED SILT FENCE LF 7.0000 2,520.00 0.000 0 025 STREET SWEEPING LS 5,000.0000 5,000.00 0.097 485.00 0.097 485 026 TEMPORARY CONCRETE WASHOUT LS 18,000.0000 18,000.00 0.000 0 027 WATER QUALITY MONITORING REPORT EA 500.0000 1,000.00 0.000 0 028 ASBESTOS COMPLIANCE PLAN LS 12,000.0000 12,000.00 0.750 9,000.00 0.750 9,000 029 REMOVE YELLOW THERMOPLASTIC TRAFFIC LF 1.0000 2,900.00 0.000 0 STRIPE (HAZARDOUS WASTE) 030 TREATED WOOD WASTE LB 0.4000 4,324.00 0.000 0 031 NOISE MONITORING LS 15,000.0000 15,000.00 0.097 1,455.00 0.097 1,455 032 CLEARING AND GRUBBING (LS) LS 25,000.0000 25,000.00 0.000 0 033 ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY CY 500.0000 13,500.00 0.000 0 DEPOSITED LEAD) 034 STRUCTURE EXCAVATION (BRIDGE) CY 325.0000 236,600.00 0.000 0 (F) 035 STRUCTURE BACKFILL (BRIDGE) CY 199.0000 134,126.00 0.000 0 (F) 036 CHECK AND TEST EXISTING IRRIGATION LS 6,500.0000 6,500.00 1.000 6,500 FACILITIES 037 OPERATE EXISTING IRRIGATION FACILITIES LS 5,786.0000 5,786.00 0.000 0 038 REMOVE IRRIGATION FACILITY LS 3,500.0000 3,500.00 1.000 3,500 039 CONTROL AND NEUTRAL CONDUCTORS LS 3,500.0000 3,500.00 0.000 0 (ARMOR-CLAD) 040 1 1/2" REMOTE CONTROL VALVE EA 1,500.0000 1,500.00 0.000 0 041 12 STATION IRRIGATION CONTROLLER (WALL EA 14,000.0000 14,000.00 0.000 0 MOUNTED) 042 2" GALVANIZED STEEL PIPE (SUPPLY LINE) LF 36.0000 720.00 0.000 0 (F) 043 1 1/2" BACKFLOW PREVENTER ASSEMBLY EA 8,500.0000 8,500.00 0.000 0 044 FLOW SENSOR CABLE LS 650.0000 650.00 0.000 0 045 FLOW SENSOR EA 3,500.0000 3,500.00 0.000 0 046 1 1/2" PLASTIC PIPE (SCHEDULE 40) LF 90.0000 1,800.00 0.000 0 (F) (SUPPLY LINE) 047 2" PLASTIC PIPE (CLASS 315) (SUPPLY LF 100.0000 3,000.00 0.000 0 (F) LINE) 048 MOVE-IN/MOVE-OUT (EROSION CONTROL) EA 1,550.0000 3,100.00 0.000 0 049 HYDROMULCH SQFT 0.4000 3,484.00 0.000 0 PROGRAM CAS145 PAGE 3 DATE 06/16/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-0P9004 TIME 02:52 PM ESTIMATE NO. 002 BID OPENING 12/10/25 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/20/26 R.E. NAME: SINGH, JASMANINDER DATE OF THIS ESTIMATE 06/16/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 050 FIBER ROLLS LF 5.7500 7,705.00 0.000 0 051 HYDROSEED SQFT 0.4000 1,828.00 0.000 0 052 COMPOST (CY) CY 87.2500 1,221.50 0.000 0 053 INCORPORATE MATERIALS SQFT 0.5000 2,285.00 0.000 0 054 HOT MIX ASPHALT (TYPE A) TON 210.0000 222,600.00 0.000 0 055 PLACE HOT MIX ASPHALT DIKE (TYPE C) LF 20.0000 2,000.00 0.000 0 056 PLACE HOT MIX ASPHALT DIKE (TYPE F) LF 20.0000 14,400.00 0.000 0 057 TACK COAT TON 650.0000 2,275.00 0.000 0 058 REMOVE ASPHALT CONCRETE DIKE LF 6.0000 3,840.00 0.000 0 059 COLD PLANE ASPHALT CONCRETE PAVEMENT SQYD 25.0000 29,500.00 0.000 0 060 STRUCTURAL CONCRETE, BRIDGE CY 11,000.0000 462,000.00 0.000 0 (F) 061 STRUCTURAL CONCRETE, BRIDGE (POLYMER CY 16,000.0000 64,000.00 0.000 0 (F) FIBER) 062 STRUCTURAL CONCRETE, BARRIER SLAB CY 1,775.0000 919,450.00 0.000 0 (F) 063 AGGREGATE BASE (APPROACH SLAB) CY 5,000.0000 2,000.00 0.000 0 064 STRUCTURAL CONCRETE, APPROACH SLAB (TYPE CY 6,000.0000 24,000.00 0.000 0 R) 065 MINOR CONCRETE (MINOR STRUCTURE) CY 6,660.0000 36,630.00 0.000 0 (F) 066 DRILL AND BOND DOWEL LF 99.0000 44,451.00 0.000 0 067 DRILL AND BOND DOWEL (CHEMICAL LF 110.0000 15,840.00 0.000 0 ADHESIVE)(LF) 068 BAR REINFORCING STEEL (BRIDGE) LB 3.0000 34,404.00 0.000 0 (F) 069 ASPHALT MEMBRANE WATERPROOFING SQFT 14.0000 22,932.00 0.000 0 (F) 070 REFINISH BRIDGE DECK SQFT 10.0000 19,700.00 0.000 0 071 CORE CONCRETE (7") LF 650.0000 29,900.00 0.000 0 072 CORE CONCRETE (8") LF 800.0000 1,600.00 0.000 0 073 ACCESS OPENING, SOFFIT EA 5,555.0000 99,990.00 0.000 0 074 BRIDGE REMOVAL (PORTION), LOCATION A LS 160,000.0000 160,000.00 0.000 0 075 BRIDGE REMOVAL (PORTION), LOCATION B LS 80,000.0000 80,000.00 0.000 0 076 BRIDGE REMOVAL (PORTION), LOCATION C LS 80,000.0000 80,000.00 0.000 0 PROGRAM CAS145 PAGE 4 DATE 06/16/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-0P9004 TIME 02:52 PM ESTIMATE NO. 002 BID OPENING 12/10/25 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/20/26 R.E. NAME: SINGH, JASMANINDER DATE OF THIS ESTIMATE 06/16/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 077 FIBER REINFORCED POLYMER SYSTEM (COLUMN) SQFT 20.0000 232,920.00 0.000 0 078 COLUMN CASING LB 9.7500 3,231,852.00 0.000 0 (F) 079 CARBON FIBER REINFORCED POLYMER BAR LF 50.0000 190,300.00 0.000 0 080 18" PLASTIC PIPE LF 325.0000 40,300.00 0.000 0 081 REMOVE INLET EA 2,750.0000 5,500.00 0.000 0 082 MISCELLANEOUS IRON AND STEEL LB 5.0000 3,945.00 0.000 0 (F) 083 BRIDGE DECK DRAINAGE SYSTEM LB 13.7500 723,208.75 0.000 0 (F) 084 WROUGHT IRON FENCE (8' HIGH) LF 500.0000 25,000.00 0.000 0 085 REMOVE FENCE LF 35.0000 35,350.00 0.000 0 086 RECONSTRUCT FENCE LF 175.0000 168,000.00 0.000 0 087 REMOVE PAVEMENT MARKER EA 5.0000 8,100.00 0.000 0 088 GUARD RAILING DELINEATOR EA 35.0000 595.00 0.000 0 089 PAVEMENT MARKER (RETROREFLECTIVE) EA 11.0000 9,900.00 0.000 0 090 OBJECT MARKER (TYPE P) EA 100.0000 500.00 0.000 0 091 REMOVE ROADSIDE SIGN EA 150.0000 1,500.00 0.000 0 092 FURNISH SINGLE SHEET ALUMINUM SIGN SQFT 25.0000 3,250.00 0.000 0 (0.080"-UNFRAMED) 093 FURNISH SINGLE SHEET ALUMINUM SIGN SQFT 35.0000 2,310.00 0.000 0 (0.063"-FRAMED) 094 METAL (BARRIER MOUNTED SIGN) LB 17.0000 28,560.00 0.000 0 095 ROADSIDE SIGN - ONE POST EA 375.0000 1,500.00 0.000 0 096 MIDWEST GUARDRAIL SYSTEM (WOOD POST) LF 55.0000 35,750.00 0.000 0 097 MIDWEST GUARDRAIL SYSTEM (8' STEEL POST) LF 55.0000 9,350.00 0.000 0 098 VEGETATION CONTROL (MINOR CONCRETE) SQYD 125.0000 68,750.00 0.000 0 099 TRANSITION RAILING (TYPE AGT) EA 7,500.0000 37,500.00 0.000 0 100 ALTERNATIVE IN-LINE TERMINAL TL-3 EA 6,500.0000 26,000.00 0.000 0 101 CONCRETE BARRIER (TYPE 842) LF 200.0000 203,600.00 0.000 0 (F) 102 CONCRETE BARRIER (TYPE 842 MODIFIED) LF 200.0000 734,200.00 0.000 0 (F) 103 REMOVE GUARDRAIL LF 12.0000 8,040.00 0.000 0 PROGRAM CAS145 PAGE 5 DATE 06/16/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-0P9004 TIME 02:52 PM ESTIMATE NO. 002 BID OPENING 12/10/25 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/20/26 R.E. NAME: SINGH, JASMANINDER DATE OF THIS ESTIMATE 06/16/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 104 SALVAGE METAL BRIDGE RAILING LF 10.0000 46,890.00 0.000 0 105 THERMOPLASTIC PAVEMENT MARKING SQFT 14.0000 3,696.00 0.000 0 106 THERMOPLASTIC PAVEMENT MARKING (ENHANCED SQFT 15.0000 14,925.00 0.000 0 WET NIGHT VISIBILITY) 107 6" THERMOPLASTIC TRAFFIC STRIPE LF 4.0000 51,680.00 0.000 0 (ENHANCED WET NIGHT VISIBILITY) 108 12" THERMOPLASTIC TRAFFIC STRIPE LF 12.0000 40,440.00 0.000 0 (ENHANCED WET NIGHT VISIBILITY) 109 REMOVE THERMOPLASTIC TRAFFIC STRIPE LF 3.0000 60,600.00 0.000 0 110 ITEM DELETED PER ADDENDUM LS 0.0000 0.00 0.000 0 111 6" RUMBLE STRIP (ASPHALT CONCRETE STA 1,800.0000 10,800.00 0.000 0 PAVEMENT) 112 6" TRAFFIC STRIPE TAPE WITH CONTRAST LF 15.0000 259,950.00 0.000 0 (WARRANTY) (BROKEN 18-12) 113 MAINTAINING EXISTING TRAFFIC MANAGEMENT LS 3,000.0000 3,000.00 0.097 291.00 0.097 291 SYSTEM ELEMENTS DURING CONSTRUCTION 114 TEMPORARY LIGHTING SYSTEMS LS 80,000.0000 80,000.00 0.000 0 115 MODIFYING LIGHTING SYSTEMS LS 970,000.0000 970,000.00 0.010 9,700.00 0.010 9,700 PROGRAM CAS145 PAGE 6 DATE 06/16/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-0P9004 TIME 02:52 PM ESTIMATE NO. 002 BID OPENING 12/10/25 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/20/26 R.E. NAME: SINGH, JASMANINDER DATE OF THIS ESTIMATE 06/16/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION 109,424.00 130,674.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 0.00 0.00 SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION 109,424.00 130,674.00 116 MOBILIZATION LS 930,000.0000 930,000.00 0.000 0 ORIGINAL CONTRACT AMOUNT 12,696,329.25 TOTAL WORK COMPLETED 109,424.00 130,674.00 MATERIALS ON HAND ON SITE 254,289.09 254,289.09 DEDUCTIONS 0.00 0.00 TOTAL 363,713.09 384,963.09 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 01/21/26 300 05/11/26 03/18/26 07/22/27 29 37 0 0 1% 10% PROGRESS IS SATISFACTORY SINGH, JASMANINDER RESIDENT ENGINEER