PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 12/22/09 EST. NO.08 TIME 07:55 AM R.E. NAME: CARTY RODOLFO 04-1A4604 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 004 0001 -200,035.00 A.C. @ L.S.(-) 111909 N 1 0 -200,035.00 TOTAL THIS ESTIMATE 70,137.87 TOTAL PREVIOUS ESTIMATE -129,897.13 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 12/22/09 EST. NO.08 TIME 07:55 AM R.E. NAME: CARTY RODOLFO 04-1A4604 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 12/22/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-1A4604 TIME 07:55 AM ESTIMATE NO. 08 BID OPENING 02/03/09 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/20/09 R.E. NAME: CARTY RODOLFO DATE OF THIS ESTIMATE 12/22/09 LOCATION PROGRESS ESTIMATE 04-ALA-24-R5.9/R6.2 ----------------- 04-CC-24-R0.0/R0.5 TABER CONSTRUCTION, INC IN ALAMEDA AND CONTRA COSTA 04-ALA-260-R0.9/R1.9 P. O. BOX 1309 COUNTIES ON ROUTE 24 AT THE MARTINEZ, CA 94553 CALDECOTT TUNNEL AND ON ROUTE 260 AT THE POSEY WEBSTER STREET TUBES FED. AID NO. N O N E UPGRADE VENTILATION SYSTEMS ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 CONSTRUCTION SITE MANAGEMENT LS 1,000.0000 1,000.00 1.000 1,000.00 02 PREPARE WATER POLLUTION CONTROL LS 600.0000 600.00 1.000 600.00 PROGRAM 03 STREET SWEEPING LS 1,000.0000 1,000.00 1.000 1,000.00 04 CONSTRUCTION AREA SIGNS LS 1,500.0000 1,500.00 1.000 1,500.00 05 TRAFFIC CONTROL SYSTEM LS 10,000.0000 10,000.00 1.000 10,000.00 06 PORTABLE CHANGEABLE MESSAGE SIGN LS 2,000.0000 2,000.00 1.000 2,000.00 07 BUILDING WORK LS 2534,000.0000 2,534,000.00 0.151 382,634.00 0.997 2,526,398.00 PROGRAM CAS145 PAGE 2 DATE 12/22/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-1A4604 TIME 07:55 AM ESTIMATE NO. 08 BID OPENING 02/03/09 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/20/09 R.E. NAME: CARTY RODOLFO DATE OF THIS ESTIMATE 12/22/09 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 382,634.00 2,542,498.00 ADJUSTMENT OF COMPENSATION -200,035.00 -200,035.00 EXTRA WORK 0.00 70,137.87 SUBTOTAL AMOUNT EARNED 182,599.00 2,412,600.87 ORIGINAL CONTRACT AMOUNT 2,550,100.00 TOTAL WORK COMPLETED 182,599.00 2,412,600.87 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 182,599.00 2,412,600.87 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 03/10/09 200 03/25/09 03/25/09 01/13/10 188 1 0 0 96% 94% PROGRESS IS SATISFACTORY CARTY RODOLFO RESIDENT ENGINEER PROGRAM CAS145 DATE 12/22/09