PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 10/20/25 EST. NO. 003 TIME 02:25 PM R.E. NAME: LARWIN, THOMAS 04-1Y7204 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0003 352.32 E.W. @ F.A.(+) 082525 N GSB-1 0004 352.32 082725 N GSB-2 0005 4,895.00 100625 N HS-001 002 0001 3,556.86 E.W. @ F.A.(+) 092725 N PAR-01 9,156.50 TOTAL THIS ESTIMATE 1,444.22 TOTAL PREVIOUS ESTIMATE 10,600.72 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 10/20/25 EST. NO. 003 TIME 02:25 PM R.E. NAME: LARWIN, THOMAS 04-1Y7204 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 10/20/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-1Y7204 TIME 02:25 PM ESTIMATE NO. 003 BID OPENING 04/10/25 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/25 R.E. NAME: LARWIN, THOMAS DATE OF THIS ESTIMATE 10/20/25 LOCATION PROGRESS ESTIMATE 04-SF-80-5.7/7.7 ----------------- GOLDEN STATE BRIDGE, INC. THE CITY AND COUNTY OF SAN FRANCISCO AT 3701 MALLARD DRIVE VARIOUS LOCATIONS FROM 0.1 MILE EAST OF BENICIA CA 94510 FREMONT STREET OFF-RAMP TO 0.2 MILE WEST OF YERBA BUENA ISLAND OFF-RAMP FED. AID NO. N O N E STRUCTURAL CONCRETE, BRIDGE (RSC) & JOINT ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 LEAD COMPLIANCE PLAN LS 10,000.0000 10,000.00 0.750 7,500 002 LEVEL 2 CRITICAL PATH METHOD SCHEDULE LS 15,000.0000 15,000.00 0.250 3,750 003 TIME-RELATED OVERHEAD (WDAY) WDAY 3,000.0000 1,350,000.00 19.000 57,000.00 46.000 138,000 004 DISPUTE RESOLUTION BOARD ON-SITE MEETING EA 6,000.0000 60,000.00 1.000 6,000 005 HOURLY OFF-SITE HR 200.0000 8,000.00 5.000 1,000.00 6.000 1,200 DISPUTE-RESOLUTION-BOARD-RELATED TASKS 006 CONSTRUCTION AREA SIGNS LS 25,000.0000 25,000.00 0.750 18,750 007 TRAFFIC CONTROL SYSTEM LS 1,220,000.0000 1,220,000.00 0.042 51,240.00 0.102 124,440 008 STATIONARY IMPACT ATTENUATOR VEHICLE DAY 770.0000 346,500.00 79.000 60,830.00 106.000 81,620 009 PORTABLE RADAR SPEED FEEDBACK SIGN DAY 45.0000 20,250.00 20.000 900.00 39.000 1,755 SYSTEM 010 PORTABLE CHANGEABLE MESSAGE SIGN (EA) EA 7,500.0000 67,500.00 0.000 0 011 MOBILE BARRIER TRAILER MO 85,000.0000 1,870,000.00 1.000 85,000.00 3.000 255,000 012 JOB SITE MANAGEMENT LS 65,000.0000 65,000.00 0.042 2,730.00 0.102 6,630 013 WATER POLLUTION CONTROL PROGRAM LS 5,000.0000 5,000.00 0.025 125.00 0.550 2,750 014 TEMPORARY DRAINAGE INLET PROTECTION EA 400.0000 20,000.00 0.000 0 015 STREET SWEEPING LS 45,000.0000 45,000.00 0.042 1,890.00 0.102 4,590 016 WORK AREA MONITORING (BRIDGE) LS 20,000.0000 20,000.00 0.109 2,180.00 0.164 3,280 017 TEMPORARY DECKING LS 750,000.0000 750,000.00 0.141 105,750.00 0.196 147,000 018 STRUCTURAL CONCRETE, BRIDGE (RSC) CY 19,000.0000 1,216,000.00 6.720 127,680.00 9.720 184,680 019 CLEAN EXPANSION JOINT LF 50.0000 406,900.00 0.000 0 020 CLEAN AND SEAL BOLT HEAD SOCKET EA 65.0000 301,080.00 0.000 0 021 CLEAN AND SEAL PLATE JOINT LF 104.0000 315,952.00 0.000 0 022 JOINT SEAL (MR 1/2" MODIFIED) LF 145.0000 67,280.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 10/20/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-1Y7204 TIME 02:25 PM ESTIMATE NO. 003 BID OPENING 04/10/25 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/25 R.E. NAME: LARWIN, THOMAS DATE OF THIS ESTIMATE 10/20/25 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 023 JOINT SEAL (MR 1" MODIFIED) LF 125.0000 1,113,750.00 0.000 0 024 BONDED JOINT SEAL (MR 2") LF 175.0000 72,450.00 0.000 0 025 BAR REINFORCING STEEL (EPOXY COATED) LB 7.0000 72,282.00 1,126.500 7,885.50 1,689.700 11,827 (F) 026 STRUCTURAL STEEL (BRIDGE) LB 45.0000 126,585.00 306.900 13,810.50 460.300 20,713 (F) 027 SPOT BLAST CLEAN AND PAINT UNDERCOAT SQFT 210.0000 514,920.00 267.490 56,172.90 401.240 84,260 028 BRIDGE REMOVAL (PORTION) LS 1,470,000.0000 1,470,000.00 0.064 94,080.00 0.273 401,310 029 GALVANIC ANODES EA 25.0000 44,000.00 192.000 4,800.00 288.000 7,200 030 MAINTAINING EXISTING TRAFFIC MANAGEMENT LS 5,000.0000 5,000.00 0.042 210.00 0.102 510 SYSTEM ELEMENTS DURING CONSTRUCTION 031 ITEM DELETED PER ADDENDUM LS 0.0000 0.00 0.000 0 032 MOBILE BARRIER SYSTEM DAY 2,500.0000 1,125,000.00 20.000 50,000.00 47.000 117,500 PROGRAM CAS145 PAGE 3 DATE 10/20/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-1Y7204 TIME 02:25 PM ESTIMATE NO. 003 BID OPENING 04/10/25 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/25 R.E. NAME: LARWIN, THOMAS DATE OF THIS ESTIMATE 10/20/25 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION 723,283.90 1,630,266.80 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 9,156.50 10,600.72 SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION 732,440.40 1,640,867.52 033 MOBILIZATION LS 1,400,000.0000 1,400,000.00 0.250 350,000.00 0.750 1,050,000 ORIGINAL CONTRACT AMOUNT 14,148,449.00 TOTAL WORK COMPLETED 1,082,440.40 2,690,867.52 MATERIALS ON HAND ON SITE -42,993.16 85,986.32 DEDUCTIONS 0.00 0.00 TOTAL 1,039,447.24 2,776,853.84 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 06/03/25 450 08/11/25 07/28/25 05/20/27 46 3 0 0 19% 10% PROGRESS IS SATISFACTORY LARWIN, THOMAS RESIDENT ENGINEER