PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 09/21/09 EST. NO.01 TIME 09:10 AM R.E. NAME: GONZALEZ ALFONSO 04-290834 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- *** THERE ARE NO EXTRA WORK PAYMENTS THIS ESTIMATE *** PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 09/21/09 EST. NO.01 TIME 09:10 AM R.E. NAME: GONZALEZ ALFONSO 04-290834 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 09/21/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-290834 TIME 09:10 AM ESTIMATE NO. 01 BID OPENING 06/03/09 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/20/09 R.E. NAME: GONZALEZ ALFONSO DATE OF THIS ESTIMATE 09/21/09 LOCATION PROGRESS ESTIMATE 04-ALA-580-13.2/19.1 ----------------- GHILOTTI CONSTRUCTION COMPANY IN ALAMEDA COUNTY IN LIVERMORE, 246 GHILOTTI AVENUE DUBLIN AND PLEASANTON FROM 0.4 KM SANTA ROSA, CA 95407 E OF PORTOLA AVENUE OVERCROSSINGTO 0.5 KM W OF HACIENDA DRIVE OC FED. AID NO. HPLU-6204(71) ,L-6204(71) CONSTRUCT HOV LANES ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 PROGRESS SCHEDULE (CRITICAL PATH METHOD) LS 7,500.0000 7,500.00 0.200 1,500.00 0.200 1,500.00 02 TIME-RELATED OVERHEAD WDAY 938.0000 459,620.00 0.040 37.52 0.040 37.52 03 TEMPORARY FENCE (TYPE ESA) M 6.0000 2,220.00 0.000 0.00 04 TEMPORARY FENCE (WILDLIFE EXCULSION) M 6.4000 3,200.00 0.000 0.00 05 CONSTRUCTION SITE MANAGEMENT LS 1,000.0000 1,000.00 0.000 0.00 06 PREPARE STORM WATER POLLUTION LS 2,500.0000 2,500.00 1.000 2,500.00 1.000 2,500.00 S) PREVENTION PLAN 07 TEMPORARY SILT FENCE M 3.6000 11,880.00 0.000 0.00 08 TEMPORARY CONSTRUCTION ENTRANCE EA 1,000.0000 17,000.00 0.000 0.00 09 TEMPORARY COVER M2 10.0000 5,100.00 0.000 0.00 10 TEMPORARY DRAINAGE INLET PROTECTION EA 100.0000 15,000.00 0.000 0.00 11 TEMPORARY HYDRAULIC MULCH M2 1.0000 3,740.00 0.000 0.00 S) (BONDED FIBER MATRIX) 12 STREET SWEEPING LS 10,000.0000 10,000.00 0.000 0.00 13 TEMPORARY CONCRETE WASHOUT BIN EA 400.0000 50,000.00 0.000 0.00 14 CONSTRUCTION AREA SIGNS LS 15,000.0000 15,000.00 0.700 10,500.00 0.700 10,500.00 S) 15 TRAFFIC CONTROL SYSTEM LS 200,000.0000 200,000.00 0.030 6,000.00 0.030 6,000.00 S) 16 TEMPORARY TRAFFIC STRIPE (TAPE) M 4.0000 101,600.00 6,348.000 25,392.00 6,348.000 25,392.00 S) 17 TEMPORARY PAVEMENT MARKING (TAPE) M2 100.0000 1,800.00 0.000 0.00 18 CHANNELIZER (SURFACE MOUNTED) EA 25.0000 13,500.00 9.000 225.00 9.000 225.00 S) 19 CHANNELIZER (SURFACE MOUNTED) EA 35.0000 840.00 0.000 0.00 S) (LEFT IN PLACE) 20 FLASHING BEACON (PORTABLE) EA 75.0000 1,050.00 0.000 0.00 S) 21 TEMPORARY PAVEMENT MARKER EA 3.0000 55,500.00 6,900.000 20,700.00 6,900.000 20,700.00 S) 22 PORTABLE CHANGEABLE MESSAGE SIGN EA 8,000.0000 32,000.00 0.000 0.00 S) PROGRAM CAS145 PAGE 2 DATE 09/21/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-290834 TIME 09:10 AM ESTIMATE NO. 01 BID OPENING 06/03/09 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/20/09 R.E. NAME: GONZALEZ ALFONSO DATE OF THIS ESTIMATE 09/21/09 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 23 TEMPORARY RAILING (TYPE K) M 14.0000 333,200.00 11,297.000 158,158.00 11,297.000 158,158.00 S) 24 TEMPORARY RAILING (TYPE K, BART) M 55.0000 34,650.00 0.000 0.00 S) 25 SAFETY CONSTRUCTION FENCE M 75.0000 41,250.00 0.000 0.00 S) 26 TEMPORARY CRASH CUSHION MODULE EA 190.0000 58,900.00 42.000 7,980.00 42.000 7,980.00 S) 27 ABANDON CULVERT EA 600.0000 22,800.00 0.000 0.00 28 OBLITERATE SURFACING M2 14.0000 784.00 0.000 0.00 29 REMOVE CHAIN LINK FENCE M 6.0000 9,480.00 0.000 0.00 30 REMOVE METAL BEAM GUARD RAILING M 35.0000 14,000.00 38.770 1,356.95 38.770 1,356.95 31 REMOVE SINGLE THRIE BEAM BARRIER M 8.2000 107,420.00 4,356.700 35,724.94 4,356.700 35,724.94 32 REMOVE DOUBLE THRIE BEAM BARRIER M 8.2000 9,840.00 550.600 4,514.92 550.600 4,514.92 33 REMOVE FLARED END SECTION EA 400.0000 2,800.00 0.000 0.00 34 REMOVE YELLOW THERMOPLASTIC TRAFFIC M 2.0000 320.00 122.000 244.00 122.000 244.00 STRIPE 35 REMOVE PAINTED TRAFFIC STRIPE M 2.0000 1,220.00 0.000 0.00 36 REMOVE THERMOPLASTIC TRAFFIC STRIPE M 2.0000 4,200.00 4,831.000 9,662.00 4,831.000 9,662.00 37 REMOVE PAVEMENT MARKER EA 0.6000 5,670.00 2,245.000 1,347.00 2,245.000 1,347.00 38 REMOVE ROADSIDE SIGN (WOOD POST) EA 60.0000 360.00 0.000 0.00 39 REMOVE SIGN STRUCTURE EA 2,000.0000 2,000.00 0.000 0.00 40 REMOVE CULVERT M 50.0000 53,000.00 0.000 0.00 41 REMOVE INLET EA 500.0000 24,500.00 0.000 0.00 42 REMOVE HEADWALL EA 1,000.0000 1,000.00 1.000 1,000.00 1.000 1,000.00 43 RECONSTRUCT SINGLE THRIE BEAM BARRIER M 45.0000 85,950.00 0.000 0.00 44 RECONSTRUCT BART BARRIER M 465.0000 265,050.00 0.000 0.00 45 RESET ROADSIDE SIGN EA 200.0000 2,600.00 0.000 0.00 46 RELOCATE ROADSIDE SIGN (WOOD POST) EA 200.0000 3,400.00 0.000 0.00 47 RELOCATE ROADSIDE SIGN EA 70.0000 420.00 0.000 0.00 (STRAP AND SADDLE BRACKET METHOD) 48 ADJUST INLET EA 1,000.0000 7,000.00 0.000 0.00 49 ADJUST MANHOLE TO GRADE EA 1,000.0000 1,000.00 0.000 0.00 PROGRAM CAS145 PAGE 3 DATE 09/21/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-290834 TIME 09:10 AM ESTIMATE NO. 01 BID OPENING 06/03/09 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/20/09 R.E. NAME: GONZALEZ ALFONSO DATE OF THIS ESTIMATE 09/21/09 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 50 MODIFY INLET TO MANHOLE EA 2,000.0000 4,000.00 0.000 0.00 51 COLD PLANE ASPHALT CONCRETE PAVEMENT M2 14.0000 173,600.00 0.000 0.00 S) 52 REMOVE CONCRETE BARRIER (TYPE K) M 10.0000 3,900.00 0.000 0.00 53 CAP INLET EA 1,000.0000 23,000.00 0.000 0.00 54 REMOVE CRASH CUSHION (SAND FILLED) EA 50.0000 700.00 0.000 0.00 55 CLEARING AND GRUBBING LS 150,000.0000 150,000.00 0.300 45,000.00 0.300 45,000.00 56 DEVELOP WATER SUPPLY LS 25,000.0000 25,000.00 1.000 25,000.00 1.000 25,000.00 57 ROADWAY EXCAVATION M3 0.0100 439.00 0.000 0.00 58 ROADWAY EXCAVATION (TYPE Y-2) M3 0.0100 410.00 0.000 0.00 (AERIALLY DEPOSITED LEAD) 59 LEAD COMPLIANCE PLAN LS 5,000.0000 5,000.00 1.000 5,000.00 1.000 5,000.00 S) 60 STRUCTURE EXCAVATION (BRIDGE) M3 165.0000 214,170.00 0.000 0.00 F) 61 STRUCTURE EXCAVATION (RETAINING WALL) M3 60.0000 87,660.00 0.000 0.00 F) 62 STRUCTURE EXCAVATION (TIEBACK WALL) M3 125.0000 36,250.00 0.000 0.00 F) 63 STRUCTURE BACKFILL (BRIDGE) M3 75.0000 69,675.00 0.000 0.00 F) 64 STRUCTURE BACKFILL (RETAINING WALL) M3 150.0000 137,400.00 0.000 0.00 F) 65 STRUCTURE BACKFILL (TIEBACK WALL) M3 200.0000 6,400.00 0.000 0.00 F) 66 PERVIOUS BACKFILL MATERIAL (RETAINING M3 150.0000 12,450.00 0.000 0.00 F) WALL) 67 SAND BACKFILL M3 170.0000 44,200.00 0.000 0.00 68 DITCH EXCAVATION M3 30.0000 22,200.00 0.000 0.00 69 IMPORTED MATERIAL (SHOULDER BACKING) TONN 40.0000 8,000.00 0.000 0.00 70 EROSION CONTROL (TYPE D) HA 4,000.0000 10,000.00 0.000 0.00 S) 71 BIOFILTRATION STRIPS M2 0.6000 3,156.00 0.000 0.00 S) 72 EROSION CONTROL (NETTING) M2 3.5000 2,905.00 0.000 0.00 S) 73 BIOFILTRATION SWALES M2 7.5000 5,550.00 0.000 0.00 S) 74 FIBER ROLLS M 6.0000 12,300.00 0.000 0.00 75 MOVE-IN/MOVE-OUT (EROSION CONTROL) EA 630.0000 1,890.00 0.000 0.00 S) 76 450 MM WELDED STEEL PIPE CONDUIT M 725.0000 3,625.00 0.000 0.00 SF)(6.35 MM THICK) PROGRAM CAS145 PAGE 4 DATE 09/21/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-290834 TIME 09:10 AM ESTIMATE NO. 01 BID OPENING 06/03/09 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/20/09 R.E. NAME: GONZALEZ ALFONSO DATE OF THIS ESTIMATE 09/21/09 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 77 LIME TONN 150.0000 846,000.00 0.000 0.00 78 LIME STABILIZATION M2 2.9000 304,500.00 0.000 0.00 79 CLASS 4 AGGREGATE SUBBASE M3 13.0000 105,170.00 0.000 0.00 80 CLASS 3 AGGREGATE BASE M3 52.0000 53,040.00 0.000 0.00 81 ASPHALTIC EMULSION (CURING SEAL) TONN 600.0000 43,800.00 0.000 0.00 82 LEAN CONCRETE BASE M3 144.0000 4,204,800.00 0.000 0.00 83 ASPHALT TREATED PERMEABLE BASE M3 160.0000 25,600.00 0.000 0.00 84 REPLACE ASPHALT CONCRETE SURFACING M3 260.0000 57,200.00 0.000 0.00 85 ASPHALT CONCRETE TONN 66.0000 5,016,000.00 0.000 0.00 86 ASPHALT CONCRETE TONN 68.0000 3,461,200.00 0.000 0.00 (CROSS SLOPE CORRECTION) 87 RUBBERIZED ASPHALT CONCRETE (TYPE G) TONN 90.0000 2,619,000.00 0.000 0.00 88 RUBBERIZED ASPHALT CONCRETE (TYPE O) TONN 9.0000 178,200.00 0.000 0.00 89 PAVING ASPHALT (BINDER-PAVEMENT TONN 1.0000 170.00 0.000 0.00 REINFORCING FABRIC) 90 PAVEMENT REINFORCING FABRIC M2 1.2000 174,000.00 0.000 0.00 91 PLACE ASPHALT CONCRETE (MISCELLANEOUS M2 7.5000 26,325.00 0.000 0.00 AREA) 92 PLACE ASPHALT CONCRETE DIKE (TYPE C) M 8.0000 2,320.00 0.000 0.00 93 PLACE ASPHALT CONCRETE DIKE (TYPE E) M 8.0000 11,040.00 0.000 0.00 94 PLACE ASPHALT CONCRETE DIKE (TYPE F) M 8.0000 704.00 0.000 0.00 95 REPLACE CONCRETE PAVEMENT M3 700.0000 336,000.00 0.000 0.00 (RAPID STRENGTH CONCRETE) 96 CRACK EXISTING CONCRETE PAVEMENT M2 0.5200 69,680.00 0.000 0.00 97 GRIND EXISTING CONCRETE M2 16.0000 39,680.00 0.000 0.00 S) PAVEMENT 98 600 MM CAST-IN-DRILLED-HOLE CONCRETE M 300.0000 21,000.00 0.000 0.00 S) PILING 99 FURNISH PILING (CLASS 900) M 80.0000 154,960.00 0.000 0.00 (ALTERNATIVE X) 00 DRIVE PILE (CLASS 900) EA 1,500.0000 144,000.00 0.000 0.00 S) (ALTERNATIVE X) 01 FURNISH PILING (CLASS 900) M 150.0000 80,700.00 0.000 0.00 (ALTERNATIVE W) 02 DRIVE PILE (CLASS 900) (ALTERNATIVE W) EA 1,500.0000 54,000.00 0.000 0.00 S) 03 TIEBACK ANCHOR EA 2,000.0000 132,000.00 0.000 0.00 S) PROGRAM CAS145 PAGE 5 DATE 09/21/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-290834 TIME 09:10 AM ESTIMATE NO. 01 BID OPENING 06/03/09 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/20/09 R.E. NAME: GONZALEZ ALFONSO DATE OF THIS ESTIMATE 09/21/09 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 04 STRUCTURAL CONCRETE, BRIDGE FOOTING M3 600.0000 210,600.00 0.000 0.00 F) 05 STRUCTURAL CONCRETE, BRIDGE M3 1,000.0000 53,000.00 0.000 0.00 F) 06 STRUCTURAL CONCRETE, RETAINING WALL M3 650.0000 469,300.00 0.000 0.00 F) 07 CLASS 2 CONCRETE (BOX CULVERT) M3 1,550.0000 32,550.00 0.000 0.00 08 MINOR CONCRETE (MINOR STRUCTURE) M3 1,475.0000 118,000.00 0.000 0.00 F) 09 FRACTURED RIB TEXTURE M2 25.0000 4,625.00 0.000 0.00 F) 10 BAR REINFORCING STEEL KG 2.5000 7,695.00 0.000 0.00 SF) 11 BAR REINFORCING STEEL (BRIDGE) KG 1.5000 75,217.50 0.000 0.00 SF) 12 BAR REINFORCING STEEL (RETAINING WALL) KG 1.7500 98,969.50 0.000 0.00 SF) 13 SHOTCRETE M3 450.0000 54,900.00 0.000 0.00 F) 14 FURNISH SIGN STRUCTURE (TRUSS) KG 11.0000 568,480.00 0.000 0.00 F) 15 INSTALL SIGN STRUCTURE (TRUSS) KG 0.5000 25,840.00 0.000 0.00 SF) 16 FURNISH FORMED PANEL SIGN (OVERHEAD) M2 130.0000 12,480.00 0.000 0.00 17 FURNISH LAMINATED PANEL SIGN M2 230.0000 4,140.00 0.000 0.00 (25.4 MM-TYPE A) 18 FURNISH SINGLE SHEET ALUMINUM SIGN M2 100.0000 700.00 0.000 0.00 (2.0 MM-UNFRAMED) 19 FURNISH SINGLE SHEET ALUMINUM SIGN M2 112.0000 3,472.00 0.000 0.00 (1.6 MM-FRAMED) 20 FURNISH FIBERGLASS REINFORCED PLASTIC M2 115.0000 805.00 0.000 0.00 PANEL SIGN (3.4 MM) 21 1524 MM CAST-IN-DRILLED-HOLE M 1,750.0000 82,250.00 0.000 0.00 CONCRETE PILE (SIGN FOUNDATION) 22 METAL (RAIL MOUNTED SIGN) KG 17.0000 41,820.00 0.000 0.00 23 ROADSIDE SIGN - ONE POST EA 250.0000 1,250.00 0.000 0.00 24 INSTALL SIGN OVERLAY M2 250.0000 1,250.00 0.000 0.00 25 INSTALL SIGN PANEL ON EXISTING FRAME M2 75.0000 4,800.00 0.000 0.00 26 INSTALL ROADSIDE SIGN PANEL ON EA 50.0000 50.00 0.000 0.00 EXISTING POST 27 PREPARE AND PAINT POSTMILE MARKINGS ON M2 30.0000 450.00 0.000 0.00 CONCRETE BARRIER 28 450 MM ALTERNATIVE PIPE CULVERT M 160.0000 12,320.00 0.000 0.00 29 600 MM ALTERNATIVE PIPE CULVERT M 185.0000 366,300.00 0.000 0.00 30 750 MM ALTERNATIVE PIPE CULVERT M 265.0000 47,700.00 0.000 0.00 PROGRAM CAS145 PAGE 6 DATE 09/21/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-290834 TIME 09:10 AM ESTIMATE NO. 01 BID OPENING 06/03/09 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/20/09 R.E. NAME: GONZALEZ ALFONSO DATE OF THIS ESTIMATE 09/21/09 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 31 900 MM ALTERNATIVE PIPE CULVERT M 355.0000 11,005.00 0.000 0.00 32 80 MM PLASTIC PIPE (EDGE DRAIN) M 13.0000 4,290.00 0.000 0.00 33 80 MM PLASTIC PIPE (EDGE DRAIN OUTLET) M 44.0000 1,012.00 0.000 0.00 34 450 MM ALTERNATIVE FLARED END SECTION EA 500.0000 1,000.00 0.000 0.00 35 600 MM ALTERNATIVE FLARED END SECTION EA 600.0000 1,800.00 0.000 0.00 36 750 MM ALTERNATIVE FLARED END SECTION EA 700.0000 700.00 0.000 0.00 37 900 MM ALTERNATIVE FLARED END SECTION EA 800.0000 800.00 0.000 0.00 38 900 MM PRECAST CONCRETE PIPE INLET M 350.0000 1,750.00 0.000 0.00 39 ROCK SLOPE PROTECTION (LIGHT, METHOD B) M3 250.0000 10,500.00 0.000 0.00 40 ROCK SLOPE PROTECTION FABRIC M2 10.0000 1,500.00 0.000 0.00 41 MINOR CONCRETE (MISCELLANEOUS M3 875.0000 31,500.00 0.000 0.00 CONSTRUCTION) 42 MINOR CONCRETE (GUTTER) M 110.0000 8,470.00 0.000 0.00 F) 43 MINOR CONCRETE (TEXTURED PAVING) M2 65.0000 69,550.00 0.000 0.00 44 MISCELLANEOUS IRON AND STEEL KG 3.0000 19,506.00 0.000 0.00 SF) 45 CHAIN LINK FENCE (TYPE CL-0.9) M 33.0000 43,560.00 0.000 0.00 S) 46 CHAIN LINK FENCE M 71.0000 5,467.00 0.000 0.00 SF)(TYPE CL-1.2, VINYL-CLAD) (MODIFIED) 47 CHAIN LINK FENCE (TYPE CL-1.8) M 43.0000 12,040.00 0.000 0.00 S) 48 DELINEATOR (CLASS 1) EA 35.0000 3,850.00 0.000 0.00 49 GUARD RAILING DELINEATOR EA 35.0000 1,575.00 0.000 0.00 50 CONCRETE BARRIER MARKER EA 35.0000 280.00 0.000 0.00 51 OBJECT MARKER EA 40.0000 280.00 0.000 0.00 52 METAL BEAM GUARD RAILING (WOOD POST) M 54.0000 79,380.00 0.000 0.00 S) 53 CONCRETE BARRIER (TYPE K) M 11.0000 3,410.00 0.000 0.00 54 TRANSITION RAILING (TYPE STB) EA 3,000.0000 12,000.00 0.000 0.00 S) 55 TRANSITION RAILING (TYPE WB) EA 2,700.0000 13,500.00 0.000 0.00 S) 56 END ANCHOR ASSEMBLY (TYPE SFT) EA 700.0000 4,900.00 0.000 0.00 S) 57 ALTERNATIVE FLARED TERMINAL SYSTEM EA 2,400.0000 24,000.00 0.000 0.00 S) PROGRAM CAS145 PAGE 7 DATE 09/21/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-290834 TIME 09:10 AM ESTIMATE NO. 01 BID OPENING 06/03/09 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/20/09 R.E. NAME: GONZALEZ ALFONSO DATE OF THIS ESTIMATE 09/21/09 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 58 CONCRETE BARRIER (TYPE 60) M 131.0000 55,020.00 0.000 0.00 59 CONCRETE BARRIER (TYPE 60C) M 210.0000 1,495,200.00 0.000 0.00 60 CONCRETE BARRIER (TYPE 60D) M 198.0000 15,048.00 0.000 0.00 F) 61 CONCRETE BARRIER (TYPE 60E) M 606.0000 121,200.00 0.000 0.00 62 CONCRETE BARRIER (TYPE 60R) M 723.0000 159,060.00 0.000 0.00 63 CONCRETE BARRIER (TYPE 60C MODIFIED) M 175.0000 238,000.00 0.000 0.00 64 CONCRETE BARRIER (TYPE 60A MODIFIED) M 160.0000 8,640.00 0.000 0.00 65 CONCRETE BARRIER (TYPE 732A) M 230.0000 90,850.00 0.000 0.00 F) 66 THERMOPLASTIC PAVEMENT MARKING M2 32.0000 21,120.00 0.000 0.00 S) 67 100 MM THERMOPLASTIC TRAFFIC STRIPE M 1.0000 28,300.00 0.000 0.00 S) 68 200 MM THERMOPLASTIC TRAFFIC STRIPE M 1.5000 3,090.00 0.000 0.00 S) 69 200 MM THERMOPLASTIC TRAFFIC STRIPE M 1.2000 2,436.00 0.000 0.00 S) (BROKEN 3.66 M - 0.92 M) 70 100 MM THERMOPLASTIC TRAFFIC STRIPE M 0.6000 372.00 0.000 0.00 S) (BROKEN 5.18 M - 2.14 M) 71 PAVEMENT MARKER (NON-REFLECTIVE) EA 1.2000 13,200.00 0.000 0.00 S) 72 PAVEMENT MARKER (RETROREFLECTIVE) EA 3.0000 14,490.00 0.000 0.00 S) 73 MAINTAINING EXISTING TRAFFIC MANAGEMENT LS 24,000.0000 24,000.00 0.000 0.00 S) SYSTEM ELEMENTS DURING CONSTRUCTION 74 LIGHTING (TEMPORARY) LS 30,000.0000 30,000.00 0.000 0.00 S) 75 LIGHTING AND SIGN ILLUMINATION LS 340,000.0000 340,000.00 0.000 0.00 S) 76 ELECTRIC SERVICE (IRRIGATION) LS 15,000.0000 15,000.00 0.000 0.00 S) 77 TRAFFIC OPERATIONS SYSTEM LS 770,000.0000 770,000.00 0.000 0.00 S) 78 GENERAL PACKET RADIO SYSTEM (GPRS) EA 3,000.0000 15,000.00 0.000 0.00 S) WIRELESS MODEM ASSEMBLY PROGRAM CAS145 PAGE 8 DATE 09/21/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-290834 TIME 09:10 AM ESTIMATE NO. 01 BID OPENING 06/03/09 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/20/09 R.E. NAME: GONZALEZ ALFONSO DATE OF THIS ESTIMATE 09/21/09 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION 361,842.33 361,842.33 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 0.00 0.00 SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION 361,842.33 361,842.33 79 MOBILIZATION LS 3000,000.0000 3,000,000.00 0.000 0.00 ORIGINAL CONTRACT AMOUNT 30,454,448.00 TOTAL WORK COMPLETED 361,842.33 361,842.33 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 361,842.33 361,842.33 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 08/05/09 490 08/21/09 08/21/09 11/30/11 19 1 0 0 1% 4% PROGRESS IS SATISFACTORY GONZALEZ ALFONSO RESIDENT ENGINEER PROGRAM CAS145 DATE 09/21/09