PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 01/28/22 EST. NO. 022 TIME 10:26 AM R.E. NAME: HALALI, BEHZAD 04-2W1204 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0490 240,462.60 E.W. @ F.A.(+) 121921 N 0483.0 0496 21,113.54 010522 N 010522 0497 20,490.78 010622 N 010622 0501 4,121.52 010322 N 010322 0507 43,825.60 010422 N 0495.0 0508 518.01 123021 N 0496.0 0509 1,345.50 011222 N 0497.0 0510 1,423.80 011322 N 0498.0 0511 1,267.21 011422 N 0499.0 0512 1,267.21 011722 N 0500.0 0513 1,345.50 011822 N 0501.0 0514 1,345.50 011922 N 0502.0 0515 1,267.21 012022 N 0503.0 0516 1,267.21 012122 N 0504.0 0517 36,015.20 011022 N 0505.0 0518 1,345.50 012422 N 0507.0 0519 12,553.82 112921 N 0508.0 0520 6,276.91 112921 N 0509.0 0521 6,276.91 112921 N 0510.0 0522 4,975.43 112921 N 0511.0 0523 1,516.31 012222 N 0506.0 410,021.27 TOTAL THIS ESTIMATE 6,179,977.09 TOTAL PREVIOUS ESTIMATE 6,589,998.36 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 01/28/22 EST. NO. 022 TIME 10:26 AM R.E. NAME: HALALI, BEHZAD 04-2W1204 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 01/28/22 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-2W1204 TIME 10:26 AM ESTIMATE NO. 022 BID OPENING 01/11/20 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 01/28/22 R.E. NAME: HALALI, BEHZAD DATE OF THIS ESTIMATE 01/28/22 LOCATION PROGRESS ESTIMATE 04-CC-580-6.7 ----------------- FLATIRON WEST INC ON THE RICHMOND 2100 GOODYEAR RD. SAN RAFAEL BRIDGE, I580 BENICIA CA 94510 STRENGTHEN GUSSET PLATES AT VARIOUS LOCATI DIR'S ORDER EMERGENCY F.A. FED. AID NO. N O N E STRENGTHEN GUSSET PLATES AT VARIOUS LOCATI ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 STRENGTHEN GUSSET PLATES AT VARIOUS LOCA LS 61,364.0000 61,364.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 01/28/22 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-2W1204 TIME 10:26 AM ESTIMATE NO. 022 BID OPENING 01/11/20 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 01/28/22 R.E. NAME: HALALI, BEHZAD DATE OF THIS ESTIMATE 01/28/22 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 410,021.27 6,589,998.36 SUBTOTAL AMOUNT EARNED 410,021.27 6,589,998.36 ORIGINAL CONTRACT AMOUNT 61,364.00 TOTAL WORK COMPLETED 410,021.27 6,589,998.36 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 410,021.27 6,589,998.36 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 03/17/21 365 01/11/20 01/19/21 07/01/22 365 0 0 0 54% 100% PROGRESS IS SATISFACTORY UNSATIS PROGRESS OVERRIDEN BECAU W H Y ... W H Y ... W H HALALI, BEHZAD RESIDENT ENGINEER PROGRAM CAS145 DATE 01/28/22