PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 06/27/25 EST. NO. 016 TIME 10:57 AM R.E. NAME: CHAMPANERIA, VINAY 04-2Y8204 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0301 65,643.25 E.W. @ F.A.(+) 110124 N 0301 0314 2,437.22 041425 N 0314 0315 2,363.13 041625 N 0315 0316 2,419.88 041725 N 0316 0317 2,419.88 041825 N 0317 0318 2,446.27 042125 N 0318 0319 2,388.69 042225 N 0319 0320 2,388.69 042325 N 0320 0321 2,419.88 042425 N 0321 0322 1,999.10 042525 N 0322 86,925.99 TOTAL THIS ESTIMATE 1,895,996.25 TOTAL PREVIOUS ESTIMATE 1,982,922.24 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 06/27/25 EST. NO. 016 TIME 10:57 AM R.E. NAME: CHAMPANERIA, VINAY 04-2Y8204 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 06/27/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-2Y8204 TIME 10:57 AM ESTIMATE NO. 016 BID OPENING 01/09/23 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/30/25 R.E. NAME: CHAMPANERIA, VINAY DATE OF THIS ESTIMATE 06/27/25 LOCATION PROGRESS ESTIMATE 04-ALA-580-0.0 ----------------- PIPE AND PLANT SOLUTIONS, INC. REPAIR AND 23286 FOLEY STREET, REPLACE DAMAGED HAYWARD, CA 94545 PUMP PLANT FED. AID NO. N O N E REPAIR AND REPLACE DAMAGED PUMP PLANT ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 REPAIR AND REPLACE DAMAGED PUMP PLANT LS 6,975.0000 6,975.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 06/27/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-2Y8204 TIME 10:57 AM ESTIMATE NO. 016 BID OPENING 01/09/23 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/30/25 R.E. NAME: CHAMPANERIA, VINAY DATE OF THIS ESTIMATE 06/27/25 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 86,925.99 1,982,922.24 SUBTOTAL AMOUNT EARNED 86,925.99 1,982,922.24 ORIGINAL CONTRACT AMOUNT 6,975.00 TOTAL WORK COMPLETED 86,925.99 1,982,922.24 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 86,925.99 1,982,922.24 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 04/18/23 30 12/31/22 12/31/22 06/30/25 445 0 0 0 71% 100% PROGRESS IS SATISFACTORY UNSATIS PROGRESS OVERRIDEN BECAU W H Y ... W H Y ... W H CHAMPANERIA, VINAY RESIDENT ENGINEER