PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 10/21/25 EST. NO. 010 TIME 02:16 PM R.E. NAME: PANDHER, PARAMJIT 04-2Y8604 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0214 16,076.62 E.W. @ F.A.(+) 091625 N 25599 0215 56,799.64 091725 N 27370 0216 15,221.76 091825 N 27371 0217 14,772.07 091925 N 27372 0218 13,652.11 092225 N 27373 0219 13,718.52 092325 N 27374 0220 15,454.01 092425 N 27375 0221 14,461.78 092525 N 27376 0222 42,040.76 092625 N 27377 0223 30,219.42 092925 N 27378 232,416.69 TOTAL THIS ESTIMATE 2,421,974.34 TOTAL PREVIOUS ESTIMATE 2,654,391.03 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 10/21/25 EST. NO. 010 TIME 02:16 PM R.E. NAME: PANDHER, PARAMJIT 04-2Y8604 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 10/21/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-2Y8604 TIME 02:16 PM ESTIMATE NO. 010 BID OPENING 01/03/23 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/25 R.E. NAME: PANDHER, PARAMJIT DATE OF THIS ESTIMATE 10/21/25 LOCATION RERUN PROGRESS ESTIMATE 04-ALA-580-26.2 ----------------------- REDGWICK CONSTRUCTION COMPANY ALA 580&680 VAR LOC 21 HEGENBERGER CT, , INCL EDEN CANYON & OAKLAND 94621 SHERDIAN, SUNOL GRADE - SLIPOUTS FED. AID NO. N O N E SLIDE AND SLIPOUT REPAIR ALONG WB 580 EDEN ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 SLIDE AND SLIPOUT REPAIR ALONG WB LS 7,380.0000 7,380.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 10/21/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-2Y8604 TIME 02:16 PM ESTIMATE NO. 010 BID OPENING 01/03/23 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/25 R.E. NAME: PANDHER, PARAMJIT DATE OF THIS ESTIMATE 10/21/25 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 232,416.69 2,654,391.03 SUBTOTAL AMOUNT EARNED 232,416.69 2,654,391.03 ORIGINAL CONTRACT AMOUNT 7,380.00 TOTAL WORK COMPLETED 232,416.69 2,654,391.03 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 232,416.69 2,654,391.03 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 02/08/23 20 01/04/23 01/04/23 12/31/25 139 558 0 0 55% 100% PROGRESS IS SATISFACTORY UNSATIS PROGRESS OVERRIDEN BECAU PROG SATISFACTORY PANDHER, PARAMJIT RESIDENT ENGINEER