PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 03/03/17 EST. NO. 001 TIME 01:47 PM R.E. NAME: CARTY, RODOLFO 04-3J6904 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- *** THERE ARE NO EXTRA WORK PAYMENTS THIS ESTIMATE *** PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 03/03/17 EST. NO. 001 TIME 01:47 PM R.E. NAME: CARTY, RODOLFO 04-3J6904 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 03/03/17 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-3J6904 TIME 01:47 PM ESTIMATE NO. 001 BID OPENING 05/19/16 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 03/01/17 R.E. NAME: CARTY, RODOLFO DATE OF THIS ESTIMATE 03/03/17 LOCATION RERUN PROGRESS ESTIMATE 04-SM-280-18.6/18.3 ----------------------- ALTA ENGINEERING GROUP, INC IN SAN MATEO COUNTY, IN THE CITY OF 1485 BAYSHORE BLVD #191 MILBRAE, WEST AND 0.1 MILES NORTH SAN FRANCISCO CA 94124 OF UNDERCROSSING OF LARKSPUR DRIVE ON HIGHWAY 280. REPLACE AND UPGRADE PUMPS AND. FED. AID NO. N O N E REPLACE AND UPGRADE PUMPS AND. ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 JOB SITE MANAGEMENT LS 2,000.0000 2,000.00 0.500 1,000.00 0.500 1,000 002 PREPARE WATER POLLUTION CONTROL PROGRAM LS 1,500.0000 1,500.00 1.000 1,500.00 1.000 1,500 003 MODIFY PUMP PLANT LS 467,296.0000 467,296.00 0.680 317,761.28 0.680 317,761 PROGRAM CAS145 PAGE 2 DATE 03/03/17 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-3J6904 TIME 01:47 PM ESTIMATE NO. 001 BID OPENING 05/19/16 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 03/01/17 R.E. NAME: CARTY, RODOLFO DATE OF THIS ESTIMATE 03/03/17 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 320,261.28 320,261.28 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 0.00 0.00 SUBTOTAL AMOUNT EARNED 320,261.28 320,261.28 ORIGINAL CONTRACT AMOUNT 470,796.00 TOTAL WORK COMPLETED 320,261.28 320,261.28 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 320,261.28 320,261.28 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 07/18/16 165 01/24/17 08/01/16 04/18/17 134 11 0 0 68% 81% PROGRESS IS SATISFACTORY CARTY, RODOLFO RESIDENT ENGINEER PROGRAM CAS145 DATE 03/03/17