PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 05/14/20 EST. NO. 008 TIME 01:30 PM R.E. NAME: MUKHERJEE, RABINDRA 04-3Q0504 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0150 3,355.41 E.W. @ F.A.(+) 030220 N 244190 0151 2,977.14 030320 N 244200 0152 3,964.94 030420 N 244210 0153 6,847.00 030520 N 244220 0154 4,788.51 030620 N 244230 0155 4,387.41 030920 N 244240 0156 3,560.55 031020 N 244250 0157 5,202.06 031120 N 244260 0158 2,976.25 031220 N 244270 0159 4,521.82 031320 N 244280 0160 2,135.26 033020 N 243210 0161 4,593.53 033120 N 243220 0162 4,743.74 040120 N 243230 0163 4,787.68 040220 N 243240 0164 4,195.94 040320 N 243250 0165 4,782.92 040720 N 243260 0166 3,875.30 040820 N 243270 0167 3,875.30 040920 N 243280 0168 4,363.80 041020 N 243290 0169 3,875.30 041320 N 243300 0170 3,875.30 041420 N 243310 0171 3,875.30 041520 N 243320 0172 3,981.86 041620 N 243330 0173 1,309.37 032420 N 243790 0176 888.00 042820 N 234600 0177 244.38 042820 N 234610 0178 4,440.00 042920 N 234630 0187 54.00 022420 N 127.20 0188 8,326.74 012320 N CORR 0 0189 17,223.25 042820 N 175.10 0190 93,418.78 042820 N 681249 221,446.84 TOTAL THIS ESTIMATE 2,096,547.46 TOTAL PREVIOUS ESTIMATE 2,317,994.30 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 05/14/20 EST. NO. 008 TIME 01:30 PM R.E. NAME: MUKHERJEE, RABINDRA 04-3Q0504 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 05/14/20 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-3Q0504 TIME 01:30 PM ESTIMATE NO. 008 BID OPENING 04/09/19 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/14/20 R.E. NAME: MUKHERJEE, RABINDRA DATE OF THIS ESTIMATE 05/14/20 LOCATION RERUN PROGRESS ESTIMATE 04-CC-4-24.9/27.0 ----------------------- REDGWICK CONSTRUCTION COMPANY IN PITTSBURGH AND ANTIOCH, FROM 0.1 MILE FERNANDO PACHECO WEST OF CENTURY BLVD. TO 0.1 MILE EAST OF 21 HEGENBERGER CT. CONTA LOMA BLVD. OAKLAND, CA 94621 FED. AID NO. N O N E INJECTION GROUTING AND REPLACE PCC SLABS ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 PAYMENT BOND PREMIUM LS 16,584.0000 16,584.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 05/14/20 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-3Q0504 TIME 01:30 PM ESTIMATE NO. 008 BID OPENING 04/09/19 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/14/20 R.E. NAME: MUKHERJEE, RABINDRA DATE OF THIS ESTIMATE 05/14/20 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 221,446.84 2,317,994.30 SUBTOTAL AMOUNT EARNED 221,446.84 2,317,994.30 ORIGINAL CONTRACT AMOUNT 16,584.00 TOTAL WORK COMPLETED 221,446.84 2,317,994.30 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 221,446.84 2,317,994.30 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 04/09/19 50 05/28/19 04/24/19 08/30/20 235 23 0 0 91% 100% PROGRESS IS SATISFACTORY EMERGENCY PROJECT MUKHERJEE, RABINDRA RESIDENT ENGINEER PROGRAM CAS145 DATE 05/14/20