PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 04/03/26 EST. NO. 001 TIME 02:08 PM R.E. NAME: KIM, JAEYOON 04-3X7404 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0001 14,502.42 E.W. @ F.A.(+) 121725 N 0003.0 0002 19,549.11 011526 N 0004.0 0003 3,011.60 022626 N 0005.0 0004 1,629.55 022726 N 0006.0 38,692.68 TOTAL THIS ESTIMATE 0.00 TOTAL PREVIOUS ESTIMATE 38,692.68 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 04/03/26 EST. NO. 001 TIME 02:08 PM R.E. NAME: KIM, JAEYOON 04-3X7404 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 04/03/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-3X7404 TIME 02:08 PM ESTIMATE NO. 001 BID OPENING 07/02/25 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 04/03/26 R.E. NAME: KIM, JAEYOON DATE OF THIS ESTIMATE 04/03/26 LOCATION RERUN PROGRESS ESTIMATE 04-CC-24-R5.1 ----------------------- BRANNON CORPORATION REPAIR ROADWAY SETTLEMENT, 10492 DOUGHERTY AVE POLYURETHANE INJECTION.RECONSTRUCT HMA MORGAN HILL CA 95037 DIKES AND MGS,EROSION CONTROL. PAVEMENT DELINEATION AND ANY ADDITIONAL WO FED. AID NO. N O N E PAVEMENT DELINEATION AND ANY ADDITIONAL WO ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 PAVEMENT DELINEATION AND ANY ADDITIONAL LS 4,476.0000 4,476.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 04/03/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-3X7404 TIME 02:08 PM ESTIMATE NO. 001 BID OPENING 07/02/25 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 04/03/26 R.E. NAME: KIM, JAEYOON DATE OF THIS ESTIMATE 04/03/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 38,692.68 38,692.68 SUBTOTAL AMOUNT EARNED 38,692.68 38,692.68 ORIGINAL CONTRACT AMOUNT 4,476.00 TOTAL WORK COMPLETED 38,692.68 38,692.68 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 38,692.68 38,692.68 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 10/21/25 30 09/08/25 09/08/25 07/03/26 71 0 0 0 2% 100% PROGRESS IS SATISFACTORY UNSATIS PROGRESS OVERRIDEN BECAU EMERGENCY PROJECT KIM, JAEYOON RESIDENT ENGINEER