PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 11/15/13 EST. NO.01 TIME 08:08 AM R.E. NAME: TSIGELMAN, IGOR 04-4H8004 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0001 29,196.09 E.W. @ F.A.(+) 063013 N L001 0 29,196.09 TOTAL THIS ESTIMATE 0.00 TOTAL PREVIOUS ESTIMATE 29,196.09 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 11/15/13 EST. NO.01 TIME 08:08 AM R.E. NAME: TSIGELMAN, IGOR 04-4H8004 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 11/15/13 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-4H8004 TIME 08:08 AM ESTIMATE NO. 01 BID OPENING 02/21/13 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 11/14/13 R.E. NAME: TSIGELMAN, IGOR DATE OF THIS ESTIMATE 11/15/13 LOCATION PROGRESS ESTIMATE 04-ALA-24-5.9 ----------------- TUTOR-SALIBA CORPORATION IN ALAMEDA/CONTRA COSTA COUNTIES, IN AND 990 FISH RANCH ROAD NEAR OAKLAND, AT CALDECOTT TUNNEL BORES 1, ORINDA, CA 94563 2, AND 3 RECONSTRUCT FIRE SUPPRESSION WATER SYSTEM FED. AID NO. N O N E RECONSTRUCT WATER SUPPLY SYSTEM ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 RECONSTRUCT WATER SUPPLY SYSTEM LS 22,800.0000 22,800.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 11/15/13 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-4H8004 TIME 08:08 AM ESTIMATE NO. 01 BID OPENING 02/21/13 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 11/14/13 R.E. NAME: TSIGELMAN, IGOR DATE OF THIS ESTIMATE 11/15/13 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 29,196.09 29,196.09 SUBTOTAL AMOUNT EARNED 29,196.09 29,196.09 ORIGINAL CONTRACT AMOUNT 22,800.00 TOTAL WORK COMPLETED 29,196.09 29,196.09 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 29,196.09 29,196.09 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 02/21/13 180 09/18/13 09/18/13 03/12/14 106 0 0 0 1% 59% PROGRESS IS SATISFACTORY TSIGELMAN, IGOR RESIDENT ENGINEER PROGRAM CAS145 DATE 11/15/13