PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 06/10/16 EST. NO. 005 TIME 01:34 PM R.E. NAME: FRED BOOSHEHRI 04-4J4304 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0076 66,039.14 E.W. @ F.A.(+) 042516 N 000270 0077 811.41 042716 N 000280 66,850.55 TOTAL THIS ESTIMATE 923,089.35 TOTAL PREVIOUS ESTIMATE 989,939.90 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 06/10/16 EST. NO. 005 TIME 01:34 PM R.E. NAME: FRED BOOSHEHRI 04-4J4304 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 06/10/16 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-4J4304 TIME 01:34 PM ESTIMATE NO. 005 BID OPENING 07/08/15 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/10/16 R.E. NAME: FRED BOOSHEHRI DATE OF THIS ESTIMATE 06/10/16 LOCATION PROGRESS ESTIMATE 04-SM-101-0.0 ----------------- ARNAUDO CONSTRUCTION INC. HENDERSON PUMP HOUSE, EAST PALO ALTO, P. O. BOX 174, 0.5 MILES SOUTH OF TRACY, CA 95378 MARSH ROAD DIRECTOR'S ORDER EMERGENCY F.A. FED. AID NO. N O N E CLEAN PUMP HOUSE DS, REPLACE PUMPS AND CPS ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 CLEAN PUMP HOUSE DRAINAGE SYSTEM (BOND) LS 14,250.0000 14,250.00 1.000 14,250 PROGRAM CAS145 PAGE 2 DATE 06/10/16 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-4J4304 TIME 01:34 PM ESTIMATE NO. 005 BID OPENING 07/08/15 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/10/16 R.E. NAME: FRED BOOSHEHRI DATE OF THIS ESTIMATE 06/10/16 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 14,250.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 66,850.55 989,939.90 SUBTOTAL AMOUNT EARNED 66,850.55 1,004,189.90 ORIGINAL CONTRACT AMOUNT 14,250.00 TOTAL WORK COMPLETED 66,850.55 1,004,189.90 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 66,850.55 1,004,189.90 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 07/08/15 80 08/24/15 08/24/15 08/31/16 105 65 0 0 67% 100% PROGRESS IS SATISFACTORY UNSATIS PROGRESS OVERRIDEN BECAU W H Y ... W H Y ... W H FRED BOOSHEHRI RESIDENT ENGINEER PROGRAM CAS145 DATE 06/10/16