PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 01/08/18 EST. NO. 009 TIME 10:38 AM R.E. NAME: NIKZAD, ALI 04-4K2304 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0359 5,427.86 E.W. @ F.A.(+) 122117 Y 0356.0 0360 2,288.71 122017 Y 0357.0 0361 1,409.85 122117 Y 0358.0 0362 5,733.09 121917 Y 0359.0 0363 20,050.00 010118 Y 0347.1 0364 15,680.14 010118 Y 0347.2 0365 43,486.13 103017 Y 0351.1 94,075.78 TOTAL THIS ESTIMATE 2,057,197.37 TOTAL PREVIOUS ESTIMATE 2,151,273.15 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 01/08/18 EST. NO. 009 TIME 10:38 AM R.E. NAME: NIKZAD, ALI 04-4K2304 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- ADMINISTRATIVE MISSING FORM CEM2302 -10,000.00 008 0.00 -10,000.00 TOTAL DEDUCTIONS 0.00 -10,000.00 PROGRAM CAS145 PAGE 1 DATE 01/08/18 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-4K2304 TIME 10:38 AM ESTIMATE NO. 009 BID OPENING 03/07/17 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/21/17 R.E. NAME: NIKZAD, ALI DATE OF THIS ESTIMATE 01/08/18 LOCATION PROGRESS ESTIMATE 04-SCL-17-5.8 ----------------- AVAR CONSTRUCTION, INC. IN SANTA CLARA COUNTY, NEAR LOS GATOS, 47375 FREMONT BLVD AT 0.7 MILE SOUTH OF EAST MAIN STREET FREMONT, CA 94538 FED. AID NO. N O N E CONSTRUCT SOIL NAIL WALL ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 EMERGENCY CONTRACT (PAYMENT BOND) LS 20,052.0000 20,052.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 01/08/18 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-4K2304 TIME 10:38 AM ESTIMATE NO. 009 BID OPENING 03/07/17 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/21/17 R.E. NAME: NIKZAD, ALI DATE OF THIS ESTIMATE 01/08/18 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 94,075.78 2,151,273.15 SUBTOTAL AMOUNT EARNED 94,075.78 2,151,273.15 ORIGINAL CONTRACT AMOUNT 20,052.00 TOTAL WORK COMPLETED 94,075.78 2,151,273.15 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 -10,000.00 TOTAL 94,075.78 2,141,273.15 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 03/07/17 50 04/24/17 04/24/17 12/21/17 0 0 0 0 87% 0% PROGRESS IS SATISFACTORY NIKZAD, ALI RESIDENT ENGINEER PROGRAM CAS145 DATE 01/08/18