PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 06/21/18 EST. NO. 010 TIME 10:15 AM R.E. NAME: CHOI, GINA 04-4S6604 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0265 1,655.28 E.W. @ F.A.(+) 052118 N 0022 0 1,655.28 TOTAL THIS ESTIMATE 529,577.71 TOTAL PREVIOUS ESTIMATE 531,232.99 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 06/21/18 EST. NO. 010 TIME 10:15 AM R.E. NAME: CHOI, GINA 04-4S6604 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- ADMINISTRATIVE MISSIMG CEM 4401 -10,000.00 004 CEM 4401 SUBMITTED 10,000.00 010 10,000.00 0.00 TOTAL DEDUCTIONS 10,000.00 0.00 PROGRAM CAS145 PAGE 1 DATE 06/21/18 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-4S6604 TIME 10:15 AM ESTIMATE NO. 010 BID OPENING 06/15/17 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/30/17 R.E. NAME: CHOI, GINA DATE OF THIS ESTIMATE 06/21/18 LOCATION PROGRESS ESTIMATE 04-MRN-1-8.1 ----------------- THOMPSON BUILDERS CORPORATION IN MARIN COUNTY, NEAR STINSON BEACH, AT 250 BEL MARIN KEYS BLVD., 2.2 MILES NORTH OF MUIR BEACH ROAD BLDG A, NOVATO, CA 94949 FED. AID NO. NH- ( ) CONST SOLDIER PILE WALL AND RSP ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 PAYMENT BOND PREMIUM LS 13,836.0000 13,836.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 06/21/18 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 04-4S6604 TIME 10:15 AM ESTIMATE NO. 010 BID OPENING 06/15/17 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/30/17 R.E. NAME: CHOI, GINA DATE OF THIS ESTIMATE 06/21/18 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 1,655.28 531,232.99 SUBTOTAL AMOUNT EARNED 1,655.28 531,232.99 ORIGINAL CONTRACT AMOUNT 13,836.00 TOTAL WORK COMPLETED 1,655.28 531,232.99 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 10,000.00 0.00 TOTAL 11,655.28 531,232.99 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 06/15/17 180 06/28/17 00/00/00 06/30/18 133 0 0 0 30% 75% PROGRESS IS SATISFACTORY UNSATIS PROGRESS OVERRIDDEN AND PCNT TIME ELAPSED INPUT BECAUSE TIME EXTENSION CHOI, GINA RESIDENT ENGINEER PROGRAM CAS145 DATE 06/21/18