PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 06/15/10 EST. NO.08 TIME 03:46 PM R.E. NAME: RICHARDS, TIM 05-0F7104 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0002 878.19 E.W. @ F.A.(+) 010810 N 002 0 0003 642.35 032410 N 003 0 0004 1,989.62 032510 N 4 0 3,510.16 TOTAL THIS ESTIMATE -1,328.15 TOTAL PREVIOUS ESTIMATE 2,182.01 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 06/15/10 EST. NO.08 TIME 03:46 PM R.E. NAME: RICHARDS, TIM 05-0F7104 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- LABOR COMPLIANCE VIOLATION MISS PAYROLLS -1,000.00 05 MISS PAYROLLS -10,000.00 07 REC'D PAYROLLS EST05 1,000.00 07 REL EST #07 10,000.00 08 10,000.00 0.00 OVERBID ITEMS OVERBID ITEM NO. 001 -1,653.00 06 0.00 -1,653.00 TOTAL DEDUCTIONS 10,000.00 -1,653.00 PROGRAM CAS145 PAGE 1 DATE 06/15/10 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 05-0F7104 TIME 03:46 PM ESTIMATE NO. 08 BID OPENING 06/23/09 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/20/10 R.E. NAME: RICHARDS, TIM DATE OF THIS ESTIMATE 06/15/10 LOCATION PROGRESS ESTIMATE 05-SLO-46-49.5/ .0 ----------------- SPECIALTY CONSTRUCTION INC IN SAN LUIS OBISPO CO NEAR SHANDON 645 CLARION COURT AT THE SHANDON SAFETY ROADSIDE REST SAN LUIS OBISPO CA 93401 AREA FED. AID NO. SARR-P046(42)E ,A-P046(42)E REHABILITATE ROADSIDE REST AREA ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 PROGRESS SCHEDULE (CRITICAL PATH METHOD) LS 8,306.0000 8,306.00 0.500 4,153.00 02 SMALL BUSINESS UTILIZATION REPORT EA 250.0000 2,500.00 3.000 750.00 03 TEMPORARY FENCE (TYPE CL-6) LF 3.3200 564.40 152.000 504.64 04 TEMPORARY 16' CHAIN LINK GATE EA 1,661.0000 1,661.00 1.000 1,661.00 (TYPE CL-6) 05 TEMPORARY FENCE (TYPE ESA) LF 6.6400 4,980.00 750.000 4,980.00 06 CONSTRUCTION SITE MANAGEMENT LS 10,521.2500 10,521.25 0.072 757.53 0.511 5,376.36 07 PREPARE STORM WATER POLLUTION LS 1,661.2500 1,661.25 0.700 1,162.88 PREVENTION PLAN 08 TEMPORARY FIBER ROLL LF 2.8700 3,444.00 886.000 2,542.82 09 TEMPORARY GRAVEL BAG BERM LF 6.7300 673.00 145.000 975.85 10 TEMPORARY CONCRETE WASHOUT FACILITY EA 2,082.1000 2,082.10 0.500 1,041.05 0.500 1,041.05 11 TEMPORARY CONSTRUCTION ENTRANCE EA 3,383.4100 3,383.41 1.000 3,383.41 12 TEMPORARY COVER SQYD 0.3400 1,156.00 0.000 0.00 13 TEMPORARY CHECK DAM LF 11.3000 248.60 22.000 248.60 22.000 248.60 14 STREET SWEEPING LS 886.0000 886.00 0.368 326.05 15 CONSTRUCTION AREA SIGNS LS 3,627.0600 3,627.06 0.700 2,538.94 16 TRAFFIC CONTROL SYSTEM LS 2,436.5000 2,436.50 0.500 1,218.25 17 RECONSTRUCT CHAIN LINK FENCE LF 21.0400 6,732.80 0.000 0.00 18 RESET ROADSIDE SIGN (ONE POST) EA 193.8100 1,356.67 0.000 0.00 19 RESET BOULDER EA 155.0500 775.25 0.000 0.00 20 CLEARING AND GRUBBING LS 27,948.0000 27,948.00 0.900 25,153.20 21 ROADWAY EXCAVATION CY 21.9600 17,787.60 600.000 13,176.00 600.000 13,176.00 22 IMPORTED BORROW CY 9.6000 17,280.00 0.000 0.00 PROGRAM CAS145 PAGE 2 DATE 06/15/10 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 05-0F7104 TIME 03:46 PM ESTIMATE NO. 08 BID OPENING 06/23/09 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/20/10 R.E. NAME: RICHARDS, TIM DATE OF THIS ESTIMATE 06/15/10 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 23 DECOMPOSED GRANITE SQFT 4.9800 28,884.00 0.000 0.00 24 HIGHWAY PLANTING LS 74,480.0000 74,480.00 0.000 0.00 25 EROSION CONTROL (SYNTHETIC TURF) SQFT 11.0700 14,391.00 0.000 0.00 26 EROSION CONTROL (TYPE D) ACRE 4,985.0000 28,913.00 0.000 0.00 (SEED MIX 1) 27 EROSION CONTROL (TYPE D) ACRE 5,870.0000 4,109.00 0.000 0.00 (SEED MIX 2) 28 MOVE-IN/MOVE-OUT (EROSION CONTROL) EA 111.0000 333.00 0.000 0.00 29 PLANT (GROUP WP) EA 12.2000 7,930.00 0.000 0.00 30 MAINTAIN EXISTING PLANTED AREAS LS 5,320.0000 5,320.00 0.000 0.00 31 PLANT ESTABLISHMENT WORK LS 24,012.0000 24,012.00 0.000 0.00 32 IRRIGATION SYSTEM LS 71,990.0000 71,990.00 0.000 0.00 33 IRRIGATION SLEEVE LF 18.0000 11,160.00 321.000 5,778.00 321.000 5,778.00 34 10" CORRUGATED HIGH DENSITY LF 36.0000 1,152.00 14.000 504.00 14.000 504.00 POLYETHYLENE PIPE CONDUIT 35 PARKING AREA SEAL COAT TON 1,086.0000 21,720.00 0.000 0.00 36 ROADSIDE PAVING (MISCELLANEOUS AREAS) SQYD 198.0000 10,296.00 0.000 0.00 37 FURNISH SINGLE SHEET ALUMINUM SIGN SQFT 61.0000 3,172.00 0.000 0.00 (0.063"-UNFRAMED) 38 FURNISH SINGLE SHEET ALUMINUM SIGN SQFT 61.0000 2,135.00 0.000 0.00 (0.080"-UNFRAMED) 39 WASTEWATER SIGN EA 554.0000 554.00 0.000 0.00 40 ROADSIDE SIGN - ONE POST EA 277.0000 3,324.00 0.000 0.00 41 ROADSIDE SIGN - TWO POST EA 388.0000 1,164.00 0.000 0.00 42 INSTALL ROADSIDE SIGN PANEL ON EA 222.0000 444.00 0.000 0.00 EXISTING POST 43 DRAINAGE INLET MARKER EA 139.0000 1,112.00 0.000 0.00 44 MINOR CONCRETE PAVEMENT CY 458.0000 146,560.00 105.900 48,502.20 105.900 48,502.20 45 MINOR CONCRETE (MOW CURB) LF 9.9200 17,558.40 0.000 0.00 46 PRECAST CONCRETE RAIL FENCE LF 30.5000 35,075.00 0.000 0.00 47 CHAIN LINK FENCE (TYPE CL-6, SLATTED) LF 39.0000 3,120.00 0.000 0.00 48 OBJECT MARKER (TYPE K) EA 82.0000 492.00 0.000 0.00 49 PAVEMENT MARKER (NON-REFLECTIVE) EA 5.0000 2,700.00 0.000 0.00 PROGRAM CAS145 PAGE 3 DATE 06/15/10 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 05-0F7104 TIME 03:46 PM ESTIMATE NO. 08 BID OPENING 06/23/09 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/20/10 R.E. NAME: RICHARDS, TIM DATE OF THIS ESTIMATE 06/15/10 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 50 EXTERIOR AREA LIGHT EA 5,426.0000 37,982.00 0.000 0.00 51 EXTERIOR SPOT LIGHT EA 945.0000 1,890.00 0.000 0.00 52 BUILDING WORK LS 2162,725.0000 2,162,725.00 0.046 99,485.35 0.549 1,187,336.03 53 PRECAST CONCRETE PICNIC TABLE EA 998.0000 3,992.00 0.000 0.00 54 PRECAST CONCRETE TRASH CONTAINER EA 875.0000 11,375.00 0.000 0.00 55 PRECAST CONCRETE RECYCLE CONTAINER EA 875.0000 5,250.00 0.000 0.00 56 PRECAST CONCRETE TRASH CONTAINER EA 610.0000 1,220.00 0.000 0.00 (ASH TRAY) 57 PRECAST CONCRETE BENCH EA 770.0000 1,540.00 0.000 0.00 58 PRECAST CONCRETE BENCH WITH BACK EA 1,025.0000 3,075.00 0.000 0.00 59 PRECAST CONCRETE BENCH PLANTER EA 3,900.0000 3,900.00 0.000 0.00 60 PRECAST CONCRETE REMOVABLE BOLLARD EA 670.0000 1,340.00 0.000 0.00 61 INTERPRETIVE DISPLAY EA 48,885.0000 48,885.00 0.500 24,442.50 62 PREFABRICATED PET WASTE BAG DISPENSER EA 560.0000 1,120.00 0.000 0.00 63 TREE GRATE EA 1,995.0000 15,960.00 4.000 7,980.00 4.000 7,980.00 PROGRAM CAS145 PAGE 4 DATE 06/15/10 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 05-0F7104 TIME 03:46 PM ESTIMATE NO. 08 BID OPENING 06/23/09 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/20/10 R.E. NAME: RICHARDS, TIM DATE OF THIS ESTIMATE 06/15/10 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 177,472.73 1,343,734.78 ADJUSTMENT OF COMPENSATION 0.00 -4,967.22 EXTRA WORK 3,510.16 7,149.23 SUBTOTAL AMOUNT EARNED 180,982.89 1,345,916.79 ORIGINAL CONTRACT AMOUNT 2,942,365.29 TOTAL WORK COMPLETED 180,982.89 1,345,916.79 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 10,000.00 -1,653.00 TOTAL 190,982.89 1,344,263.79 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE MAXIMUM CONTRACT OVERBID VALUE PRICE AMOUNT 001 PROGRESS SCHEDULE (CRITICAL PATH METHOD) 5,000.00 8,306.00 3,306.00 DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 08/12/09 530 11/18/09 10/06/09 01/06/12 143 30 0 0 46% 51% PROGRESS IS SATISFACTORY RICHARDS, TIM RESIDENT ENGINEER PROGRAM CAS145 DATE 06/15/10