PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 02/26/09 EST. NO.02 TIME 09:52 AM R.E. NAME: BALLENTINE, DAVID 05-0R9604 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0010 28,317.19 E.W. @ F.A.(+) 121208 N AEC001 0011 18,894.48 121308 N AEC002 0012 4,511.00 121908 N AEC003 0013 3,653.31 010709 N CPCO10 0014 9,073.49 010209 N 10 0 0016 342.17 010609 N 12 0 0017 9,147.59 010809 N 13 0 0018 7,654.31 010909 N 14 0 0019 15,235.11 011209 N 15 0 0020 10,007.62 011309 N 16 0 0021 8,018.59 011409 N 17 0 0022 1,125.91 010809 N CPCO20 0023 1,125.91 010909 N CPCO30 0024 8,358.01 011509 N 18 0 0025 4,702.62 011209 N CPCO40 0026 3,035.11 011309 N CPCO50 0027 3,765.50 011409 N CPCO60 0028 2,855.78 011509 N CPCO70 0029 2,610.99 011609 N CPCO80 0030 2,884.16 011909 N CPCO90 0031 5,544.89 012009 N CPCO10 0034 22,324.25 012009 N 21 0 0041 5,677.69 012909 N 28 0 178,865.68 TOTAL THIS ESTIMATE 75,136.04 TOTAL PREVIOUS ESTIMATE 254,001.72 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 02/26/09 EST. NO.02 TIME 09:52 AM R.E. NAME: BALLENTINE, DAVID 05-0R9604 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 02/26/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 05-0R9604 TIME 09:52 AM ESTIMATE NO. 02 BID OPENING 11/13/08 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 02/20/09 R.E. NAME: BALLENTINE, DAVID DATE OF THIS ESTIMATE 02/26/09 LOCATION PROGRESS ESTIMATE 05-SB-192-4.8/6.2 ----------------- SOUZA CONSTRUCTION, INC THE TEA FIRE, SIDE SLOPE DAMAGE. EROSION PO BOX 3810 CONTROL, DRAINAGE REPAIR, PLACE RSP, SAN LUIS OBISPO, CA 93403 REPAIR TWO RETAINING WALLS FED. AID NO. N O N E EROSION CONTROL,DRAINAGE/RETNG WALL REPAIR ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 FIRE DAMAGE REPAIR LS 7,500.0000 7,500.00 0.000 0.00 PROGRAM CAS145 PAGE 2 DATE 02/26/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 05-0R9604 TIME 09:52 AM ESTIMATE NO. 02 BID OPENING 11/13/08 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 02/20/09 R.E. NAME: BALLENTINE, DAVID DATE OF THIS ESTIMATE 02/26/09 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 178,865.68 254,001.72 SUBTOTAL AMOUNT EARNED 178,865.68 254,001.72 ORIGINAL CONTRACT AMOUNT 7,500.00 TOTAL WORK COMPLETED 178,865.68 254,001.72 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 178,865.68 254,001.72 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 11/24/08 90 12/12/08 00/00/00 05/15/09 31 15 0 0 17% 34% PROGRESS IS SATISFACTORY BALLENTINE, DAVID RESIDENT ENGINEER PROGRAM CAS145 DATE 02/26/09