PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 07/19/13 EST. NO.12 TIME 11:16 AM R.E. NAME: WILSON, JENNIFER 05-0S9404 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0047 709.50 E.W. @ F.A.(+) 053113 N 47 0 709.50 TOTAL THIS ESTIMATE 205,000.61 TOTAL PREVIOUS ESTIMATE 205,710.11 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 07/19/13 EST. NO.12 TIME 11:16 AM R.E. NAME: WILSON, JENNIFER 05-0S9404 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 07/19/13 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 05-0S9404 TIME 11:16 AM ESTIMATE NO. 12 BID OPENING 01/25/10 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 07/20/13 R.E. NAME: WILSON, JENNIFER DATE OF THIS ESTIMATE 07/19/13 LOCATION PROGRESS ESTIMATE 05-MON-1-46.8/46.8 ----------------- GRANITE CONSTRUCTION HWY 1 AT THE BIG SUR LODGE BIG SUR PARK PO BOX 720 CAMPGROUNDS WATSONVILLE CA 95077 FED. AID NO. N O N E PLACE ROCK SLOPE PROTECTION ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 PLACE ROCK SLOPE PROTECTION LS 4,625.0000 4,625.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 07/19/13 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 05-0S9404 TIME 11:16 AM ESTIMATE NO. 12 BID OPENING 01/25/10 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 07/20/13 R.E. NAME: WILSON, JENNIFER DATE OF THIS ESTIMATE 07/19/13 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 709.50 205,710.11 SUBTOTAL AMOUNT EARNED 709.50 205,710.11 ORIGINAL CONTRACT AMOUNT 4,625.00 TOTAL WORK COMPLETED 709.50 205,710.11 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 709.50 205,710.11 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 01/25/10 30 01/29/10 00/00/00 08/31/13 19 847 0 0 23% 63% PROGRESS IS SATISFACTORY WILSON, JENNIFER RESIDENT ENGINEER PROGRAM CAS145 DATE 07/19/13