PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 05/05/20 EST. NO. 004 TIME 05:13 PM R.E. NAME: BALLENTINE, DAVID 05-1M6104 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0179 12,341.47 E.W. @ F.A.(+) 031120 N 0206.0 0181 7,989.75 031320 N 0208.0 0189 18,435.17 032420 N 0216.0 0204 11,142.02 031320 N 0181.0 0206 4,336.76 021420 N 0183.0 0211 5,735.48 022620 N 0188.0 0227 1,603.25 032520 N 0229.0 0232 151.25 030220 N 0234.0 0234 11,778.33 032620 N 0236.0 0236 692.33 010720 N 0238.0 0237 593.42 022820 N 0239.0 0238 395.61 022820 N 0240.0 0243 2,394.52 040120 N 0245.0 0249 9,213.91 040120 N 0251.0 0256 783.73 040920 N 0258.0 0262 8,746.25 010920 N 0180.1 0263 7,665.18 030420 N 0199.1 0264 3,053.58 030520 N 0200.1 0265 18,305.03 031820 N 0211.1 125,357.04 TOTAL THIS ESTIMATE 1,466,268.85 TOTAL PREVIOUS ESTIMATE 1,591,625.89 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 05/05/20 EST. NO. 004 TIME 05:13 PM R.E. NAME: BALLENTINE, DAVID 05-1M6104 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 05/05/20 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 05-1M6104 TIME 05:13 PM ESTIMATE NO. 004 BID OPENING 11/27/19 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/05/20 R.E. NAME: BALLENTINE, DAVID DATE OF THIS ESTIMATE 05/05/20 LOCATION PROGRESS ESTIMATE 05-SB-154-24.5/31.5 ----------------- GRANITE CONSTRUCTION COMPANY REMOVE & REPLACE FIRE DAMAGED GUARDRAIL, PO BOX 6744 DRAINAGE SYSTEMS, ROCK FALL BARRIERS & SANTA BARBARA, CA 93160 DAMAGED SIGNS. EROSION & TRAFFIC CONTROL DIRS EFA 05A2222 FED. AID NO. N O N E REPAIR DAMAGE CAUSED BY THE CAVE FIRE ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 REPAIR FIRE DAMAGE (BOND PREMIUM) LS 6,400.0000 6,400.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 05/05/20 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 05-1M6104 TIME 05:13 PM ESTIMATE NO. 004 BID OPENING 11/27/19 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/05/20 R.E. NAME: BALLENTINE, DAVID DATE OF THIS ESTIMATE 05/05/20 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 125,357.04 1,591,625.89 SUBTOTAL AMOUNT EARNED 125,357.04 1,591,625.89 ORIGINAL CONTRACT AMOUNT 6,400.00 TOTAL WORK COMPLETED 125,357.04 1,591,625.89 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 125,357.04 1,591,625.89 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 11/27/19 30 11/27/19 11/27/19 06/30/20 670 0 0 0 86% 100% PROGRESS IS SATISFACTORY PROGRESS IS SATISFACTORY BALLENTINE, DAVID RESIDENT ENGINEER PROGRAM CAS145 DATE 05/05/20