PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 05/22/25 EST. NO. 029 TIME 11:26 AM R.E. NAME: MURDOCK,KEVIN/ENGLER, JAIME 05-1R1404 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0499 5,875.12 E.W. @ F.A.(+) 111323 N 0334.0 0502 20,848.64 111523 N 0337.0 0625 6,851.18 121123 N 0365.0 0677 6,194.00 012224 N 0429.0 0690 1,902.80 122623 N 0404.0 0807 103,756.87 022224 N 0519.0 0807-1 -103,756.87 022224 N 0519.0 DAO CORRECTING ENTRY 0807-2 102,451.87 022224 N 0519.0 DAO CORRECTING ENTRY 0965 43,829.31 032924 N 0619.0 0979 39.74 030625 N 256505 0980 2,174.59 030425 N 0628.0 0981 3,550.11 030625 N 0629.0 0982 702.10 030725 N 0630.0 0983 3,479.20 031025 N 0631.0 0984 492.74 031125 N 0632.0 0985 1,135.92 031925 N 0633.0 0986 1,229.49 032025 N 0634.0 0987 973.66 032125 N 0635.0 0988 51,808.00 033025 N 0636.0 0988-1 -51,808.00 033025 N 0636.0 DAO CORRECTING ENTRY 0988-2 28,318.40 033025 N 0636.0 DAO CORRECTING ENTRY 0989 21,876.80 033025 N 0637.0 0990 4,125.57 032625 N 0638.0 0991 41,140.00 041425 N 0639.0 0992 3,354.87 033125 N 0640.0 0993 1,155.17 042825 N 0641.0 301,701.28 TOTAL THIS ESTIMATE 14,865,451.62 TOTAL PREVIOUS ESTIMATE 15,167,152.90 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 05/22/25 EST. NO. 029 TIME 11:26 AM R.E. NAME: MURDOCK,KEVIN/ENGLER, JAIME 05-1R1404 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- ADMINISTRATIVE ANNUAL CEM-4401 2023 -10,000.00 012 0.00 -10,000.00 LABOR COMPLIANCE VIOLATION MISS PAYROLLS -10,000.00 005 MISS PAYROLLS -4,000.00 007 MISS PAYROLLS -10,000.00 011 MISS PAYROLLS -10,000.00 012 MISS PAYROLLS -10,000.00 014 RECD PAYROLLS 11 10,000.00 014 MISS PAYROLLS -6,000.00 016 RECD PAYROLLS 14 10,000.00 016 RECD PAYROLLS 5 & 17 14,000.00 018 MISSING PAYROLLS -4,000.00 021 REC'D PAYROLLS 16&21 10,000.00 024 MISSING PAYROLLS -5,000.00 025 REC'D PAYROLLS #12 10,000.00 025 MISSING PAYROLLS -5,000.00 026 REC'D PAYROLLS 25&26 10,000.00 027 MISSING PAYROLLS -10,000.00 029 -10,000.00 -10,000.00 TOTAL DEDUCTIONS -10,000.00 -20,000.00 PROGRAM CAS145 PAGE 1 DATE 05/22/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 05-1R1404 TIME 11:26 AM ESTIMATE NO. 029 BID OPENING 05/15/23 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/20/25 R.E. NAME: MURDOCK,KEVIN/ENGLER, JAIME DATE OF THIS ESTIMATE 05/22/25 LOCATION PROGRESS ESTIMATE 05-SB-101-47.0/47.3 ----------------- CALPORTLAND CONSTRUCTION GAVIOTA CREEK SCOUR REPAIRS, SB CNTY 101 @ 1625 E DONOVAN RD GAVIOTA TUNNELS. REPAIR SECANT PILE WALL & SANTA MARIA, CA 93454 REPAIR EMBANKMENT. DIRS EFA 05A2625 FED. AID NO. N O N E GAVIOTA CREEK REPAIRS ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 GAVIOTA CREEK REPAIRS (BOND PREMIUM) LS 75,000.0000 75,000.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 05/22/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 05-1R1404 TIME 11:26 AM ESTIMATE NO. 029 BID OPENING 05/15/23 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/20/25 R.E. NAME: MURDOCK,KEVIN/ENGLER, JAIME DATE OF THIS ESTIMATE 05/22/25 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 301,701.28 15,167,152.90 SUBTOTAL AMOUNT EARNED 301,701.28 15,167,152.90 ORIGINAL CONTRACT AMOUNT 75,000.00 TOTAL WORK COMPLETED 301,701.28 15,167,152.90 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS -10,000.00 -20,000.00 TOTAL 291,701.28 15,147,152.90 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 05/26/23 100 01/13/23 01/13/23 05/30/25 232 39 0 0 87% 100% PROGRESS IS SATISFACTORY MURDOCK,KEVIN/ENGLER, JAIME RESIDENT ENGINEER