PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 04/08/26 EST. NO. 001 TIME 01:50 PM R.E. NAME: SANDHU, MANDIP 05-2A0504 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0001 45,790.99 E.W. @ F.A.(+) 022026 N 01 0002 23,898.94 022026 N 02 0003 2,238.82 021926 N 03 0004 25,581.00 022026 N 04 0005 16,434.39 022126 N 05 0006 2,331.99 022226 N 06 0007 1,828.90 022326 N 07 0008 1,750.63 022426 N 08 0009 2,794.03 022526 N 09 0010 1,484.77 022626 N 10 0011 3,477.17 022726 N 11 0012 2,379.55 022826 N 12 0013 2,331.99 030126 N 13 0014 11,633.63 030226 N 14 0015 9,907.34 030326 N 15 0017 10,859.22 030526 N 17 0018 7,345.86 030626 N 18 0020 2,331.99 030826 N 20 0021 1,921.69 030926 N 21 0022 1,484.77 031026 N 22 0023 1,484.77 031126 N 23 0025 1,669.75 031326 N 25 180,962.19 TOTAL THIS ESTIMATE 0.00 TOTAL PREVIOUS ESTIMATE 180,962.19 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 04/08/26 EST. NO. 001 TIME 01:50 PM R.E. NAME: SANDHU, MANDIP 05-2A0504 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 04/08/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 05-2A0504 TIME 01:50 PM ESTIMATE NO. 001 BID OPENING 02/18/26 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 04/08/26 R.E. NAME: SANDHU, MANDIP DATE OF THIS ESTIMATE 04/08/26 LOCATION RERUN PROGRESS ESTIMATE 05-MON-1-542.0/55.6 ----------------------- 05-MON-1-542.0/54.2 TOP TIER GRADING LLC PLACE TEMP RAILING,INSTALL TEMP. SIGNAL 8305 PRUNEDALE N.RD #155 STABILIZE SITE AND TRAFFIC CONTROL SALINAS, CA 93907 EMBANKMENT STABILIZATION.GEOTECH EXPLORE DIRS EFA 05A FED. AID NO. N O N E STABILIZE SITE,TEMP RAIL & SIGNAL, TC ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 STBLZ SITE,TEMP RAIL&SIGNAL,TC(BONDPREM) LS 10,895.0000 10,895.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 04/08/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 05-2A0504 TIME 01:50 PM ESTIMATE NO. 001 BID OPENING 02/18/26 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 04/08/26 R.E. NAME: SANDHU, MANDIP DATE OF THIS ESTIMATE 04/08/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 180,962.19 180,962.19 SUBTOTAL AMOUNT EARNED 180,962.19 180,962.19 ORIGINAL CONTRACT AMOUNT 10,895.00 TOTAL WORK COMPLETED 180,962.19 180,962.19 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 180,962.19 180,962.19 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 04/03/26 150 02/18/26 02/18/26 04/30/26 30 0 0 0 8% 20% PROGRESS IS SATISFACTORY PROGRESS IS SATISFACTORY SANDHU, MANDIP RESIDENT ENGINEER