PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 12/22/05 EST. NO.02 TIME 05:30 AM R.E. NAME: HISHAM ALNATOUR 06-0C2004 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- *** THERE ARE NO EXTRA WORK PAYMENTS THIS ESTIMATE *** PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 12/22/05 EST. NO.02 TIME 05:30 AM R.E. NAME: HISHAM ALNATOUR 06-0C2004 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 12/22/05 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 06-0C2004 TIME 05:30 AM ESTIMATE NO. 02 BID OPENING 02/02/05 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/20/05 R.E. NAME: HISHAM ALNATOUR DATE OF THIS ESTIMATE 12/22/05 LOCATION PROGRESS ESTIMATE 06-KER-58-46.1/51.6 ----------------- GRIFFITH COMPANY IN KERN COUNTY IN AND NEAR P.O. BOX 70157 BAKERSFIELD FROM ALLEN ROAD TO BAKERSFIELD, CA. 93387 CAMINO DEL RIO COURT FED. AID NO. N O N E ASPHALT CONCRETE OVERLAY ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 PREPARE WATER POLLUTION CONTROL LS 900.0000 900.00 0.250 225.00 1.000 900.00 PROGRAM 02 WATER POLLUTION CONTROL LS 5,000.0000 5,000.00 0.200 1,000.00 0.950 4,750.00 03 CONSTRUCTION AREA SIGNS LS 6,000.0000 6,000.00 0.100 600.00 0.900 5,400.00 S) 04 TRAFFIC CONTROL SYSTEM LS 20,490.0000 20,490.00 0.250 5,122.50 1.000 20,490.00 S) 05 PORTABLE CHANGEABLE MESSAGE SIGN LS 2,500.0000 2,500.00 0.250 625.00 1.000 2,500.00 S) 06 ASPHALTIC EMULSION (POLYMER MODIFIED) TONN 325.0000 68,250.00 128.680 41,821.00 07 GAP GRADED POLYMER MODIFIED ASPHALT TONN 133.0000 1,077,300.00 8,639.920 1,149,109.36 CONCRETE (BONDED WEARING COURSE) 08 THERMOPLASTIC PAVEMENT MARKING M2 29.0000 33,640.00 1,160.000 33,640.00 1,160.000 33,640.00 S) 09 200 MM THERMOPLASTIC TRAFFIC STRIPE M 2.1000 8,820.00 4,200.000 8,820.00 4,200.000 8,820.00 S) 10 100 MM THERMOPLASTIC TRAFFIC STRIPE M 0.6500 12,545.00 14,397.000 9,358.05 14,397.000 9,358.05 S) (BROKEN 10.98 M - 3.66 M) 11 PAVEMENT MARKER (RETROREFLECTIVE) EA 3.2000 6,176.00 1,930.000 6,176.00 1,930.000 6,176.00 S) PROGRAM CAS145 PAGE 2 DATE 12/22/05 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 06-0C2004 TIME 05:30 AM ESTIMATE NO. 02 BID OPENING 02/02/05 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/20/05 R.E. NAME: HISHAM ALNATOUR DATE OF THIS ESTIMATE 12/22/05 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 65,566.55 1,282,964.41 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 0.00 0.00 SUBTOTAL AMOUNT EARNED 65,566.55 1,282,964.41 ORIGINAL CONTRACT AMOUNT 1,241,621.00 TOTAL WORK COMPLETED 65,566.55 1,282,964.41 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 65,566.55 1,282,964.41 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE PROGRAM N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 02/28/05 30 10/22/05 03/15/05 01/03/06 25 168 0 4 97% 70% PROGRESS IS SATISFACTORY HISHAM ALNATOUR RESIDENT ENGINEER PROGRAM CAS145 PAGE 3 DATE 12/22/05