PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 05/31/16 EST. NO. 007 TIME 09:07 AM R.E. NAME: MENGONI, MARK 06-0U3304 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0053 11,630.92 E.W. @ F.A.(+) 111615 N 0060.0 0054 18,931.85 111915 N 0063.0 0055 17,389.94 112015 N 0064.0 0057 14,928.09 111815 N 0062.0 0059 7,417.10 112415 N 0067.0 0060 4,022.49 112515 N 0068.0 0094 9,499.32 120115 N 0070.0 0095 10,330.61 120215 N 0071.0 0120 8,783.45 123115 N 0101.0 0125 8,191.49 011216 N 0109.0 0127 7,658.87 011416 N 0111.0 0135 10,772.86 012016 N 0116.0 0172 2,138.30 110315 N 0050.1 0173 4,982.65 110415 N 0051.1 0175 9,380.31 110615 N 0053.1 0177 13,182.33 022216 N 0145.0 0178 13,645.49 022316 N 0146.0 0180 11,988.70 022516 N 0148.0 0181 14,933.53 022616 N 0149.0 0182 484.72 022616 N 0150.0 0189 1,456.25 030116 N 0155.0 0191 609.46 030216 N 0157.0 0207 7,038.28 010516 N 0103.0 0208 8,420.62 010616 N 0104.0 0233 7,269.54 051016 N 0212.0 0235 5,639.32 042016 N 0201.0 0236 8,706.82 042116 N 0202.0 0237 4,884.97 042216 N 0203.0 244,318.28 TOTAL THIS ESTIMATE 2,802,816.62 TOTAL PREVIOUS ESTIMATE 3,047,134.90 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 05/31/16 EST. NO. 007 TIME 09:07 AM R.E. NAME: MENGONI, MARK 06-0U3304 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 05/31/16 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 06-0U3304 TIME 09:07 AM ESTIMATE NO. 007 BID OPENING 07/30/15 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/27/16 R.E. NAME: MENGONI, MARK DATE OF THIS ESTIMATE 05/31/16 LOCATION PROGRESS ESTIMATE 06-FRE-168-0.7/9.1 ----------------- 06-FRE-180-54.4/54.4 WABO LANDSCAPE CONSTRUCTION, UPGRADE 97 BOOSTER PUMPS TO HIGH EFFICENCY INC VARIABLE FREQUENCY DRIVE, REPLACE 87 726 ALFRED NOBEL DRIVE COMMUNICATION FLOW SENSORS AND MASTER HERCULES, CA 94547 VALVES THAT DO NOT WORK EFFCIENTLY FED. AID NO. N O N E IRRIGATION SYSTEM UPGRADES ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 IRRIGATION SYSTEM UPGRADES LS 24,500.0000 24,500.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 05/31/16 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 06-0U3304 TIME 09:07 AM ESTIMATE NO. 007 BID OPENING 07/30/15 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/27/16 R.E. NAME: MENGONI, MARK DATE OF THIS ESTIMATE 05/31/16 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 244,318.28 3,047,134.90 SUBTOTAL AMOUNT EARNED 244,318.28 3,047,134.90 ORIGINAL CONTRACT AMOUNT 24,500.00 TOTAL WORK COMPLETED 244,318.28 3,047,134.90 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 244,318.28 3,047,134.90 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 08/03/15 90 08/31/15 00/00/00 06/13/16 177 8 1 87 62% 99% PROGRESS IS SATISFACTORY UNSATIS PROGRESS OVERRIDEN BECAU W H Y ... W H Y ... W H MENGONI, MARK RESIDENT ENGINEER PROGRAM CAS145 DATE 05/31/16