PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 10/26/26 EST. NO. 003 TIME 12:33 PM R.E. NAME: CHAP, CHANTHA 06-0Y1804 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- *** THERE ARE NO EXTRA WORK PAYMENTS THIS ESTIMATE *** PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 10/26/26 EST. NO. 003 TIME 12:33 PM R.E. NAME: CHAP, CHANTHA 06-0Y1804 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 10/26/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 06-0Y1804 TIME 12:33 PM ESTIMATE NO. 003 BID OPENING 01/13/26 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/26 R.E. NAME: CHAP, CHANTHA DATE OF THIS ESTIMATE 10/26/26 LOCATION PROGRESS ESTIMATE 06-MAD-145-8.0/12.0 ----------------- CAL VALLEY CONSTRUCTION, INC. MADERA COUNTY IN AND NEAR MADERA FROM 0.1 5125 N GATES AVE STE 102 MILE SOUTH OF AVENUE 13 TO 0.1 MILE SOUTH FRESNO CA 93722 OF EAST MADERA UNDERPASS FED. AID NO. ACST-S145(2)E PLACE HMA (TYPE A), MINOR CONCRETE SIDEWAL ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 LEAD COMPLIANCE PLAN LS 2,900.0000 2,900.00 1.000 2,900 002 TIME-RELATED OVERHEAD (WDAY) WDAY 3,500.0000 700,000.00 21.000 73,500.00 67.000 234,500 003 DISPUTE RESOLUTION BOARD ON-SITE MEETING EA 6,000.0000 36,000.00 0.000 0 004 HOURLY OFF-SITE HR 200.0000 8,000.00 0.000 0 DISPUTE-RESOLUTION-BOARD-RELATED TASKS 005 DEVELOP WATER SUPPLY LS 2,300.0000 2,300.00 0.105 241.50 0.335 770 006 CONSTRUCTION AREA SIGNS LS 95,000.0000 95,000.00 0.105 9,975.00 0.505 47,975 007 TRAFFIC CONTROL SYSTEM LS 1,563,000.0000 1,563,000.00 0.105 164,115.00 0.335 523,605 008 STATIONARY IMPACT ATTENUATOR VEHICLE DAY 1,325.0000 238,500.00 1.000 1,325.00 32.000 42,400 009 TYPE III BARRICADE EA 135.0000 5,670.00 12.000 1,620 010 TEMPORARY PAVEMENT MARKING (PAINT) SQFT 3.0000 7,800.00 172.000 516 011 TEMPORARY TRAFFIC STRIPE (PAINT) LF 0.8000 21,760.00 1,992.960 1,594 012 CHANNELIZER (SURFACE MOUNTED) EA 100.0000 38,000.00 35.000 3,500 013 PORTABLE RADAR SPEED FEEDBACK SIGN DAY 60.0000 21,600.00 21.000 1,260.00 67.000 4,020 SYSTEM 014 TEMPORARY PAVEMENT MARKER EA 100.0000 1,300.00 0.000 0 015 TEMPORARY BARRIER SYSTEM LF 30.0000 150,600.00 1,220.000 36,600 016 TEMPORARY PEDESTRIAN ACCESS ROUTE LS 15,500.0000 15,500.00 0.105 1,627.50 0.335 5,192 017 PORTABLE CHANGEABLE MESSAGE SIGN (LS) LS 30,000.0000 30,000.00 0.105 3,150.00 0.335 10,050 018 TEMPORARY CRASH CUSHION TL-2 EA 4,000.0000 104,000.00 3.000 12,000 019 TEMPORARY RADAR SPEED FEEDBACK SIGN EA 10,000.0000 20,000.00 2.000 20,000 SYSTEM 020 JOB SITE MANAGEMENT LS 5,500.0000 5,500.00 0.105 577.50 0.335 1,842 021 STORMWATER POLLUTION PREVENTION PLAN LS 2,500.0000 2,500.00 1.000 2,500 022 STORMWATER ANNUAL REPORT EA 3,000.0000 3,000.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 10/26/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 06-0Y1804 TIME 12:33 PM ESTIMATE NO. 003 BID OPENING 01/13/26 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/26 R.E. NAME: CHAP, CHANTHA DATE OF THIS ESTIMATE 10/26/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 023 TEMPORARY DRAINAGE INLET PROTECTION EA 325.0000 48,750.00 60.000 19,500 024 STREET SWEEPING LS 10,000.0000 10,000.00 0.005 50.00 0.015 150 025 TEMPORARY CONCRETE WASHOUT LS 2,200.0000 2,200.00 0.040 88.00 0.040 88 026 REMOVE YELLOW THERMOPLASTIC TRAFFIC LF 2.5000 28,750.00 0.000 0 STRIPE (HAZARDOUS WASTE) 027 TREATED WOOD WASTE LB 0.3500 1,851.50 0.000 0 028 VIBRATION MONITORING LS 19,300.0000 19,300.00 0.000 0 029 CRACK MONITORING LS 19,480.0000 19,480.00 0.000 0 030 PHOTO AND VIDEO SITE DOCUMENTATION OF LS 11,500.0000 11,500.00 0.000 0 EXISTING NON-HIGHWAY FACILITIES 031 RESET METAL BENCH (EA) EA 600.0000 2,400.00 0.000 0 032 REMOVE PLANTER EA 600.0000 3,000.00 0.000 0 033 RESET TRASH RECEPTACLE (EA) EA 600.0000 3,000.00 0.000 0 034 RELOCATE TRASH RECEPTACLE EA 600.0000 1,800.00 0.000 0 035 RELOCATE BUS SHELTER AND TRASH EA 2,000.0000 2,000.00 0.000 0 RECEPTACLE (EA) 036 CLEARING AND GRUBBING (LS) LS 1,000,000.0000 1,000,000.00 0.050 50,000.00 0.350 350,000 037 ROADWAY EXCAVATION CY 6.0000 75,000.00 733.080 4,398 038 SHOULDER BACKING TON 60.0000 16,200.00 0.000 0 039 PRUNE EXISTING PLANTS LS 10,000.0000 10,000.00 0.000 0 040 SOIL AMENDMENT CY 60.0000 4,800.00 0.000 0 041 PACKET FERTILIZER EA 0.3000 819.00 0.000 0 042 PLANT (GROUP K) EA 300.0000 17,700.00 0.000 0 043 PLANT (GROUP Z) (EA) EA 2,000.0000 18,000.00 0.000 0 044 PLANT (GROUP A) EA 15.0000 24,300.00 0.000 0 045 PLANT (GROUP B) EA 29.0000 3,480.00 0.000 0 046 PLANT (GROUP U) EA 100.0000 500.00 0.000 0 047 PLANT ESTABLISHMENT WORK LS 10,000.0000 10,000.00 0.000 0 048 WOOD MULCH CY 80.0000 18,400.00 0.000 0 049 ROOT BARRIER LF 9.0000 10,620.00 0.000 0 PROGRAM CAS145 PAGE 3 DATE 10/26/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 06-0Y1804 TIME 12:33 PM ESTIMATE NO. 003 BID OPENING 01/13/26 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/26 R.E. NAME: CHAP, CHANTHA DATE OF THIS ESTIMATE 10/26/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 050 TREE GRATE EA 2,840.0000 122,120.00 0.000 0 051 BIKE RACK EA 1,856.0000 11,136.00 0.000 0 052 TREE STAKE EA 100.0000 4,300.00 0.000 0 053 SIMME SEAT EA 2,550.0000 15,300.00 0.000 0 054 CHECK AND TEST EXISTING IRRIGATION LS 6,000.0000 6,000.00 0.000 0 FACILITIES 055 OPERATE EXISTING IRRIGATION FACILITIES LS 5,000.0000 5,000.00 0.000 0 056 REMOVE IRRIGATION FACILITY LS 3,000.0000 3,000.00 0.000 0 057 CONTROL AND NEUTRAL CONDUCTORS LS 49,000.0000 49,000.00 0.000 0 (ARMOR-CLAD) 058 3/4" REMOTE CONTROL VALVE EA 700.0000 9,800.00 0.000 0 059 1" REMOTE CONTROL VALVE EA 1,100.0000 8,800.00 0.000 0 060 16-18 STATION IRRIGATION CONTROLLER EA 6,000.0000 6,000.00 0.000 0 (PEDESTAL MOUNTED) 061 24-32 STATION IRRIGATION CONTROLLER EA 7,000.0000 7,000.00 0.000 0 (PEDESTAL MOUNTED) 062 6 STATION IRRIGATION CONTROLLER EA 4,000.0000 4,000.00 0.000 0 (PEDESTAL MOUNTED) 063 3/4" COPPER PIPE (SUPPLY LINE) LF 45.0000 450.00 0.000 0 (F) 064 1" COPPER PIPE (SUPPLY LINE) LF 50.0000 1,000.00 0.000 0 (F) 065 5/8" DRIP IRRIGATION TUBING LF 2.0000 13,656.00 0.000 0 (F) 066 3/4" BACKFLOW PREVENTER ASSEMBLY EA 4,000.0000 4,000.00 0.000 0 067 1" BACKFLOW PREVENTER ASSEMBLY EA 5,000.0000 10,000.00 0.000 0 068 FLOW SENSOR EA 600.0000 1,800.00 0.000 0 069 TREE WELL SPRINKLER ASSEMBLY EA 120.0000 18,000.00 0.000 0 070 DRIP VALVE ASSEMBLY EA 420.0000 8,820.00 0.000 0 071 3/4" GATE VALVE EA 365.0000 730.00 0.000 0 072 1" GATE VALVE EA 380.0000 3,800.00 0.000 0 073 1" PLASTIC PIPE (SCHEDULE 40) (SUPPLY LF 8.0000 68,384.00 0.000 0 (F) LINE) 074 BALL VALVE EA 355.0000 5,680.00 0.000 0 075 PVC PIPE CONDUIT (SLEEVE) LF 41.0000 105,698.00 0.000 0 (F) 076 8" CORRUGATED HIGH DENSITY POLYETHYLENE LF 65.0000 46,800.00 0.000 0 PIPE CONDUIT PROGRAM CAS145 PAGE 4 DATE 10/26/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 06-0Y1804 TIME 12:33 PM ESTIMATE NO. 003 BID OPENING 01/13/26 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/26 R.E. NAME: CHAP, CHANTHA DATE OF THIS ESTIMATE 10/26/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 077 CLASS 2 AGGREGATE BASE (CY) CY 75.0000 189,000.00 0.000 0 078 HOT MIX ASPHALT (TYPE A) TON 95.0000 4,265,500.00 147.790 14,040 079 PLACE HOT MIX ASPHALT DIKE (TYPE A) LF 8.0000 5,920.00 0.000 0 080 TACK COAT TON 1.0000 67.00 0.000 0 081 COLD PLANE ASPHALT CONCRETE PAVEMENT SQYD 0.7000 106,400.00 0.000 0 082 JOINTED PLAIN CONCRETE PAVEMENT (COLORED CY 935.0000 121,550.00 0.000 0 AND TEXTURED) 083 STRUCTURAL CONCRETE, DRAINAGE INLET CY 3,300.0000 118,800.00 0.000 0 (F) 084 MINOR CONCRETE (MINOR STRUCTURE) CY 10,000.0000 4,000.00 0.000 0 (F) 085 STRESS REDUCING SLAB CY 1,200.0000 48,000.00 0.000 0 086 24" REINFORCED CONCRETE PIPE (CLASS IV, LF 240.0000 57,600.00 0.000 0 RUBBER GASKET JOINT) 087 18" REINFORCED CONCRETE PIPE (CLASS IV, LF 225.0000 110,250.00 0.000 0 RUBBER GASKET JOINT) 088 GRATED LINE DRAIN LF 350.0000 25,550.00 0.000 0 089 ABANDON CULVERT (EA) EA 10,000.0000 20,000.00 0.000 0 090 REMOVE CULVERT (LF) LF 30.0000 8,400.00 14.000 420.00 14.000 420 091 REMOVE INLET EA 1,000.0000 13,000.00 1.000 1,000 092 ADJUST INLET EA 2,300.0000 6,900.00 0.000 0 093 ADJUST FRAME AND COVER TO GRADE EA 1,800.0000 147,600.00 4.000 7,200 094 SAND BACKFILL CY 60.0000 1,560.00 0.000 0 095 DETECTABLE WARNING SURFACE SQFT 55.0000 111,100.00 75.500 4,152 096 MINOR CONCRETE (MISCELLANEOUS CY 680.0000 1,060,800.00 138.400 94,112.00 380.620 258,821 CONSTRUCTION) 097 MINOR CONCRETE (TEXTURED PAVING) CY 1,500.0000 57,000.00 0.000 0 098 REMOVE CONCRETE (CURB, GUTTER, AND CY 400.0000 108,000.00 15.470 6,188.00 329.640 131,856 SIDEWALK) (CY) 099 MISCELLANEOUS IRON AND STEEL LB 3.5000 11,312.00 0.000 0 (F) 100 FRAME AND COVER EA 550.0000 15,400.00 0.000 0 101 WATER METER EA 2,600.0000 7,800.00 1.000 2,600.00 1.000 2,600 102 ELECTRICAL SERVICE FOR IRRIGATION (CITY) LS 30,000.0000 30,000.00 0.000 0 103 RECTANGULAR RAPID FLASHING BEACON LS 75,000.0000 75,000.00 0.000 0 SYSTEMS (CITY) PROGRAM CAS145 PAGE 5 DATE 10/26/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 06-0Y1804 TIME 12:33 PM ESTIMATE NO. 003 BID OPENING 01/13/26 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/26 R.E. NAME: CHAP, CHANTHA DATE OF THIS ESTIMATE 10/26/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 104 LIGHTING (CITY STREET) LS 1,750,000.0000 1,750,000.00 0.046 80,500.00 0.135 236,250 105 BUS SHELTER EA 36,000.0000 216,000.00 0.000 0 106 1" POLYETHYLENE SERVICE PIPE LF 150.0000 9,000.00 0.000 0 107 ADJUST FIRE HYDRANT TO GRADE EA 3,000.0000 33,000.00 0.000 0 108 SURVEY MONUMENT (TYPE A) EA 900.0000 15,300.00 0.000 0 109 ADJUST ACCESS BOX FRAME AND COVER EA 1,900.0000 58,900.00 0.000 0 (UTILITY) 110 ADJUST MANHOLE FRAME AND COVER (UTILITY) EA 1,900.0000 9,500.00 0.000 0 111 TEMPORARY FENCE (TYPE CL-6) LF 25.0000 450.00 18.000 450.00 18.000 450 112 REMOVE PAVEMENT MARKER EA 4.0000 1,760.00 0.000 0 113 PAVEMENT MARKER (RETROREFLECTIVE) EA 5.0000 12,250.00 0.000 0 114 OBJECT MARKER EA 75.0000 4,050.00 0.000 0 115 REMOVE ROADSIDE SIGN (WOOD POST) EA 50.0000 4,450.00 0.000 0 116 REMOVE ROADSIDE SIGN (METAL POST) EA 90.0000 4,770.00 0.000 0 117 REMOVE ROADSIDE SIGN (STRAP AND SADDLE EA 40.0000 3,600.00 0.000 0 BRACKET METHOD) 118 FURNISH LAMINATED PANEL SIGN (1"-TYPE B) SQFT 44.0000 3,300.00 0.000 0 119 FURNISH SINGLE SHEET ALUMINUM SIGN SQFT 20.0000 45,200.00 0.000 0 (0.063"-UNFRAMED) 120 FURNISH SINGLE SHEET ALUMINUM SIGN SQFT 20.0000 8,400.00 0.000 0 (0.080"-UNFRAMED) 121 FURNISH SINGLE SHEET ALUMINUM SIGN SQFT 40.0000 9,600.00 0.000 0 (0.063"-FRAMED) 122 FURNISH SINGLE SHEET ALUMINUM SIGN SQFT 45.0000 9,000.00 0.000 0 (0.080"-FRAMED) 123 ROADSIDE SIGN - ONE POST EA 475.0000 152,000.00 0.000 0 124 ROADSIDE SIGN - TWO POST EA 750.0000 4,500.00 0.000 0 125 INSTALL SIGN (STRAP AND SADDLE BRACKET EA 200.0000 16,800.00 0.000 0 METHOD) 126 INSTALL ROADSIDE SIGN (LAMINATED WOOD EA 1,900.0000 1,900.00 0.000 0 BOX POST) 127 FURNISH LAMINATED WOOD BOX POST (TYPE M) EA 2,700.0000 5,400.00 0.000 0 128 THERMOPLASTIC PAVEMENT MARKING (ENHANCED SQFT 10.0000 214,000.00 0.000 0 WET NIGHT VISIBILITY) 129 PAINT PAVEMENT MARKING (2-COAT) SQFT 3.5000 4,445.00 0.000 0 130 6" THERMOPLASTIC TRAFFIC STRIPE LF 1.1500 109,135.00 0.000 0 (ENHANCED WET NIGHT VISIBILITY) PROGRAM CAS145 PAGE 6 DATE 10/26/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 06-0Y1804 TIME 12:33 PM ESTIMATE NO. 003 BID OPENING 01/13/26 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/26 R.E. NAME: CHAP, CHANTHA DATE OF THIS ESTIMATE 10/26/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 131 8" THERMOPLASTIC TRAFFIC STRIPE LF 1.6000 9,536.00 0.000 0 (ENHANCED WET NIGHT VISIBILITY) 132 REMOVE THERMOPLASTIC TRAFFIC STRIPE LF 0.7500 1,680.00 0.000 0 133 REMOVE THERMOPLASTIC PAVEMENT MARKING SQFT 25.0000 3,750.00 0.000 0 134 12" RUMBLE STRIP (ASPHALT CONCRETE STA 29.0000 10,730.00 0.000 0 PAVEMENT) 135 LIGHTING SYSTEM LS 130,000.0000 130,000.00 0.000 0 136 CAMERA SYSTEMS LS 300,000.0000 300,000.00 0.102 30,600.00 0.102 30,600 137 TEMPORARY LIGHTING SYSTEMS LS 200,000.0000 200,000.00 0.000 0 138 MODIFYING SIGNAL AND LIGHTING SYSTEMS LS 1,600,000.0000 1,600,000.00 0.004 6,400.00 0.013 20,800 139 REMOVING SIGNAL AND LIGHTING SYSTEMS LS 100,000.0000 100,000.00 0.300 30,000 140 WATER METER CHARGES LS 1,000.0000 1,000.00 0.000 0 141 IRRIGATION WATER SERVICE CHARGES LS 1,050.0000 1,050.00 0.000 0 PROGRAM CAS145 PAGE 7 DATE 10/26/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 06-0Y1804 TIME 12:33 PM ESTIMATE NO. 003 BID OPENING 01/13/26 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/26 R.E. NAME: CHAP, CHANTHA DATE OF THIS ESTIMATE 10/26/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION 527,179.50 2,063,912.50 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 0.00 0.00 SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION 527,179.50 2,063,912.50 142 MOBILIZATION LS 1,350,000.0000 1,350,000.00 0.250 337,500.00 0.750 1,012,500 ORIGINAL CONTRACT AMOUNT 18,118,019.50 TOTAL WORK COMPLETED 864,679.50 3,076,412.50 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 864,679.50 3,076,412.50 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 05/26/26 450 07/16/26 00/00/00 05/04/26 67 0 0 0 17% 15% PROGRESS IS SATISFACTORY CHAP, CHANTHA RESIDENT ENGINEER