PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 05/26/26 EST. NO. 001 TIME 12:49 PM R.E. NAME: VANESSA VALDEZ 06-1J3104 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0016 28,216.08 E.W. @ F.A.(+) 020626 N 0048.0 0025 5,664.62 022026 N 0057.0 33,880.70 TOTAL THIS ESTIMATE 0.00 TOTAL PREVIOUS ESTIMATE 33,880.70 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 05/26/26 EST. NO. 001 TIME 12:49 PM R.E. NAME: VANESSA VALDEZ 06-1J3104 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 05/26/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 06-1J3104 TIME 12:49 PM ESTIMATE NO. 001 BID OPENING 10/06/25 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/20/26 R.E. NAME: VANESSA VALDEZ DATE OF THIS ESTIMATE 05/26/26 LOCATION RERUN PROGRESS ESTIMATE 06-KER-204-59.0/5.9 ----------------------- BULGER CONSTRUCTION REPLACEMENT OF EXSISTING 4847 HOPYARD RD ST 4 #395 BRIDGE BARRIER RAIL PLEASANTON CA 94588 ADN GUARDRAIL SYSTEM DIR ORDER EMERGENCY F.A. FED. AID NO. N O N E REPLACEMENT OF BRIDGE RAIL & GUARDRAIL ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 REPLACEMENT OF BRIDGE RAIL & GUARDRAIL LS 7,075.0000 7,075.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 05/26/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 06-1J3104 TIME 12:49 PM ESTIMATE NO. 001 BID OPENING 10/06/25 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/20/26 R.E. NAME: VANESSA VALDEZ DATE OF THIS ESTIMATE 05/26/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 33,880.70 33,880.70 SUBTOTAL AMOUNT EARNED 33,880.70 33,880.70 ORIGINAL CONTRACT AMOUNT 7,075.00 TOTAL WORK COMPLETED 33,880.70 33,880.70 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 33,880.70 33,880.70 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 10/24/25 65 02/02/26 00/00/00 05/27/26 65 1 0 0 2% 100% PROGRESS IS SATISFACTORY UNSATIS PROGRESS OVERRIDEN BECAU W H Y ... W H Y ... W H VANESSA VALDEZ RESIDENT ENGINEER