PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 01/22/09 EST. NO.10 TIME 12:12 PM R.E. NAME: IRA, ALFRED 07-1189F4 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0018 723.08 E.W. @ F.A.(+) 120808 N 0054.0 0019 553.08 121108 N 0056.0 0020 377.52 121208 N 0057.0 0021 519.01 122908 N 0058.0 0022 324.38 123008 N 0059.0 002 0005 271.20 E.W. @ F.A.(+) 111208 N 0051.0 009 0001 88.45 E.W. @ F.A.(+) 090808 N 0036.0 0002 485.96 090908 N 0037.0 0003 694.51 080108 N 0033.0 0004 232.62 090408 N 0034.0 0005 960.27 090508 N 0035.0 0006 763.69 100208 N 0041.0 0007 115.00 100208 N 0044.0 0008 350.18 112008 N 0061.0 6,458.95 TOTAL THIS ESTIMATE 114,011.57 TOTAL PREVIOUS ESTIMATE 120,470.52 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 01/22/09 EST. NO.10 TIME 12:12 PM R.E. NAME: IRA, ALFRED 07-1189F4 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- LABOR COMPLIANCE VIOLATION JULY 08 -10,000.00 05 JULY 08 10,000.00 06 0.00 0.00 TOTAL DEDUCTIONS 0.00 0.00 PROGRAM CAS145 PAGE 1 DATE 01/22/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-1189F4 TIME 12:12 PM ESTIMATE NO. 10 BID OPENING 11/29/07 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 01/20/09 R.E. NAME: IRA, ALFRED DATE OF THIS ESTIMATE 01/22/09 LOCATION PROGRESS ESTIMATE 07-VEN-150-28.5/28.5 ----------------- C A RASMUSSEN, INC. IN VENTURA COUNTY NEAR SULPHUR 28548 LIVINGSTON AVE. SPRINGS AT SISAR CREEK BRIDGE AND VALENCIA, CA 91355-4171 SANTA PAULA CREEK BRIDGE FED. AID NO. ACST-P150(24)E ,P-P150(24)E WIDEN BRIDGE AND UPGRADE RAILING ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 PROGRESS SCHEDULE (CRITICAL PATH METHOD) LS 1,250.0000 1,250.00 0.080 100.00 0.780 975.00 02 GROUNDWATER TREATMENT LS 375,000.0000 375,000.00 1.000 375,000.00 03 HYDROCARBON IN SOIL SAMPLING AND LS 6,000.0000 6,000.00 1.000 6,000.00 ANALYSIS WORKPLAN 04 CONSTRUCTION SITE MANAGEMENT LS 2,000.0000 2,000.00 0.080 160.00 0.780 1,560.00 05 HEALTH AND SAFETY PLAN LS 7,000.0000 7,000.00 1.000 7,000.00 06 PREPARE STORM WATER POLLUTION LS 2,000.0000 2,000.00 0.750 1,500.00 PREVENTION PLAN 07 TEMPORARY FIBER ROLL M 13.0000 1,820.00 23.000 299.00 08 TEMPORARY SILT FENCE M 80.0000 4,800.00 92.000 7,360.00 09 TEMPORARY GRAVEL BAG BERM M 20.0000 4,800.00 17.700 354.00 10 TEMPORARY CONCRETE WASHOUT FACILITY EA 3,000.0000 3,000.00 1.000 3,000.00 11 STREET SWEEPING LS 15,000.0000 15,000.00 0.080 1,200.00 0.780 11,700.00 12 TEMPORARY CREEK DIVERSION SYSTEM LS 75,000.0000 75,000.00 1.000 75,000.00 13 CONSTRUCTION AREA SIGNS LS 8,000.0000 8,000.00 0.750 6,000.00 S) 14 TRAFFIC CONTROL SYSTEM LS 115,000.0000 115,000.00 0.080 9,200.00 0.780 89,700.00 S) 15 CHANNELIZER (SURFACE MOUNTED) EA 25.0000 4,000.00 58.000 1,450.00 S) 16 PORTABLE CHANGEABLE MESSAGE SIGN LS 17,000.0000 17,000.00 0.050 850.00 0.760 12,920.00 S) 17 TEMPORARY RAILING (TYPE K) M 80.0000 36,800.00 164.600 13,168.00 18 TEMPORARY CRASH CUSHION MODULE EA 200.0000 11,200.00 28.000 5,600.00 S) 19 REMOVE FENCE M 40.0000 1,360.00 0.000 0.00 20 REMOVE GATE EA 200.0000 200.00 1.000 200.00 21 REMOVE METAL BEAM GUARD RAILING M 20.0000 3,800.00 124.000 2,480.00 22 REMOVE YELLOW THERMOPLASTIC TRAFFIC M 5.0000 3,000.00 513.000 2,565.00 S) STRIPE PROGRAM CAS145 PAGE 2 DATE 01/22/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-1189F4 TIME 12:12 PM ESTIMATE NO. 10 BID OPENING 11/29/07 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 01/20/09 R.E. NAME: IRA, ALFRED DATE OF THIS ESTIMATE 01/22/09 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 23 REMOVE PAINTED TRAFFIC STRIPE M 2.0000 5,680.00 515.000 1,030.00 S) 24 REMOVE PAVEMENT MARKER EA 2.0000 500.00 174.000 348.00 S) 25 REMOVE ASPHALT CONCRETE DIKE M 105.0000 420.00 0.000 0.00 26 REMOVE INLET EA 2,000.0000 2,000.00 0.000 0.00 27 REMOVE MASONRY WALL M2 30.0000 2,520.00 108.000 3,240.00 28 REMOVE ASPHALT CONCRETE SURFACING M2 48.0000 16,176.00 0.000 0.00 29 RESET MAILBOX EA 400.0000 1,200.00 1.000 400.00 30 ADJUST MANHOLE TO GRADE EA 600.0000 600.00 0.000 0.00 31 PREPARE CONCRETE BRIDGE DECK SURFACE M2 15.0000 7,575.00 0.000 0.00 32 BRIDGE REMOVAL (PORTION), LOCATION A LS 40,000.0000 40,000.00 0.900 36,000.00 33 BRIDGE REMOVAL (PORTION), LOCATION B LS 40,000.0000 40,000.00 0.900 36,000.00 34 CLEARING AND GRUBBING LS 4,000.0000 4,000.00 0.800 3,200.00 35 ROADWAY EXCAVATION M3 70.0000 36,400.00 78.000 5,460.00 78.000 5,460.00 36 LEAD COMPLIANCE PLAN LS 5,000.0000 5,000.00 1.000 5,000.00 37 STRUCTURE EXCAVATION (BRIDGE) M3 660.0000 128,700.00 195.000 128,700.00 F) 38 STRUCTURE EXCAVATION (TYPE D) M3 250.0000 22,500.00 90.000 22,500.00 F) 39 STRUCTURE EXCAVATION (TYPE D) M3 374.0000 31,042.00 83.000 31,042.00 F) (CUTOFF WALL) 40 STRUCTURE EXCAVATION (RETAINING WALL) M3 145.0000 21,025.00 143.640 20,827.80 F) 41 STRUCTURE BACKFILL (BRIDGE) M3 250.0000 63,250.00 215.000 53,750.00 F) 42 STRUCTURE BACKFILL (CUTOFF WALL) M3 500.0000 14,000.00 28.000 14,000.00 F) 43 STRUCTURE BACKFILL (RETAINING WALL) M3 150.0000 34,500.00 195.500 29,325.00 F) 44 IMPORTED BORROW M3 55.0000 39,050.00 648.600 35,673.00 45 HIGHWAY PLANTING LS 6,000.0000 6,000.00 0.000 0.00 S) 46 EROSION CONTROL (TYPE D) M2 3.5000 4,200.00 0.000 0.00 S) 47 PLANT ESTABLISHMENT WORK LS 6,000.0000 6,000.00 0.000 0.00 S) 48 IRRIGATION SYSTEM LS 3,000.0000 3,000.00 0.000 0.00 S) 49 CLASS 4 AGGREGATE SUBBASE M3 130.0000 24,700.00 142.500 18,525.00 142.500 18,525.00 PROGRAM CAS145 PAGE 3 DATE 01/22/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-1189F4 TIME 12:12 PM ESTIMATE NO. 10 BID OPENING 11/29/07 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 01/20/09 R.E. NAME: IRA, ALFRED DATE OF THIS ESTIMATE 01/22/09 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 50 CLASS 2 AGGREGATE BASE M3 135.0000 24,300.00 135.000 18,225.00 135.000 18,225.00 51 ASPHALT CONCRETE (TYPE B) TONN 115.0000 112,700.00 294.000 33,810.00 294.000 33,810.00 52 RUBBERIZED ASPHALT CONCRETE (TYPE G) TONN 210.0000 65,100.00 0.000 0.00 53 PLACE ASPHALT CONCRETE (MISCELLANEOUS M2 60.0000 1,560.00 0.000 0.00 AREA) 54 STRUCTURAL CONCRETE, BRIDGE FOOTING M3 800.0000 44,000.00 55.000 44,000.00 F) 55 STRUCTURAL CONCRETE, BRIDGE M3 3,200.0000 400,000.00 112.500 360,000.00 F) 56 STRUCTURAL CONCRETE, RETAINING WALL M3 1,600.0000 80,000.00 45.000 72,000.00 F) 57 STRUCTURE CONCRETE, CUTOFF WALL M3 800.0000 44,000.00 55.000 44,000.00 F) 58 DRILL AND BOND DOWEL M 150.0000 14,550.00 26.000 3,900.00 59 FURNISH PRECAST PRESTRESSED CONCRETE EA 22,000.0000 44,000.00 2.000 44,000.00 GIRDER (15 M - 20 M) 60 FURNISH PRECAST PRESTRESSED CONCRETE EA 24,000.0000 48,000.00 2.000 48,000.00 GIRDER (20 M - 25 M) 61 ERECT PRECAST PRESTRESSED CONCRETE EA 5,000.0000 20,000.00 4.000 20,000.00 GIRDER 62 FURNISH POLYESTER CONCRETE OVERLAY M3 3,500.0000 52,500.00 0.000 0.00 63 PLACE POLYESTER CONCRETE OVERLAY M2 65.0000 32,825.00 0.000 0.00 F) 64 BAR REINFORCING STEEL (BRIDGE) KG 5.0000 147,500.00 28,200.000 141,000.00 F) 65 BAR REINFORCING STEEL (RETAINING WALL) KG 6.5000 7,605.00 970.000 6,305.00 F) 66 BAR REINFORCING STEEL (CUTOFF WALL) KG 4.0000 9,200.00 2,300.000 9,200.00 F) 67 450 MM CORRUGATED STEEL PIPE DOWNDRAIN M 740.0000 1,850.00 0.000 0.00 (2.77 MM THICK) 68 450 MM STEEL FLARED END SECTION EA 600.0000 600.00 0.000 0.00 69 METAL BEAM GUARD RAILING (WOOD POST) M 170.0000 9,350.00 0.000 0.00 70 TRANSITION RAILING (TYPE WB) EA 2,900.0000 23,200.00 0.000 0.00 S) 71 END ANCHOR ASSEMBLY (TYPE SFT) EA 1,000.0000 3,000.00 0.000 0.00 S) 72 ALTERNATIVE IN-LINE TERMINAL SYSTEM EA 3,500.0000 7,000.00 0.000 0.00 S) 73 ALTERNATIVE FLARED TERMINAL SYSTEM EA 2,800.0000 8,400.00 0.000 0.00 S) 74 CONCRETE BARRIER (TYPE 80 MODIFIED) M 950.0000 69,350.00 23.000 21,850.00 28.000 26,600.00 75 CONCRETE BARRIER (TYPE 80 A)(MODIFIED) M 950.0000 83,600.00 20.000 19,000.00 27.000 25,650.00 76 100 MM THERMOPLASTIC TRAFFIC STRIPE M 2.0000 1,200.00 0.000 0.00 S) PROGRAM CAS145 PAGE 4 DATE 01/22/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-1189F4 TIME 12:12 PM ESTIMATE NO. 10 BID OPENING 11/29/07 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 01/20/09 R.E. NAME: IRA, ALFRED DATE OF THIS ESTIMATE 01/22/09 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 77 PAINT TRAFFIC STRIPE (2-COAT) M 1.0000 2,240.00 775.000 775.00 S) 78 PAVEMENT MARKER (RETROREFLECTIVE) EA 10.0000 2,500.00 73.000 730.00 S) PROGRAM CAS145 PAGE 5 DATE 01/22/09 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-1189F4 TIME 12:12 PM ESTIMATE NO. 10 BID OPENING 11/29/07 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 01/20/09 R.E. NAME: IRA, ALFRED DATE OF THIS ESTIMATE 01/22/09 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION 128,380.00 1,967,046.80 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 6,458.95 120,470.52 SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION 134,838.95 2,087,517.32 79 MOBILIZATION LS 180,000.0000 180,000.00 1.000 180,000.00 ORIGINAL CONTRACT AMOUNT 2,798,198.00 TOTAL WORK COMPLETED 134,838.95 2,267,517.32 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 134,838.95 2,267,517.32 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 02/06/08 515 02/21/08 02/21/08 04/27/10 200 29 0 0 77% 75% PROGRESS IS SATISFACTORY IRA, ALFRED RESIDENT ENGINEER PROGRAM CAS145 PAGE 2 DATE 01/22/09