PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 03/26/19 EST. NO. 003 TIME 09:49 AM R.E. NAME: PATEL, PRAVIN 07-1XJ504 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0011 4,328.28 E.W. @ F.A.(+) 021119 N 011 0 0013 6,303.70 021219 N 013 0 0014 771.88 021919 N 014 0 0015 4,830.56 021919 N 015 0 0016 2,822.16 022219 N 016 0 0017 2,073.53 022519 N 017 0 0018 6,263.85 022619 N 018 0 0019 514.58 022819 N 019 0 0020 3,361.67 022819 N 020 0 0022 3,008.59 021119 N 907070 0023 4,052.22 021219 N 907090 0024 4,921.05 021919 N 907130 0025 4,650.97 022219 N 089756 0026 4,667.83 022519 N 907160 0027 4,711.27 022619 N 907170 0028 4,667.83 022819 N 902980 0029 23,833.92 022019 N 022 0 0030 815.14 021119 N 029 0 0031 4,041.72 021219 N 030 0 0032 1,689.00 022019 N 031 0 0033 6,956.05 022219 N 032 0 0034 2,073.53 030419 N 033 0 0035 4,155.39 030719 N 034 0 0036 2,470.66 030819 N 035 0 107,985.38 TOTAL THIS ESTIMATE 15,307.44 TOTAL PREVIOUS ESTIMATE 123,292.82 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 03/26/19 EST. NO. 003 TIME 09:49 AM R.E. NAME: PATEL, PRAVIN 07-1XJ504 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 03/26/19 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-1XJ504 TIME 09:49 AM ESTIMATE NO. 003 BID OPENING 09/25/18 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 03/20/19 R.E. NAME: PATEL, PRAVIN DATE OF THIS ESTIMATE 03/26/19 LOCATION PROGRESS ESTIMATE 07-LA-60-110.0 ----------------- BEADOR CONSTRUCTION COMPANY IN LA CNTY CITY S.EL MONTE E/B LA-60 @PECK 26320 LESTER CIRCLE RD UC BRDG#53-1766,PLACE TEMP K-RAIL,REMOV CORONA CA 92883 & RECONSTC DAMAGED CONCRT BARRIER DIR'S EMERGENCY FORCE ACCOUNT FED. AID NO. N O N E REMOVE & RECONSTC DAMAGED CONCRETE BARRIER ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 RECONSTC CONCRETE BARRIER (BOND PREMIUM) LS 6,048.0000 6,048.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 03/26/19 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-1XJ504 TIME 09:49 AM ESTIMATE NO. 003 BID OPENING 09/25/18 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 03/20/19 R.E. NAME: PATEL, PRAVIN DATE OF THIS ESTIMATE 03/26/19 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 107,985.38 123,292.82 SUBTOTAL AMOUNT EARNED 107,985.38 123,292.82 ORIGINAL CONTRACT AMOUNT 6,048.00 TOTAL WORK COMPLETED 107,985.38 123,292.82 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 107,985.38 123,292.82 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 10/30/18 60 11/02/18 11/02/18 05/02/19 32 61 0 0 30% 53% PROGRESS IS SATISFACTORY EMERGENCY JOB PATEL, PRAVIN RESIDENT ENGINEER PROGRAM CAS145 DATE 03/26/19