PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 12/26/05 EST. NO.01 TIME 11:38 AM R.E. NAME: KIM, ANTHONY 07-250804 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0001 973.56 E.W. @ F.A.(+) 103105 N 1 0 0002 973.56 111505 N 2 0 0003 1,772.20 111705 N 3 0 0004 1,669.58 112005 N 4 0 0005 1,121.89 112205 N 5 0 0007 855.57 112305 N 6 0 0010 32,545.00 111705 N 10 0 0011 143.75 112105 N 11 0 0012 5,576.18 112905 N 12 0 0013 2,828.87 112805 N 13 0 0014 1,321.05 112905 N 14 0 0015 4,013.28 112905 N 15 0 0016 6,294.07 113005 N 16 0 0017 4,958.21 120105 N 17 0 0018 4,442.83 120205 N 18 0 69,489.60 TOTAL THIS ESTIMATE 0.00 TOTAL PREVIOUS ESTIMATE 69,489.60 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 12/26/05 EST. NO.01 TIME 11:38 AM R.E. NAME: KIM, ANTHONY 07-250804 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 12/26/05 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-250804 TIME 11:38 AM ESTIMATE NO. 01 BID OPENING 10/03/05 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/20/05 R.E. NAME: KIM, ANTHONY DATE OF THIS ESTIMATE 12/26/05 LOCATION PROGRESS ESTIMATE 07-LA-10-0.0/0.6 ----------------- DRILL TECH DRILLING & SHORING E/B LA-10 AT 101/10W EAST TO PM 0.65 EASTS 2200 WYMORE WAY OF DOWNTOWN L.A. TO INSTALL SOLDIER PILE ANTIOCH, CA 94509 RETAINING WALL W/TIEBACK & CRIB WALLS DIR'S EMERGENCY F.A. CONTRACT FED. AID NO. N O N E INSTALL RETAINING WALL/CRIB WALLS/EROSION ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 STORM DAMAGE EROSION REPAIR(BOND PREMIUM LS 26,560.0000 26,560.00 1.000 26,560.00 1.000 26,560.00 PROGRAM CAS145 PAGE 2 DATE 12/26/05 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-250804 TIME 11:38 AM ESTIMATE NO. 01 BID OPENING 10/03/05 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/20/05 R.E. NAME: KIM, ANTHONY DATE OF THIS ESTIMATE 12/26/05 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 26,560.00 26,560.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 69,489.60 69,489.60 SUBTOTAL AMOUNT EARNED 96,049.60 96,049.60 ORIGINAL CONTRACT AMOUNT 26,560.00 TOTAL WORK COMPLETED 96,049.60 96,049.60 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 96,049.60 96,049.60 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 10/19/05 50 11/28/05 11/28/05 02/02/06 21 1 0 0 4% 42% PROGRESS IS SATISFACTORY KIM, ANTHONY RESIDENT ENGINEER PROGRAM CAS145 DATE 12/26/05