PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 06/21/10 EST. NO.04 TIME 02:56 PM R.E. NAME: CASTILLO, ELOY 07-2X7904 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0110 1,771.11 E.W. @ F.A.(+) 051410 N 0092.3 0111 6,536.75 051710 N 0093.0 0112 5,124.35 051710 N 0093.5 0113 4,860.81 051810 N 0094.0 0114 9,151.44 051910 N 0095.0 0115 6,350.26 052010 N 0096.0 0116 209.88 051210 N 0092.1 0117 3,526.95 051310 N 0092.2 0118 4,571.70 052010 N 0097.0 0119 6,333.67 052110 N 0098.0 0120 6,407.40 052410 N 0099.0 0121 4,593.51 052410 N 0100.0 0122 7,856.42 052510 N 0101.0 0123 6,135.73 052610 N 0102.0 0124 11,164.60 052710 N 0103.0 0125 2,507.45 052710 N 0104.0 0126 2,820.95 052710 N 0105.0 0127 4,814.88 052810 N 0106.0 0128 9,320.10 060110 N 0107.0 0129 7,861.30 060210 N 0108.0 0130 6,168.66 060310 N 0109.0 0131 6,343.51 060410 N 0110.0 0132 8,459.59 061010 N 0115.0 0133 5,801.70 061110 N 0116.0 0134 6,744.75 061410 N 0117.0 0135 23,604.36 061510 N 0118.0 0136 9,141.44 060910 N 0114.0 0137 16,724.02 060910 N 0114.5 0138 2,820.95 052710 N 0105.1 0139 1,292.48 060210 N 0110.5 0140 1,280.48 060410 N 0111.0 0141 7,709.48 060710 N 0112.0 0142 6,137.72 060810 N 0113.0 214,148.40 TOTAL THIS ESTIMATE 787,320.22 TOTAL PREVIOUS ESTIMATE 1,001,468.62 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 06/21/10 EST. NO.04 TIME 02:56 PM R.E. NAME: CASTILLO, ELOY 07-2X7904 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 06/21/10 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-2X7904 TIME 02:56 PM ESTIMATE NO. 04 BID OPENING 02/11/10 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/20/10 R.E. NAME: CASTILLO, ELOY DATE OF THIS ESTIMATE 06/21/10 LOCATION PROGRESS ESTIMATE 07-LA-1-35.2/62.9 ----------------- DB GENERAL ENGINEERING AND PCH, FROM PM 35.2 IN THE CITY OF MALIBU SITE DEVELOPMENT, INC. NORTH THROUGH THE CITY OF MALIBU TO PM 2158 SCENICPARK STREET 62.9 AT THE LA/VENTURA COUNTY LINE. THOUSAND OAKS, CA 91362 DIR'S ORDER EMERGENCY FA CONTRACT FED. AID NO. N O N E REMOVE ALL STORM DEBRIS AND FIX DRAINAGE ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 REMOVE ALL STORM DEBRIS AND FIX DRAINAGE LS 20,975.0000 20,975.00 1.000 20,975.00 PROGRAM CAS145 PAGE 2 DATE 06/21/10 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-2X7904 TIME 02:56 PM ESTIMATE NO. 04 BID OPENING 02/11/10 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 06/20/10 R.E. NAME: CASTILLO, ELOY DATE OF THIS ESTIMATE 06/21/10 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 20,975.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 214,148.40 1,001,468.62 SUBTOTAL AMOUNT EARNED 214,148.40 1,022,443.62 ORIGINAL CONTRACT AMOUNT 20,975.00 TOTAL WORK COMPLETED 214,148.40 1,022,443.62 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 214,148.40 1,022,443.62 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 02/16/10 120 02/16/10 00/00/00 07/30/10 80 0 0 0 29% 67% PROGRESS IS SATISFACTORY EMERGENCY FA CASTILLO, ELOY RESIDENT ENGINEER PROGRAM CAS145 PAGE 8 DATE 06/21/10