PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 08/08/23 EST. NO. 004 TIME 03:42 PM R.E. NAME: TEHRANI, JOSEPH 07-2XF604 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0118 5,360.84 E.W. @ F.A.(+) 051223 N 0013.6 0154 6,809.96 041323 N 0005.6 0155 20,786.29 062323 N 0017.2 0156 8,568.23 062123 N 0017.3 0157 13,120.89 062723 N 0017.4 0158 14,121.91 062823 N 0017.5 0159 14,182.88 062923 N 0017.6 0160 20,853.00 063023 N 0017.7 0161 16,223.95 063023 N 0017.8 0162 5,796.77 062123 N 0017.9 0163 986.15 053023 N 0018.0 0164 2,379.23 051023 N 0010.1 0165 3,404.72 051023 N 0011.0 0166 4,771.23 052323 N 0013.3 0168 12,648.03 062023 N 0018.1 0169 15,387.74 070323 N 18.2 0 0170 366.79 063023 N 18.3 0 0171 19,192.48 070523 N 18.4 0 0175 1,687.17 040423 N 0004.0 0184 17,286.38 070723 N 18.610 203,934.64 TOTAL THIS ESTIMATE 1,255,455.63 TOTAL PREVIOUS ESTIMATE 1,459,390.27 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 08/08/23 EST. NO. 004 TIME 03:42 PM R.E. NAME: TEHRANI, JOSEPH 07-2XF604 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 08/08/23 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-2XF604 TIME 03:42 PM ESTIMATE NO. 004 BID OPENING 03/02/23 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 08/06/23 R.E. NAME: TEHRANI, JOSEPH DATE OF THIS ESTIMATE 08/08/23 LOCATION PROGRESS ESTIMATE 07-VEN-33-24.2/27.3 ----------------- GRANITE CONSTRUCTION COMPANY IN VENTURA COUNTY IN CITY OF OJAI VEN-33 4820 MCGRATH STE #101 TO REPAIR SLOPES/SHOULDERS,DIKES,GUARDRAIL VENTURA, CA 93003 CONSTRUCT SPW DUE TO STORM DAMAGE DIR'S EMERGENCY FORCE ACCOUNT FED. AID NO. N O N E REPAIR STORM DAMAGE ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 REPAIR STORM DAMAGE (BOND PREMIUM) LS 41,917.0000 41,917.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 08/08/23 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-2XF604 TIME 03:42 PM ESTIMATE NO. 004 BID OPENING 03/02/23 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 08/06/23 R.E. NAME: TEHRANI, JOSEPH DATE OF THIS ESTIMATE 08/08/23 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 203,934.64 1,459,390.27 SUBTOTAL AMOUNT EARNED 203,934.64 1,459,390.27 ORIGINAL CONTRACT AMOUNT 41,917.00 TOTAL WORK COMPLETED 203,934.64 1,459,390.27 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 203,934.64 1,459,390.27 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 04/11/23 240 03/06/23 03/20/23 04/30/24 97 0 0 0 8% 40% PROGRESS IS SATISFACTORY EMERGENCY JOB TEHRANI, JOSEPH RESIDENT ENGINEER