PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 02/24/26 EST. NO. 001 TIME 09:08 AM R.E. NAME: ALI SHALVIRI 07-2XW504 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0001 4,323.41 E.W. @ F.A.(+) 122525 N 001 0025 37,267.84 021026 N PV01 0032 9,819.97 122925 N PV02 0035 28,244.35 021126 N PV03 79,655.57 TOTAL THIS ESTIMATE 0.00 TOTAL PREVIOUS ESTIMATE 79,655.57 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 02/24/26 EST. NO. 001 TIME 09:08 AM R.E. NAME: ALI SHALVIRI 07-2XW504 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 02/24/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-2XW504 TIME 09:08 AM ESTIMATE NO. 001 BID OPENING 01/16/26 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 02/20/26 R.E. NAME: ALI SHALVIRI DATE OF THIS ESTIMATE 02/24/26 LOCATION PROGRESS ESTIMATE 07-LA-110-792.0/82.2 ----------------- SGV ENTERPRISES INC IN THE AREA OF LA&SBD CITY OF WRIGHTWOOD 615 LAS TUNAS DR SUITE J OON ROUTE SR-2, REPAIR&RECONSTRUCT SIDE ARCADIA CA 91007 SLOPE, SHOULDER AND ROADWAY DIR'S EMERGENCY F.A. FED. AID NO. N O N E REPAIR LANDSLIDE CAUSED BY STORM DAMAGE ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 REPAIR SIDE SLOPE(BOND PREMIUM) LS 37,865.0000 37,865.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 02/24/26 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-2XW504 TIME 09:08 AM ESTIMATE NO. 001 BID OPENING 01/16/26 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 02/20/26 R.E. NAME: ALI SHALVIRI DATE OF THIS ESTIMATE 02/24/26 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 79,655.57 79,655.57 SUBTOTAL AMOUNT EARNED 79,655.57 79,655.57 ORIGINAL CONTRACT AMOUNT 37,865.00 TOTAL WORK COMPLETED 79,655.57 79,655.57 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 79,655.57 79,655.57 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 02/16/26 180 01/12/26 12/26/26 12/31/26 30 7 0 0 2% 17% PROGRESS IS SATISFACTORY EMERGENCY PROJECT ALI SHALVIRI RESIDENT ENGINEER