PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 05/26/05 EST. NO.04 TIME 07:45 AM R.E. NAME: MOGHADDAS, SEYED 07-4K8404 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0047 3,272.78 E.W. @ F.A.(+) 041405 N 16 0 0048 2,021.01 041505 N 17 0 0049 2,021.01 041805 N 18 0 0050 2,021.01 041905 N 19 0 0051 2,021.01 042005 N 20 0 0052 2,021.01 042105 N 22 0 0053 1,196.95 042205 N 23 0 0054 3,989.20 040505 N 24 0 0055 3,112.86 040605 N 26 0 0056 2,807.79 040705 N 27 0 0057 2,647.44 040805 N 28 0 0058 3,245.94 041105 N 29 0 0059 3,457.19 041305 N 30 0 0060 1,196.95 042505 N 31 0 0061 1,196.95 042605 N 32 0 36,229.10 TOTAL THIS ESTIMATE 112,958.17 TOTAL PREVIOUS ESTIMATE 149,187.27 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 05/26/05 EST. NO.04 TIME 07:45 AM R.E. NAME: MOGHADDAS, SEYED 07-4K8404 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 05/26/05 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-4K8404 TIME 07:45 AM ESTIMATE NO. 04 BID OPENING 01/09/05 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/20/05 R.E. NAME: MOGHADDAS, SEYED DATE OF THIS ESTIMATE 05/26/05 LOCATION PROGRESS ESTIMATE 07-LA-5-45.0/66.0 ----------------- GRANITE CONSTRUCTION COMPANY ON LA-5 AT THE 5/14 INTERCHANGE (PM45.0) P.P. BOX 50085 INTO GRAPEVINE AREA OF ANGELES NATIONAL WATSONVILLE, CA 95077 FOREST, ENDING AT TEMPLIN HIGHWAY U/C PM66 DIR'S EMERGENCY F.A. CONTRACT FED. AID NO. N O N E REMOVE & DISPOSE OF ALL SLIDE DEBRIS ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 SLIDE DEBRIS CLEANUP (BOND PREMIUM) LS 569.0000 569.00 1.000 569.00 PROGRAM CAS145 PAGE 2 DATE 05/26/05 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-4K8404 TIME 07:45 AM ESTIMATE NO. 04 BID OPENING 01/09/05 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 05/20/05 R.E. NAME: MOGHADDAS, SEYED DATE OF THIS ESTIMATE 05/26/05 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 569.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 36,229.10 149,187.27 SUBTOTAL AMOUNT EARNED 36,229.10 149,756.27 ORIGINAL CONTRACT AMOUNT 569.00 TOTAL WORK COMPLETED 36,229.10 149,756.27 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 36,229.10 149,756.27 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 01/12/05 35 01/09/05 01/09/05 06/30/05 47 0 0 0 46% 100% PROGRESS IS SATISFACTORY UNSATIS PROGRESS OVERRIDEN BECAU EMERGENCY JOB MOGHADDAS, SEYED RESIDENT ENGINEER PROGRAM CAS145 DATE 05/26/05