PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 08/25/05 EST. NO.08 TIME 01:19 PM R.E. NAME: YOUNG, FRED 07-4L1004 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0126 5,039.30 E.W. @ F.A.(+) 070505 N 119 0 0127 3,708.75 070605 N 120 0 0128 1,383.99 071805 N 121 0 0129 650.77 072205 N 122 0 0130 1,887.35 072505 N 123 0 0131 5,887.64 072605 N 124 0 0132 6,380.99 072705 N 125 0 0133 6,245.11 072805 N 126 0 0134 6,380.99 072905 N 127 0 0135 86.25 072605 N 128 0 0136 172.50 072705 N 129 0 0137 258.75 072805 N 130 0 0138 690.00 072905 N 131 0 0139 6,815.41 080105 N 132 0 0140 629.94 080105 N 132A 0 0142 629.94 080205 N 133A 0 0143 7,544.22 080305 N 134 0 0144 629.94 080305 N 134A 0 0145 7,123.19 080405 N 135 0 0146 629.94 080405 N 135A 0 0147 6,144.73 080505 N 136 0 0148 6,815.41 080205 N 133 0 0149 804.54 072705 N 125A 0 0150 804.54 072805 N 126A 0 0151 804.54 072905 N 127A 0 0152 9,529.57 080805 N 137 0 0153 169.34 080805 N 137A 0 0154 1,337.72 080805 N 138 0 0155 8,233.57 080905 N 139 0 0156 690.39 080905 N 139A 0 0157 8,321.10 081005 N 140 0 0158 169.34 081005 N 140A 0 0159 8,140.18 081105 N 141 0 0160 169.34 081105 N 141A 0 0161 5,820.63 081205 N 142 0 120,729.91 TOTAL THIS ESTIMATE 685,430.87 TOTAL PREVIOUS ESTIMATE 806,160.78 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 08/25/05 EST. NO.08 TIME 01:19 PM R.E. NAME: YOUNG, FRED 07-4L1004 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 08/25/05 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-4L1004 TIME 01:19 PM ESTIMATE NO. 08 BID OPENING 03/18/05 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 08/20/05 R.E. NAME: YOUNG, FRED DATE OF THIS ESTIMATE 08/25/05 LOCATION PROGRESS ESTIMATE 07-LA-5-64.4/64.4 ----------------- CHUMO CONSTRUCTION SB LA-5 AT PM 64.45- 1.5 MILES SOUTH OF 14425 JOANBRIDGE STREET THE TEMPLIN HIGHWAY U/C WITHIN THE ANGELES BALDWIN PARK, CA 91705 NATIONAL FOREST, IN NORTHERN LA COUNTY DIR'S EMERGENCY F.A. CONTRACT FED. AID NO. N O N E REMOVE SLIDE & PLACE BUTTRESS TO STABLE SL ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 REMOVE SLIDE (BOND PREMIUM) LS 4,740.0000 4,740.00 1.000 4,740.00 PROGRAM CAS145 PAGE 2 DATE 08/25/05 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 07-4L1004 TIME 01:19 PM ESTIMATE NO. 08 BID OPENING 03/18/05 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 08/20/05 R.E. NAME: YOUNG, FRED DATE OF THIS ESTIMATE 08/25/05 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 4,740.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 120,729.91 806,160.78 SUBTOTAL AMOUNT EARNED 120,729.91 810,900.78 ORIGINAL CONTRACT AMOUNT 4,740.00 TOTAL WORK COMPLETED 120,729.91 810,900.78 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 120,729.91 810,900.78 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 03/22/05 40 03/28/05 03/28/05 09/30/05 78 20 0 0 45% 100% PROGRESS IS SATISFACTORY UNSATIS PROGRESS OVERRIDEN BECAU EMERGENCY CONTRACT YOUNG, FRED RESIDENT ENGINEER PROGRAM CAS145 DATE 08/25/05