PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 04/10/08 EST. NO.03 TIME 03:37 PM R.E. NAME: GADALLA, AMGAD 08-0L1404 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0042 2,275.28 E.W. @ F.A.(+) 031708 N 0046.0 0043 2,275.28 011608 N 0041.0 4,550.56 TOTAL THIS ESTIMATE 175,107.91 TOTAL PREVIOUS ESTIMATE 179,658.47 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 04/10/08 EST. NO.03 TIME 03:37 PM R.E. NAME: GADALLA, AMGAD 08-0L1404 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 04/10/08 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-0L1404 TIME 03:37 PM ESTIMATE NO. 03 BID OPENING 10/26/07 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 03/17/08 R.E. NAME: GADALLA, AMGAD DATE OF THIS ESTIMATE 04/10/08 LOCATION PROGRESS ESTIMATE AFTER ACCEPTANCE 08-SBD-18-34.5/39.1 ---------------------------------- CALIFORNIA PROFESSIONAL NEAR RUNNING SPRINGS FROM GREEN VALLEY ENGINEERING INC. LAKE ROAD TO 3.5 MI EAST OF SNOW VALLEY 9316 MABEL AVENUE AT LAKEVIEW POINT SOUTH EL MONTE, CA 91733 FED. AID NO. NH- ( ) RMV DEBRIS, EROSION CONTROL, SLOPE STABLE ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 EROSION CONTROL LS 20,000.0000 20,000.00 0.000 0.00 PROGRAM CAS145 PAGE 2 DATE 04/10/08 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-0L1404 TIME 03:37 PM ESTIMATE NO. 03 BID OPENING 10/26/07 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 03/17/08 R.E. NAME: GADALLA, AMGAD DATE OF THIS ESTIMATE 04/10/08 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 4,550.56 179,658.47 SUBTOTAL AMOUNT EARNED 4,550.56 179,658.47 ORIGINAL CONTRACT AMOUNT 20,000.00 TOTAL WORK COMPLETED 4,550.56 179,658.47 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 4,550.56 179,658.47 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN JOB COM- WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR PLETED ON DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 10/30/07 120 11/06/07 11/06/07 03/17/08 88 0 0 0 100% 100% GADALLA, AMGAD RESIDENT ENGINEER PROGRAM CAS145 PAGE 2 DATE 04/10/08