PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 10/26/16 EST. NO. 001 TIME 04:31 PM R.E. NAME: BENSON, DAVID 08-0R5404 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- *** THERE ARE NO EXTRA WORK PAYMENTS THIS ESTIMATE *** PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 10/26/16 EST. NO. 001 TIME 04:31 PM R.E. NAME: BENSON, DAVID 08-0R5404 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 10/26/16 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-0R5404 TIME 04:31 PM ESTIMATE NO. 001 BID OPENING 07/06/16 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/16 R.E. NAME: BENSON, DAVID DATE OF THIS ESTIMATE 10/26/16 LOCATION PROGRESS ESTIMATE 08-SBD-15-32.5/42.2 ----------------- ARAMEXX CONSTRUCTION IN HESPERIA & VICTORILLE FROM 0.2 123 E. 9TH STREET SUITE 100D MI N/O JOSHUA ST OC TO 0.2 MI N/O UPLAND CA 91786 MOJAVE DR OC FED. AID NO. STPI-015 -1(242)E INSTALL ROCK BLANKET ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 LEAD COMPLIANCE PLAN LS 1,989.0000 1,989.00 0.500 994.50 0.500 994 002 CONSTRUCTION AREA SIGNS LS 8,000.0000 8,000.00 0.350 2,800.00 0.350 2,800 003 TRAFFIC CONTROL SYSTEM LS 13,000.0000 13,000.00 0.000 0 004 PORTABLE CHANGEABLE MESSAGE SIGN (EA) EA 12,360.0000 49,440.00 0.000 0 005 JOB SITE MANAGEMENT LS 1,500.0000 1,500.00 0.000 0 006 PREPARE STORM WATER POLLUTION PREVENTION LS 2,985.0000 2,985.00 0.500 1,492.50 0.500 1,492 PLAN 007 STORM WATER ANNUAL REPORT EA 2,000.0000 2,000.00 0.000 0 008 TEMPORARY DRAINAGE INLET PROTECTION EA 135.0000 1,485.00 0.000 0 009 TEMPORARY FIBER ROLL LF 6.0000 5,400.00 0.000 0 010 TEMPORARY CONCRETE WASHOUT LS 4,890.0000 4,890.00 0.000 0 011 REMOVE ASPHALT CONCRETE PAVEMENT (SQFT) SQFT 8.0000 3,360.00 0.000 0 012 RESET ROADSIDE SIGN (ONE POST) EA 185.0000 4,625.00 0.000 0 013 ROADSIDE CLEARING LS 2,000.0000 2,000.00 0.000 0 014 ROCK BLANKET SQFT 8.0500 690,690.00 0.000 0 015 POST SLEEVE EA 380.0000 9,500.00 0.000 0 016 MAINTAINING EXISTING TRAFFIC MANAGEMENT LS 2,000.0000 2,000.00 0.000 0 SYSTEM ELEMENTS DURING CONSTRUCTION PROGRAM CAS145 PAGE 2 DATE 10/26/16 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-0R5404 TIME 04:31 PM ESTIMATE NO. 001 BID OPENING 07/06/16 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/16 R.E. NAME: BENSON, DAVID DATE OF THIS ESTIMATE 10/26/16 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION 5,287.00 5,287.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 0.00 0.00 SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION 5,287.00 5,287.00 017 MOBILIZATION LS 35,000.0000 35,000.00 0.000 0 ORIGINAL CONTRACT AMOUNT 837,864.00 TOTAL WORK COMPLETED 5,287.00 5,287.00 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 5,287.00 5,287.00 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 09/01/16 75 09/16/16 00/00/00 01/25/17 17 0 0 0 1% 23% PROGRESS IS SATISFACTORY BENSON, DAVID RESIDENT ENGINEER PROGRAM CAS145 DATE 10/26/16