PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 10/25/21 EST. NO. 013 TIME 11:21 AM R.E. NAME: SUFIPUR, RAMBOD 08-1H7704 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0001 496.78 E.W. @ F.A.(+) 120920 N 0001.0 002 0001 1,217.03 E.W. @ F.A.(+) 011321 N 0002.0 004 0001 764.38 E.W. @ F.A.(+) 072121 N 0007.0 0002 4,611.09 072821 N 0008.0 0005 3,252.66 080421 N 0011.0 10,341.94 TOTAL THIS ESTIMATE 0.00 TOTAL PREVIOUS ESTIMATE 10,341.94 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 10/25/21 EST. NO. 013 TIME 11:21 AM R.E. NAME: SUFIPUR, RAMBOD 08-1H7704 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- LABOR COMPLIANCE VIOLATION NOVEMBER 2020 -3,000.00 002 DECEMBER 2020 -1,000.00 003 NOVEMBER 2020 RLS 3,000.00 003 DECEMBER 2020 RLS 1,000.00 004 JANUARY 2021 -10,000.00 004 MARCH 2021 -1,000.00 006 APRIL 2021 -1,000.00 007 APRIL 2021 RLS 1,000.00 008 JANUARY 2021 RLS 10,000.00 008 MARCH 2021 RLS 1,000.00 008 JUNE 2021 -4,000.00 009 JUNE 2021 RLS 4,000.00 010 0.00 0.00 TOTAL DEDUCTIONS 0.00 0.00 PROGRAM CAS145 PAGE 1 DATE 10/25/21 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-1H7704 TIME 11:21 AM ESTIMATE NO. 013 BID OPENING 02/12/20 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/21 R.E. NAME: SUFIPUR, RAMBOD DATE OF THIS ESTIMATE 10/25/21 LOCATION PROGRESS ESTIMATE 08-SBD-215-4.8/5.8 ----------------- BEADOR CONSTRUCTION COMPANY, IN SAN BERNARDINO FROM 0.5 MI S/O INC. ORANGE SHOW/AUTO PLAZA RD OC TO 0.2 26320 LESTER CIRCLE; MI N/O INLAND CENTER DRIVE OC CORONA CA 92883 FED. AID NO. HSIM- 215-1(249)E LANE RECONFIGURATION & PAVEMENT ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 LEAD COMPLIANCE PLAN LS 5,500.0000 5,500.00 0.750 4,125 002 TIME-RELATED OVERHEAD (WDAY) WDAY 1,100.0000 198,000.00 180.000 198,000 003 DEVELOP WATER SUPPLY LS 35,000.0000 35,000.00 1.000 35,000 004 CONSTRUCTION AREA SIGNS LS 28,000.0000 28,000.00 0.800 22,400 005 TRAFFIC CONTROL SYSTEM LS 148,739.3000 148,739.30 1.000 148,739 006 TYPE III BARRICADE EA 110.0000 110.00 1.000 110 007 TEMPORARY TRAFFIC STRIPE (PAINT) LF 0.1800 7,236.00 31,752.000 5,715 008 CHANNELIZER (SURFACE MOUNTED) EA 42.0000 2,814.00 74.000 3,108 009 TEMPORARY PAVEMENT MARKER EA 2.5000 2,150.00 717.000 1,792 010 PORTABLE CHANGEABLE MESSAGE SIGN (LS) LS 75,000.0000 75,000.00 1.000 75,000 011 TEMPORARY RAILING (TYPE K) LF 16.0000 56,640.00 4,080.000 65,280 012 TEMPORARY CRASH CUSHION MODULE EA 300.0000 19,200.00 67.000 20,100 013 TEMPORARY TRAFFIC SCREEN LF 3.5000 12,390.00 3,660.000 12,810 014 JOB SITE MANAGEMENT LS 50,000.0000 50,000.00 1.000 50,000 015 PREPARE STORM WATER POLLUTION PREVENTION LS 3,000.0000 3,000.00 0.750 2,250 PLAN 016 TEMPORARY DRAINAGE INLET PROTECTION EA 110.0000 1,320.00 8.000 880 017 TEMPORARY FIBER ROLL LF 7.0000 24,500.00 1,396.000 9,772 018 TEMPORARY CONSTRUCTION ENTRANCE EA 4,200.0000 8,400.00 1.000 4,200 019 TEMPORARY CONCRETE WASHOUT LS 25,000.0000 25,000.00 1.000 25,000 020 REMOVE YELLOW THERMOPLASTIC TRAFFIC LF 1.1000 5,720.00 2,830.000 3,113 STRIPE (HAZARDOUS WASTE) 021 TREATED WOOD WASTE LB 24.0000 1,080.00 45.000 1,080 022 CLEARING AND GRUBBING (LS) LS 50,000.0000 50,000.00 1.000 50,000 PROGRAM CAS145 PAGE 2 DATE 10/25/21 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-1H7704 TIME 11:21 AM ESTIMATE NO. 013 BID OPENING 02/12/20 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/21 R.E. NAME: SUFIPUR, RAMBOD DATE OF THIS ESTIMATE 10/25/21 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 023 ROADWAY EXCAVATION CY 48.0000 480,000.00 8,369.460 401,734 024 SHOULDER BACKING TON 95.0000 12,350.00 118.110 11,220.45 125.670 11,938 025 STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 155.0000 18,135.00 117.000 18,135 (F) 026 STRUCTURE EXCAVATION (GROUND ANCHOR CY 86.0000 22,790.00 264.990 22,789 (F) WALL) 027 STRUCTURE BACKFILL (CULVERT) CY 270.0000 15,120.00 56.000 15,120 (F) 028 STRUCTURE BACKFILL (GROUND ANCHOR WALL) CY 440.0000 7,480.00 0.000 0 (F) 029 STRUCTURE BACKFILL (SOIL NAIL WALL) CY 630.0000 7,560.00 0.000 0 (F) 030 CONCRETE BACKFILL CY 205.0000 32,800.00 10.000 2,050.00 70.000 14,350 (F) 031 ROADSIDE CLEARING LS 10,000.0000 10,000.00 1.000 10,000 032 ROCK BLANKET SQFT 14.0000 57,540.00 2,284.200 31,978.80 4,185.000 58,590 033 MAINTAIN EXISTING PLANTED AREAS LS 5,500.0000 5,500.00 1.000 5,500 034 CHECK AND TEST EXISTING IRRIGATION LS 7,200.0000 7,200.00 0.800 5,760 FACILITIES 035 OPERATE EXISTING IRRIGATION FACILITIES LS 2,750.0000 2,750.00 1.000 2,750 036 REMOVE IRRIGATION FACILITY LS 8,800.0000 8,800.00 0.950 8,360 037 CONTROL AND NEUTRAL CONDUCTORS LS 30,000.0000 30,000.00 1.000 30,000 (ARMOR-CLAD) 038 1" REMOTE CONTROL VALVE EA 550.0000 550.00 1.000 550 039 1 1/2" REMOTE CONTROL VALVE EA 660.0000 3,300.00 5.000 3,300 040 2" REMOTE CONTROL VALVE EA 72.0000 1,080.00 15.000 1,080 041 RISER SPRINKLER ASSEMBLY (GEAR DRIVEN) EA 120.0000 1,080.00 9.000 1,080 042 POP-UP SPRINKLER ASSEMBLY (GEAR DRIVEN) EA 84.0000 6,804.00 85.000 7,140 043 1" PLASTIC PIPE (SCHEDULE 40) (SUPPLY LF 5.5000 1,309.00 238.000 1,309 (F) LINE) 044 1 1/2" PLASTIC PIPE (SCHEDULE 40) LF 7.0000 5,229.00 747.000 5,229 (F) (SUPPLY LINE) 045 2" PLASTIC PIPE (SCHEDULE 40) LF 9.0000 5,634.00 626.000 5,634 (F) (SUPPLY LINE) 046 2 1/2" PLASTIC PIPE (SCHEDULE 40) LF 11.0000 38,753.00 3,523.000 38,753 (F) (SUPPLY LINE) 047 3" PLASTIC PIPE (SCHEDULE 40) LF 16.0000 49,488.00 3,093.000 49,488 (F) (SUPPLY LINE) 048 BALL VALVE EA 395.0000 1,975.00 5.000 1,975 049 10" CORRUGATED STEEL PIPE CONDUIT LF 110.0000 1,100.00 10.000 1,100 (.064" THICK) PROGRAM CAS145 PAGE 3 DATE 10/25/21 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-1H7704 TIME 11:21 AM ESTIMATE NO. 013 BID OPENING 02/12/20 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/21 R.E. NAME: SUFIPUR, RAMBOD DATE OF THIS ESTIMATE 10/25/21 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 050 CLASS 2 AGGREGATE SUBBASE CY 70.0000 12,600.00 170.000 11,900 051 CLASS 2 AGGREGATE BASE (CY) CY 54.0000 122,040.00 2,689.150 145,214 052 LEAN CONCRETE BASE CY 275.0000 35,750.00 127.510 35,065 053 PRIME COAT TON 1,235.0000 29,640.00 2.000 2,470 054 HOT MIX ASPHALT (TYPE A) TON 100.0000 273,000.00 39.880 3,988.00 2,995.570 299,557 055 RUBBERIZED HOT MIX ASPHALT (GAP GRADED) TON 115.0000 115,000.00 1,187.440 136,555 056 PLACE HOT MIX ASPHALT DIKE (TYPE C) LF 16.0000 1,200.00 56.000 896.00 56.000 896 057 PLACE HOT MIX ASPHALT DIKE (TYPE E) LF 9.0000 16,290.00 1,608.000 14,472.00 1,608.000 14,472 058 PLACE HOT MIX ASPHALT DIKE (TYPE F) LF 11.0000 1,980.00 260.000 2,860.00 260.000 2,860 059 PLACE HOT MIX ASPHALT SQYD 108.0000 9,828.00 80.200 8,661 (MISCELLANEOUS AREA) 060 TACK COAT TON 2,230.0000 10,481.00 2.000 4,460 061 REMOVE BASE AND SURFACING CY 110.0000 14,300.00 72.000 7,920 062 JOINTED PLAIN CONCRETE PAVEMENT CY 500.0000 130,000.00 255.000 127,500 063 ISOLATION JOINT SEAL (SILICONE) LF 15.0000 9,150.00 0.000 0 064 GRIND EXISTING CONCRETE SQYD 44.0000 9,240.00 210.000 9,240 PAVEMENT 065 GROUND ANCHOR (SUBHORIZONTAL) EA 3,500.0000 224,000.00 64.000 224,000 066 SOIL NAIL LF 46.0000 176,962.00 4,147.100 190,766 067 60" CAST-IN-DRILLED-HOLE CONCRETE LF 1,175.0000 95,175.00 81.000 95,175 PILE (SIGN FOUNDATION) 068 STRUCTURAL CONCRETE, RETAINING WALL CY 1,875.0000 241,875.00 129.000 241,875 (F) 069 STRUCTURAL CONCRETE, DRAINAGE INLET CY 1,770.0000 49,560.00 23.200 41,064 (F) 070 CONCRETE SURFACE TEXTURE (MOUNTAIN SQFT 60.0000 101,160.00 1,517.000 91,020 (F) RELIEF) 071 FRACTURED RIB TEXTURE (ARROWHEAD) SQFT 30.0000 52,530.00 1,751.000 52,530 (F) 072 BAR REINFORCING STEEL LB 2.9000 27,608.00 9,520.000 27,608 (F) 073 BAR REINFORCING STEEL (RETAINING WALL) LB 1.4000 67,089.40 47,921.000 67,089 074 STRUCTURAL SHOTCRETE CY 1,150.0000 141,450.00 123.000 141,450 (F) 075 FURNISH SIGN STRUCTURE (TRUSS) LB 3.7500 231,510.00 61,736.000 231,510 (F) 076 INSTALL SIGN STRUCTURE (TRUSS) LB 0.5000 30,868.00 58,650.000 29,325 (F) PROGRAM CAS145 PAGE 4 DATE 10/25/21 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-1H7704 TIME 11:21 AM ESTIMATE NO. 013 BID OPENING 02/12/20 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/21 R.E. NAME: SUFIPUR, RAMBOD DATE OF THIS ESTIMATE 10/25/21 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 077 REMOVE SIGN STRUCTURE (EA) EA 14,500.0000 14,500.00 0.060 870.00 1.000 14,500 078 18" ALTERNATIVE PIPE CULVERT LF 315.0000 14,175.00 16.000 5,040 079 24" ALTERNATIVE PIPE CULVERT LF 310.0000 20,150.00 63.000 19,530 080 18" REINFORCED CONCRETE PIPE (CLASS IV) LF 160.0000 28,800.00 175.000 28,000 081 24" REINFORCED CONCRETE PIPE (CLASS IV) LF 190.0000 104,500.00 496.700 94,373 082 30" REINFORCED CONCRETE PIPE (CLASS IV) LF 245.0000 73,500.00 291.000 71,295 083 48" REINFORCED CONCRETE PIPE (CLASS IV) LF 1,230.0000 11,070.00 9.000 11,070 084 GEOCOMPOSITE DRAIN SQFT 12.0000 14,076.00 1,230.000 14,760 085 36" PRECAST CONCRETE PIPE INLET LF 1,570.0000 5,495.00 3.500 5,495 086 ABANDON CULVERT (LF) LF 55.0000 8,250.00 0.000 0 087 REMOVE CULVERT (LF) LF 71.0000 64,610.00 1,087.000 77,177 088 REMOVE INLET EA 3,300.0000 16,500.00 5.000 16,500 089 SAND BACKFILL CY 610.0000 10,980.00 1.860 1,134 090 REMOVE SLOPE PAVING (SQYD) SQYD 280.0000 9,240.00 33.000 9,240 091 SLOPE PAVING (CONCRETE) CY 4,580.0000 13,740.00 0.000 0 092 MINOR CONCRETE (GUTTER) (LF) LF 87.0000 23,751.00 0.000 0 093 MINOR CONCRETE (CURB AND GUTTER) CY 1,600.0000 22,400.00 15.000 24,000 094 MISCELLANEOUS IRON AND STEEL LB 3.0000 10,425.00 2,823.000 8,469 (F) 095 REMOVE PAVEMENT MARKER EA 1.2000 1,116.00 743.000 891 096 DELINEATOR (CLASS 1) EA 56.0000 3,528.00 0.000 0 097 GUARD RAILING DELINEATOR EA 27.0000 1,188.00 0.000 0 098 PAVEMENT MARKER (RETROREFLECTIVE) EA 2.4000 2,232.00 0.000 0 099 MARKER (CULVERT) EA 135.0000 1,350.00 0.000 0 100 OBJECT MARKER EA 165.0000 495.00 0.000 0 101 ITEM DELETED PER ADDENDUM LS 0.0000 0.00 0.000 0 102 REMOVE ROADSIDE SIGN EA 165.0000 3,795.00 0.000 0 103 REMOVE SIGN PANEL EA 2,750.0000 2,750.00 0.000 0 PROGRAM CAS145 PAGE 5 DATE 10/25/21 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-1H7704 TIME 11:21 AM ESTIMATE NO. 013 BID OPENING 02/12/20 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/21 R.E. NAME: SUFIPUR, RAMBOD DATE OF THIS ESTIMATE 10/25/21 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 104 FURNISH LAMINATED PANEL SIGN (1"-TYPE A) SQFT 30.0000 25,200.00 766.000 22,980 105 FURNISH LAMINATED PANEL SIGN (1"-TYPE B) SQFT 31.0000 7,130.00 0.000 0 106 FURNISH SINGLE SHEET ALUMINUM SIGN SQFT 14.0000 2,660.00 0.000 0 (0.063"-UNFRAMED) 107 ROADSIDE SIGN - ONE POST EA 440.0000 3,520.00 0.000 0 108 ROADSIDE SIGN - TWO POST EA 715.0000 1,430.00 0.000 0 109 RETROREFLECTIVE SHEETING TYPE XI SQFT 3.8000 4,066.00 0.000 0 110 INSTALL SIGN PANEL ON EXISTING FRAME SQFT 46.0000 3,312.00 0.000 0 111 RETROREFLECTIVE SHEETING TYPE XI SQFT 5.4000 3,564.00 0.000 0 (FOR CONSTRUCTION AREA SIGN) 112 MIDWEST GUARDRAIL SYSTEM (WOOD POST) LF 38.0000 19,000.00 150.000 5,700.00 325.000 12,350 113 VEGETATION CONTROL (MINOR CONCRETE) SQYD 96.0000 42,240.00 98.000 9,408.00 248.000 23,808 114 CABLE RAILING LF 38.0000 10,374.00 273.000 10,374.00 273.000 10,374 115 END ANCHOR ASSEMBLY (TYPE SFT) EA 1,100.0000 3,300.00 1.000 1,100.00 2.000 2,200 116 ALTERNATIVE IN-LINE TERMINAL SYSTEM EA 4,400.0000 13,200.00 1.000 4,400.00 2.000 8,800 117 CONCRETE BARRIER (TYPE 60MD MODIFIED) LF 115.0000 31,395.00 0.000 0 118 CONCRETE BARRIER (TYPE 60MGF) LF 330.0000 42,900.00 130.000 42,900.00 130.000 42,900 119 CONCRETE BARRIER (TYPE 60MS) LF 365.0000 25,550.00 70.000 25,550.00 70.000 25,550 120 REMOVE GUARDRAIL LF 13.0000 1,560.00 115.000 1,495 121 REMOVE CONCRETE BARRIER LF 165.0000 33,000.00 192.000 31,680 122 THERMOPLASTIC PAVEMENT MARKING SQFT 25.0000 1,650.00 0.000 0 (ENHANCED WET NIGHT VISIBILITY) 123 PAINT TRAFFIC STRIPE (2-COAT) LF 0.2000 1,086.00 0.000 0 124 PAINT PAVEMENT MARKING (2-COAT) SQFT 2.6000 546.00 186.000 483 125 6" THERMOPLASTIC TRAFFIC STRIPE LF 0.6000 6,600.00 0.000 0 (ENHANCED WET NIGHT VISIBILITY) 126 8" THERMOPLASTIC TRAFFIC STRIPE LF 0.9000 1,206.00 0.000 0 (ENHANCED WET NIGHT VISIBILITY) 127 REMOVE THERMOPLASTIC TRAFFIC STRIPE LF 0.5000 3,537.50 7,012.000 3,506 128 REMOVE THERMOPLASTIC PAVEMENT MARKING SQFT 3.3000 217.80 75.000 247 129 8" TRAFFIC STRIPE TAPE WITH CONTRAST LF 3.4000 13,260.00 0.000 0 (BROKEN 36-12) (WARRANTY) 130 ITEM DELETED PER ADDENDUM LS 0.0000 0.00 0.000 0 PROGRAM CAS145 PAGE 6 DATE 10/25/21 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-1H7704 TIME 11:21 AM ESTIMATE NO. 013 BID OPENING 02/12/20 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/21 R.E. NAME: SUFIPUR, RAMBOD DATE OF THIS ESTIMATE 10/25/21 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 131 ITEM DELETED PER ADDENDUM LS 0.0000 0.00 0.000 0 132 MAINTAINING EXISTING TRAFFIC MANAGEMENT LS 5,000.0000 5,000.00 1.000 5,000 SYSTEM ELEMENTS DURING CONSTRUCTION 133 CAMERA SYSTEMS LS 27,500.0000 27,500.00 0.016 440.00 0.662 18,205 134 MODIFYING LIGHTING SYSTEMS LS 110,000.0000 110,000.00 0.900 99,000 135 MODIFYING SIGNAL AND LIGHTING SYSTEMS LS 30,000.0000 30,000.00 0.730 21,900 136 MODIFYING RAMP METERING SYSTEMS LS 180,000.0000 180,000.00 0.800 144,000 137 ITEM DELETED PER ADDENDUM LS 0.0000 0.00 0.000 0 138 6" TRAFFIC STRIPE TAPE WITH CONTRAST LF 2.3500 27,495.00 0.000 0 (BROKEN 36-12) (WARRANTY)) 139 8" TRAFFIC STRIPE TAPE WITH CONTRAST LF 2.7500 66,000.00 0.000 0 (BROKEN 12-3) (WARRANTY)) 140 STORM WATER ANNUAL REPORT EA 2,000.0000 2,000.00 1.000 2,000 141 THERMOPLASTIC PAVEMENT MARKING SQFT 15.0000 29,700.00 0.000 0 PROGRAM CAS145 PAGE 7 DATE 10/25/21 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-1H7704 TIME 11:21 AM ESTIMATE NO. 013 BID OPENING 02/12/20 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/21 R.E. NAME: SUFIPUR, RAMBOD DATE OF THIS ESTIMATE 10/25/21 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION 168,207.25 4,578,278.88 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 10,341.94 10,341.94 SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION 178,549.19 4,588,620.82 142 MOBILIZATION LS 473,472.0000 473,472.00 1.000 473,472 ORIGINAL CONTRACT AMOUNT 5,559,700.00 TOTAL WORK COMPLETED 178,549.19 5,062,092.82 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 178,549.19 5,062,092.82 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 06/29/20 180 10/13/20 10/13/20 12/15/21 180 47 0 0 89% 100% PROGRESS IS SATISFACTORY SUFIPUR, RAMBOD RESIDENT ENGINEER PROGRAM CAS145 DATE 10/25/21