PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 09/24/03 EST. NO.15 TIME 02:35 PM R.E. NAME: OZOWARA, DENIS O. 08-4047U4 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0149 134.97 E.W. @ F.A.(+) 072103 N 001147 0150 204.12 072203 N 001148 0151 243.00 073003 N 001149 0152 1,371.19 080403 N 001150 0153 243.03 080403 N 001151 0154 1,201.12 080503 N 001152 0155 218.65 080503 N 001153 0157 1,613.73 080603 N 001155 0158 249.46 080703 N 001156 0159 193.57 080803 N 001157 0160 289.15 080803 N 001158 0161 233.86 081103 N 001159 0162 242.98 081203 N 001160 0163 249.49 081303 N 001161 0164 877.78 081303 N 001162 0165 122.75 081403 N 001163 0166 1,566.32 081903 N 001164 0167 1,164.39 082103 N 001165 0168 535.46 082203 N 001166 0169 151.34 082503 N 001167 0170 361.09 082603 N 001168 0172 204.12 072303 N 001170 0173 204.12 072403 N 001171 0174 127.57 072503 N 001172 0175 146.55 072803 N 001173 0176 212.04 072803 N 001174 0177 212.04 072903 N 001175 0178 242.92 073103 N 001176 0180 499.54 082703 N 001178 0181 707.74 090203 N 001179 0182 168.54 090303 N 001180 0183 218.22 090403 N 001181 0184 1,207.49 090403 N 001182 0185 205.56 091003 N 001183 015 0005 1,681.46 E.W. @ F.A.(+) 030503 N 015005 0013 1,287.82 071503 N 015013 0014 1,931.74 071603 N 015014 017 0001 1,468.77 E.W. @ F.A.(+) 032803 Y 017001 0002 445.70 033103 Y 017002 0003 374.57 040103 Y 017003 0004 2,526.58 041003 Y 017004 0005 2,064.20 042503 Y 017005 0006 291.32 042403 Y 017006 0007 335.64 052103 Y 017007 0008 360.46 052203 Y 017008 0009 222.19 052703 Y 017009 0010 360.46 052803 Y 017010 0011 513.50 060303 Y 017011 0012 1,194.84 051603 Y 017012 0013 473.91 051903 Y 017013 0014 888.74 052003 Y 017014 PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 2 DATE 09/24/03 EST. NO.15 TIME 02:35 PM R.E. NAME: OZOWARA, DENIS O. 08-4047U4 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 0015 291.32 052703 Y 017015 0016 370.24 033103 Y 017016 021 0005 1,399.23 E.W. @ F.A.(+) 071603 N 021005 0006 611.57 071703 N 021006 0007 515.19 082003 N 021007 0008 3,324.26 082103 N 021008 0009 1,535.03 082503 N 021009 0011 1,538.64 082503 N 021011 0012 1,650.77 082703 N 021012 0013 2,405.22 090203 N 021013 0014 1,389.13 090303 N 021014 47,276.40 TOTAL THIS ESTIMATE 412,073.12 TOTAL PREVIOUS ESTIMATE 459,349.52 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 09/24/03 EST. NO.15 TIME 02:35 PM R.E. NAME: OZOWARA, DENIS O. 08-4047U4 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- ADMINISTRATIVE MIX DESIGN CHANGE -1,500.00 10 MIX DESIGN -1,500.00 14 0.00 -3,000.00 OVERBID ITEMS OVERBID ITEM NO. 149 -57,031.60 04 OVERBID ITEM NO. 149 -28,515.80 06 OVERBID ITEM NO. 149 -22,812.64 09 0.00 -108,360.04 TOTAL DEDUCTIONS 0.00 -111,360.04 PROGRAM CAS145 PAGE 1 DATE 09/24/03 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-4047U4 TIME 02:35 PM ESTIMATE NO. 15 BID OPENING 05/23/02 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/19/03 R.E. NAME: OZOWARA, DENIS O. DATE OF THIS ESTIMATE 09/24/03 LOCATION PROGRESS ESTIMATE 08-SBD-15-R137.0/163.3 ----------------- GRANITE CONSTRUCTION COMPANY IN SAN BERNARDINO COUNTY NEAR BAKER 38000 MONROE STREET FROM 1.9 KM WEST OF EAST BAKER INDIO, CA 92203-9500 OVERCROSSING TO 0.6 KM EAST OF CIMA ROAD OVERCROSSING FED. AID NO. ACIM-015 -3(39)242,ACIM-015 -3(39)N REHABILITATE ROADWAY ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 PROGRESS SCHEDULE (CRITICAL PATH METHOD) LS 500.0000 500.00 0.500 250.00 0.750 375.00 02 LEAD COMPLIANCE PLAN LS 500.0000 500.00 1.000 500.00 03 TIME-RELATED OVERHEAD WDAY 6,300.0000 2,394,000.00 20.000 126,000.00 185.000 1,165,500.00 04 TEMPORARY TORTOISE FENCE M 15.0000 14,400.00 720.000 10,800.00 05 600 MM TEMPORARY CULVERT M 85.0000 35,700.00 155.500 13,217.50 06 PREPARE STORM WATER POLLUTION LS 1,000.0000 1,000.00 0.750 750.00 PREVENTION PLAN 07 WATER POLLUTION CONTROL LS 50,000.0000 50,000.00 0.052 2,600.00 0.483 24,150.00 08 CONSTRUCTION AREA SIGNS LS 50,000.0000 50,000.00 0.020 1,000.00 0.620 31,000.00 S) 09 TRAFFIC CONTROL SYSTEM LS 100,000.0000 100,000.00 0.052 5,200.00 0.483 48,300.00 S) 10 TEMPORARY PAVEMENT MARKING (PAINT) M2 60.0000 2,280.00 0.000 0.00 S) 11 TEMPORARY TRAFFIC STRIPE (PAINT) M 0.4500 93,150.00 132,547.000 59,646.15 317,843.000 143,029.35 S) 12 CHANNELIZER (SURFACE MOUNTED) EA 30.0000 2,070.00 0.000 0.00 S) 13 FLASHING BEACON (PORTABLE) EA 5,000.0000 10,000.00 1.000 5,000.00 S) 14 TEMPORARY PAVEMENT MARKER EA 4.0000 38,760.00 5,937.000 23,748.00 14,613.000 58,452.00 S) 15 PORTABLE CHANGEABLE MESSAGE SIGN EA 7,000.0000 42,000.00 3.000 21,000.00 S) 16 TEMPORARY RAILING (TYPE K) M 35.0000 1,214,500.00 12,404.930 434,172.55 41,185.310 1,441,485.85 S) 17 TEMPORARY CRASH CUSHION MODULE EA 250.0000 11,000.00 110.000 27,500.00 S) 18 TEMPORARY TRAFFIC SCREEN M 6.0000 185,400.00 0.000 0.00 S) 19 ABANDON CULVERT EA 1,000.0000 3,000.00 2.000 2,000.00 20 REMOVE ENTRANCE TAPER EA 500.0000 15,500.00 12.000 6,000.00 21 REMOVE FLARED END SECTION EA 200.0000 13,000.00 59.000 11,800.00 22 REMOVE YELLOW PAINTED TRAFFIC STRIPE M 1.4000 105,980.00 1,471.000 2,059.40 105,855.600 148,197.84 PROGRAM CAS145 PAGE 2 DATE 09/24/03 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-4047U4 TIME 02:35 PM ESTIMATE NO. 15 BID OPENING 05/23/02 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/19/03 R.E. NAME: OZOWARA, DENIS O. DATE OF THIS ESTIMATE 09/24/03 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 23 REMOVE YELLOW THERMOPLASTIC TRAFFIC M 1.4000 61,180.00 410.000 574.00 STRIPE 24 REMOVE PAVEMENT MARKER EA 0.8000 11,440.00 11,569.000 9,255.20 25 REMOVE SIGN STRUCTURE EA 12,000.0000 60,000.00 1.000 12,000.00 26 REMOVE ASPHALT CONCRETE M2 12.0000 7,320.00 309.800 3,717.60 27 REMOVE ASPHALT CONCRETE DIKE M 0.7500 22,800.00 16,676.000 12,507.00 28 REMOVE CORRUGATED STEEL PIPE M 60.0000 11,400.00 159.560 9,573.60 29 REMOVE INLET EA 300.0000 2,400.00 8.000 2,400.00 30 REMOVE DOWNDRAIN M 50.0000 14,500.00 123.600 6,180.00 31 REMOVE ASPHALT CONCRETE SURFACING M2 10.0000 23,100.00 1,293.210 12,932.10 32 REMOVE ASPHALT CONCRETE OVERSIDE DRAIN EA 300.0000 33,000.00 19.000 5,700.00 33 SALVAGE METAL BEAM GUARD RAILING M 16.0000 29,760.00 107.760 1,724.16 974.480 15,591.68 34 ITEM DELETED PER ADDENDUM LS 0.0000 0.00 0.000 0.00 35 RELAY ENTRANCE TAPER AND PIPE DOWNDRAIN EA 800.0000 7,200.00 5.000 4,000.00 36 RELAY STEEL FLARED END SECTION EA 325.0000 20,800.00 34.000 11,050.00 37 RESET ROADSIDE SIGN (TWO POST) EA 1,000.0000 2,000.00 0.000 0.00 38 RELOCATE ROADSIDE SIGN-ONE POST EA 500.0000 1,000.00 0.000 0.00 39 RELOCATE ROADSIDE SIGN-TWO POST EA 1,000.0000 1,000.00 0.000 0.00 40 PLASTIC PIPE LINER (538 MM O.D.) M 300.0000 33,000.00 0.000 0.00 41 COLD PLANE ASPHALT CONCRETE PAVEMENT M2 0.5500 110,000.00 5,718.000 3,144.90 49,685.200 27,326.86 S) (30 MM MAXIMUM) 42 COLD PLANE ASPHALT CONCRETE PAVEMENT M2 1.8000 217,800.00 32,777.100 58,998.78 42,558.300 76,604.94 S) (60 MM MAXIMUM) 43 COLD PLANE ASPHALT CONCRETE PAVEMENT M2 2.2000 624,800.00 79,823.000 175,610.60 S) (90 MM MAXIMUM) 44 COLD PLANE ASPHALT CONCRETE PAVEMENT M2 3.1000 165,230.00 3,452.400 10,702.44 57,435.910 178,051.32 S) (120 MM MAXIMUM) 45 COLD PLANE ASPHALT CONCRETE PAVEMENT M2 4.0000 9,040.00 34,005.600 136,022.40 S) (135 MM MAXIMUM) 46 COLD PLANE ASPHALT CONCRETE PAVEMENT M2 4.8000 26,496.00 49,706.400 238,590.72 S) (180 MM MAXIMUM) 47 REMOVE CONCRETE CURB M 12.0000 8,640.00 250.000 3,000.00 48 PREPARE CONCRETE BRIDGE DECK SURFACE M2 20.0000 46,400.00 519.660 10,393.20 894.660 17,893.20 49 CLEAN BRIDGE DECK M2 12.0000 9,396.00 500.000 6,000.00 790.000 9,480.00 PROGRAM CAS145 PAGE 3 DATE 09/24/03 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-4047U4 TIME 02:35 PM ESTIMATE NO. 15 BID OPENING 05/23/02 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/19/03 R.E. NAME: OZOWARA, DENIS O. DATE OF THIS ESTIMATE 09/24/03 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 50 REMOVE CONCRETE (MISCELLANEOUS) M3 1,000.0000 8,000.00 0.000 0.00 51 BRIDGE REMOVAL (PORTION), LOCATION A LS 20,890.0000 20,890.00 0.800 16,712.00 52 BRIDGE REMOVAL (PORTION), LOCATION B LS 4,980.0000 4,980.00 1.000 4,980.00 53 BRIDGE REMOVAL (PORTION), LOCATION C LS 5,420.0000 5,420.00 1.000 5,420.00 54 BRIDGE REMOVAL (PORTION), LOCATION D LS 10,930.0000 10,930.00 1.000 10,930.00 55 BRIDGE REMOVAL (PORTION), LOCATION E LS 4,980.0000 4,980.00 1.000 4,980.00 56 BRIDGE REMOVAL (PORTION), LOCATION F LS 3,560.0000 3,560.00 0.000 0.00 57 BRIDGE REMOVAL (PORTION), LOCATION G LS 3,290.0000 3,290.00 0.000 0.00 58 BRIDGE REMOVAL (PORTION), LOCATION H LS 6,490.0000 6,490.00 0.000 0.00 59 BRIDGE REMOVAL (PORTION), LOCATION I LS 5,960.0000 5,960.00 0.000 0.00 60 BRIDGE REMOVAL (PORTION), LOCATION J LS 6,850.0000 6,850.00 0.000 0.00 61 BRIDGE REMOVAL, LOCATION K LS 16,000.0000 16,000.00 1.000 16,000.00 62 BRIDGE REMOVAL, LOCATION L LS 29,000.0000 29,000.00 0.000 0.00 63 DEVELOP WATER SUPPLY LS 27,000.0000 27,000.00 1.000 27,000.00 64 ROADWAY EXCAVATION M3 6.5000 370,500.00 105,780.290 687,571.89 65 ROADWAY EXCAVATION (TYPE Y) M3 2.5000 45,000.00 18,000.000 45,000.00 (AERIALLY DEPOSITED LEAD) 66 ROADWAY EXCAVATION (DETOUR REMOVAL) M3 7.0000 195,300.00 2,039.000 14,273.00 2,039.000 14,273.00 67 SHOULDER BACKING STA 70.0000 95,200.00 176.000 12,320.00 319.000 22,330.00 68 STRUCTURE EXCAVATION (BRIDGE) M3 35.0000 79,450.00 1,813.330 63,466.55 F) 69 STRUCTURE EXCAVATION (ROCK) M3 125.0000 16,625.00 133.000 16,625.00 F) 70 STRUCTURE EXCAVATION (RETAINING WALL) M3 27.0000 2,700.00 100.000 2,700.00 F) 71 STRUCTURE BACKFILL (BRIDGE) M3 27.0000 41,040.00 1,109.550 29,957.85 F) 72 STRUCTURE BACKFILL (RETAINING WALL) M3 20.0000 1,480.00 74.000 1,480.00 74.000 1,480.00 F) 73 SAND BACKFILL M3 375.0000 5,625.00 8.000 3,000.00 74 IMPORTED BORROW M3 6.7500 2,133,000.00 250,000.000 1,687,500.00 75 FIBER (EROSION CONTROL) KG 1.0000 27,000.00 0.000 0.00 S) 76 STABILIZING EMULSION (EROSION CONTROL) KG 2.5000 13,500.00 0.000 0.00 S) PROGRAM CAS145 PAGE 4 DATE 09/24/03 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-4047U4 TIME 02:35 PM ESTIMATE NO. 15 BID OPENING 05/23/02 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/19/03 R.E. NAME: OZOWARA, DENIS O. DATE OF THIS ESTIMATE 09/24/03 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 77 TRANSPLANT JOSHUA TREE EA 600.0000 12,000.00 20.000 12,000.00 S) 78 CLASS 2 AGGREGATE BASE M3 21.0000 1,493,100.00 1,658.880 34,836.48 82,572.850 1,734,029.85 79 AGGREGATE BASE (APPROACH SLAB) M3 250.0000 8,750.00 12.000 3,000.00 80 ASPHALTIC EMULSION (FOG SEAL COAT) TONN 125.0000 21,250.00 13.500 1,687.50 81 ASPHALT CONCRETE TONN 34.0000 3,502,000.00 869.210 29,553.14 30,729.890 1,044,816.26 82 ASPHALT CONCRETE (TYPE B) TONN 41.0000 463,300.00 0.000 0.00 83 ASPHALT CONCRETE (LEVELING) TONN 37.0000 108,780.00 6,322.790 233,943.23 84 ASPHALT CONCRETE TONN 40.0000 8,040,000.00 11,337.770 453,510.80 150,012.070 6,000,482.80 (TYPE C - PBA-6A MODIFIED) 85 ASPHALT CONCRETE (TYPE C - AR 8000) TONN 36.0000 2,023,200.00 597.320 21,503.52 41,762.010 1,503,432.36 86 ASPHALT CONCRETE (OPEN GRADED) TONN 38.0000 832,200.00 0.000 0.00 87 PLACE ASPHALT CONCRETE (MISCELLANEOUS M2 46.0000 159,160.00 846.340 38,931.64 846.340 38,931.64 AREA) 88 PLACE ASPHALT CONCRETE DIKE (TYPE C) M 1.5000 1,935.00 406.010 609.02 406.010 609.02 89 PLACE ASPHALT CONCRETE DIKE (TYPE E) M 1.5000 40,050.00 8,487.400 12,731.10 8,487.400 12,731.10 90 PLACE ASPHALT CONCRETE DIKE (TYPE F) M 1.5000 3,270.00 586.700 880.05 586.700 880.05 91 RUMBLE STRIP STA 10.0000 16,500.00 0.000 0.00 92 CONCRETE PAVEMENT M3 74.0000 7,770,000.00 0.000 0.00 93 SEAL PAVEMENT JOINT M 3.0000 405,000.00 0.000 0.00 94 600 MM CAST-IN-DRILLED-HOLE CONCRETE M 315.0000 94,185.00 309.250 97,413.75 S) PILING 95 PRESTRESSING CAST-IN-PLACE CONCRETE LS 50,000.0000 50,000.00 0.000 0.00 S) 96 STRUCTURAL CONCRETE, BRIDGE FOOTING M3 375.0000 142,500.00 284.990 106,871.25 F) 97 STRUCTURAL CONCRETE, BRIDGE M3 600.0000 786,000.00 1,023.180 613,908.00 F) 98 STRUCTURAL CONCRETE, RETAINING WALL M3 600.0000 14,400.00 24.000 14,400.00 F) 99 STRUCTURAL CONCRETE, APPROACH SLAB M3 850.0000 167,450.00 85.000 72,250.00 160.550 136,467.50 F) (TYPE N) 00 STRUCTURAL CONCRETE, APPROACH SLAB M3 700.0000 229,600.00 1.750 1,225.00 105.920 74,144.00 (TYPE R) 01 MINOR CONCRETE (MINOR STRUCTURE) M3 1,000.0000 12,000.00 11.090 11,090.00 F) 02 PAVING NOTCH EXTENSION M3 2,500.0000 17,500.00 0.000 0.00 03 DRILL AND BOND DOWEL M 50.0000 2,000.00 35.420 1,771.00 PROGRAM CAS145 PAGE 5 DATE 09/24/03 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-4047U4 TIME 02:35 PM ESTIMATE NO. 15 BID OPENING 05/23/02 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/19/03 R.E. NAME: OZOWARA, DENIS O. DATE OF THIS ESTIMATE 09/24/03 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 04 FURNISH POLYESTER CONCRETE OVERLAY M3 1,500.0000 120,000.00 31.740 47,610.00 65.740 98,610.00 05 PLACE POLYESTER CONCRETE OVERLAY M2 15.0000 46,650.00 1,032.150 15,482.25 1,707.150 25,607.25 F) 06 JOINT SEAL (TYPE AL) M 120.0000 1,440.00 11.000 1,320.00 11.000 1,320.00 S) 07 JOINT SEAL (MR 15 MM) M 100.0000 53,400.00 260.020 26,002.00 260.020 26,002.00 S) 08 BAR REINFORCING STEEL (BRIDGE) KG 1.0000 119,870.00 98,185.000 98,185.00 SF) 09 BAR REINFORCING STEEL (RETAINING WALL) KG 1.0000 1,240.00 1,240.000 1,240.00 SF) 10 BAR REINFORCING STEEL (EPOXY COATED) KG 2.0000 110,740.00 38,320.300 76,640.60 SF)(BRIDGE) 11 SILANE SEAL CONCRETE SURFACE M2 16.0000 48,960.00 0.000 0.00 F) 12 FURNISH SIGN STRUCTURE (LIGHTWEIGHT) KG 4.2500 6,693.75 1,575.000 6,693.75 F) 13 INSTALL SIGN STRUCTURE (LIGHTWEIGHT) KG 2.5000 3,937.50 1,575.000 3,937.50 F) 14 FURNISH SIGN STRUCTURE (TRUSS) KG 4.2500 107,525.00 15,040.000 63,920.00 F) 15 INSTALL SIGN STRUCTURE (TRUSS) KG 2.5000 63,250.00 15,040.000 37,600.00 F) 16 760 MM CAST-IN-DRILLED-HOLE M 1.0000 24.00 0.000 0.00 CONCRETE PILE (SIGN FOUNDATION) 17 920 MM CAST-IN-DRILLED-HOLE M 1,000.0000 33,000.00 20.000 20,000.00 CONCRETE PILE (SIGN FOUNDATION) 18 ROADSIDE SIGN - ONE POST EA 250.0000 500.00 0.000 0.00 19 ROADSIDE SIGN - TWO POST EA 350.0000 1,050.00 0.000 0.00 20 600 MM BITUMINOUS COATED CORRUGATED M 200.0000 158,000.00 763.360 152,672.00 STEEL PIPE (2.01 MM THICK) 21 900 MM BITUMINOUS COATED CORRUGATED M 230.0000 36,800.00 216.450 49,783.50 STEEL PIPE (2.01 MM THICK) 22 900 MM CORRUGATED STEEL PIPE INLET M 450.0000 24,750.00 41.200 18,540.00 (2.01 MM THICK) 23 ROCK SLOPE PROTECTION M3 150.0000 4,200.00 0.000 0.00 F) (1/4 TON, METHOD B) 24 ROCK SLOPE PROTECTION FABRIC M2 20.0000 1,380.00 0.000 0.00 F) 25 MISCELLANEOUS IRON AND STEEL KG 2.5000 12,950.00 4,647.000 11,617.50 S) 26 TEMPORARY TORTOISE FENCE M 14.0000 970,200.00 82,400.000 1,153,600.00 27 DELINEATOR (CLASS 1) EA 40.0000 19,200.00 136.000 5,440.00 136.000 5,440.00 28 OBJECT MARKER (TYPE P) EA 200.0000 200.00 0.000 0.00 29 METAL BEAM GUARD RAILING (WOOD POST) M 80.0000 285,600.00 883.920 70,713.60 1,131.570 90,525.60 S) 30 TERMINAL SYSTEM (TYPE ET) EA 4,000.0000 36,000.00 1.000 4,000.00 1.000 4,000.00 S) PROGRAM CAS145 PAGE 6 DATE 09/24/03 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-4047U4 TIME 02:35 PM ESTIMATE NO. 15 BID OPENING 05/23/02 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/19/03 R.E. NAME: OZOWARA, DENIS O. DATE OF THIS ESTIMATE 09/24/03 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 31 TERMINAL SYSTEM (TYPE SRT) EA 2,000.0000 142,000.00 16.000 32,000.00 25.000 50,000.00 S) 32 TERMINAL ANCHOR ASSEMBLY (TYPE CA) EA 1,000.0000 8,000.00 4.000 4,000.00 4.000 4,000.00 S) 33 RETURN SECTION EA 200.0000 1,600.00 4.000 800.00 4.000 800.00 S) 34 CRASH CUSHION, SAND FILLED EA 5,400.0000 21,600.00 0.000 0.00 S) 35 CONCRETE BARRIER (TYPE 732) M 230.0000 50,140.00 50.000 11,500.00 158.000 36,340.00 F) 36 CONCRETE BARRIER (TYPE 732R) M 275.0000 18,700.00 0.000 0.00 F) 37 CONCRETE BARRIER (TYPE 732 MOD) M 300.0000 98,700.00 108.000 32,400.00 F) 38 THERMOPLASTIC PAVEMENT MARKING M2 20.0000 5,200.00 0.000 0.00 S) 39 THERMOPLASTIC TRAFFIC STRIPE M 0.5000 158,500.00 0.000 0.00 S) (SPRAYABLE) 40 PAVEMENT MARKER (RETROREFLECTIVE) EA 2.5000 24,225.00 0.000 0.00 S) 41 PAVEMENT MARKER EA 9.0000 316,800.00 0.000 0.00 S) (RETROREFLECTIVE-RECESSED) 42 HIGHWAY LIGHTING LS 325,000.0000 325,000.00 0.106 34,450.00 0.697 226,525.00 S) 43 LIGHTING (STAGE CONSTRUCTION) LS 175,000.7500 175,000.75 0.006 1,050.00 0.276 48,300.21 S) 44 SIGN ILLUMINATION LS 25,000.0000 25,000.00 0.556 13,900.00 S) 45 MODIFY SIGN ILLUMINATION LS 10,000.0000 10,000.00 0.000 0.00 S) 46 MODIFY TRAFFIC MONITORING STATION LS 10,000.0000 10,000.00 0.000 0.00 S) (COUNT) 47 ITEM DELETED PER ADDENDUM LS 0.0000 0.00 0.000 0.00 48 914 MM CAST-IN-DRILLED-HOLE CONCRETE M 1,000.0000 4,600.00 4.600 4,600.00 PILE (SIGN FOUNDATION) PROGRAM CAS145 PAGE 7 DATE 09/24/03 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-4047U4 TIME 02:35 PM ESTIMATE NO. 15 BID OPENING 05/23/02 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 09/19/03 R.E. NAME: OZOWARA, DENIS O. DATE OF THIS ESTIMATE 09/24/03 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION 1,694,111.18 20,792,454.27 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 47,276.40 459,349.52 SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION 1,741,387.58 21,251,803.79 49 MOBILIZATION LS 4482,400.0000 4,482,400.00 0.950 4,258,280.00 ORIGINAL CONTRACT AMOUNT 43,683,368.00 TOTAL WORK COMPLETED 1,741,387.58 25,510,083.79 MATERIALS ON HAND ON SITE 263,103.02 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 -111,360.04 TOTAL 1,741,387.58 25,661,826.77 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE MAXIMUM CONTRACT OVERBID VALUE PRICE AMOUNT 149 MOBILIZATION 4,368,336.80 4,482,400.00 114,063.20 DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 07/12/02 380 10/08/02 09/10/02 07/03/04 185 71 3 0 55% 48% PROGRESS IS SATISFACTORY OZOWARA, DENIS O. RESIDENT ENGINEER PROGRAM CAS145 PAGE 6 DATE 09/24/03