PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 02/25/05 EST. NO.09 TIME 09:25 AM R.E. NAME: SPRAY, MICHAEL 08-474204 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 006 0007 1,701.90 A.C. @ L.S.(+) 092804 N 1 0 013 0002 2,480.00 E.W. @ L.S.(+) 020405 N 3 0 4,181.90 TOTAL THIS ESTIMATE 53,383.71 TOTAL PREVIOUS ESTIMATE 57,565.61 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 02/25/05 EST. NO.09 TIME 09:25 AM R.E. NAME: SPRAY, MICHAEL 08-474204 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 02/25/05 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-474204 TIME 09:25 AM ESTIMATE NO. 09 BID OPENING 03/25/04 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 02/18/05 R.E. NAME: SPRAY, MICHAEL DATE OF THIS ESTIMATE 02/25/05 LOCATION PROGRESS ESTIMATE 08-SBD-10-30.9/31.9 ----------------- DIVERSIFIED LANDSCAPE COMPANY IN SAN BERNARDINO COUNTY IN 33801 WASHINGTON ST. REDLANDS FROM 10 AND 38 SEPARATION WINCHESTER, CA 92596 TO UNIVERSITY STREET UNDERCROSSING FED. AID NO. ACIM-010 -2(251)78E HIGHWAY PLANTING AND IRRIGATION ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 PREPARE STORM WATER POLLUTION LS 3,850.0000 3,850.00 1.000 3,850.00 PREVENTION PLAN 02 WATER POLLUTION CONTROL LS 39,333.0000 39,333.00 0.088 3,461.30 0.726 28,555.76 03 CONSTRUCTION AREA SIGNS LS 12,100.0000 12,100.00 0.178 2,153.80 0.900 10,890.00 S) 04 TRAFFIC CONTROL SYSTEM LS 48,000.0000 48,000.00 0.170 8,160.00 0.950 45,600.00 S) 05 ROADWAY EXCAVATION (TYPE Y) M3 265.0000 11,660.00 44.000 11,660.00 (AERIALLY DEPOSITED LEAD) 06 LEAD COMPLIANCE PLAN LS 3,600.0000 3,600.00 1.000 3,600.00 07 ROADSIDE CLEARING LS 46,800.0000 46,800.00 0.178 8,330.40 0.900 42,120.00 08 PRUNE EXISTING PLANTS LS 42,000.0000 42,000.00 0.050 2,100.00 1.000 42,000.00 09 INTERLOCKING CONCRETE PAVERS M2 129.0000 136,740.00 34.550 4,456.95 962.950 124,220.55 10 MULCH M3 20.0000 640.00 34.400 688.00 34.400 688.00 11 GRAVEL MULCH M2 32.0000 8,320.00 260.000 8,320.00 260.000 8,320.00 12 PLANT (GROUP A) EA 5.7500 6,842.50 653.500 3,757.63 980.000 5,635.00 13 PLANT (GROUP B) EA 16.0000 6,400.00 200.500 3,208.00 400.000 6,400.00 14 PLANT (GROUP H) EA 0.2300 37,720.00 152,940.000 35,176.20 152,940.000 35,176.20 15 PLANT (GROUP U) EA 69.0000 24,840.00 181.000 12,489.00 360.000 24,840.00 16 PLANT ESTABLISHMENT WORK LS 138,000.0000 138,000.00 0.000 0.00 17 CONTROL AND NEUTRAL CONDUCTORS LS 55,091.0000 55,091.00 1.000 55,091.00 18 25 MM ELECTRIC REMOTE CONTROL VALVE EA 210.0000 630.00 2.800 588.00 19 40 MM ELECTRIC REMOTE CONTROL VALVE EA 215.0000 8,815.00 40.000 8,600.00 20 50 MM ELECTRIC REMOTE CONTROL VALVE EA 220.0000 5,500.00 21.000 4,620.00 21 50 MM FLOW SENSOR (MASTER) EA 765.0000 2,295.00 2.700 2,065.50 22 36 STATION FIELD UNIT EA 19,260.0000 57,780.00 0.075 1,444.50 2.700 52,002.00 PROGRAM CAS145 PAGE 2 DATE 02/25/05 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-474204 TIME 09:25 AM ESTIMATE NO. 09 BID OPENING 03/25/04 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 02/18/05 R.E. NAME: SPRAY, MICHAEL DATE OF THIS ESTIMATE 02/25/05 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 23 40 MM GALVANIZED STEEL PIPE M 66.0000 2,310.00 35.000 2,310.00 F) (SUPPLY LINE) 24 100 MM GALVANIZED STEEL PIPE M 71.0000 3,195.00 45.000 3,195.00 F) (SUPPLY LINE) 25 20 MM PLASTIC PIPE (PR 200) M 5.9000 25,440.80 4,322.000 25,499.80 F) (SUPPLY LINE) 26 25 MM PLASTIC PIPE (PR 200) M 6.2500 13,900.00 2,234.000 13,962.50 F) (SUPPLY LINE) 27 32 MM PLASTIC PIPE (PR 200) M 7.0000 7,406.00 1,058.000 7,406.00 F) (SUPPLY LINE) 28 40 MM PLASTIC PIPE (PR 200) M 7.2500 4,618.25 637.000 4,618.25 F) (SUPPLY LINE) 29 50 MM PLASTIC PIPE (PR 200) M 7.5000 24,052.50 3,295.000 24,712.50 F) (SUPPLY LINE) 30 65 MM PLASTIC PIPE (PR 315) M 8.2500 6,435.00 834.000 6,880.50 F) (SUPPLY LINE) 31 75 MM PLASTIC PIPE (PR 315) M 11.0000 3,795.00 352.000 3,872.00 F) (SUPPLY LINE) 32 BACKFLOW PREVENTER ASSEMBLY ENCLOSURE EA 1,950.0000 5,850.00 3.000 5,850.00 33 75 MM BACKFLOW PREVENTER ASSEMBLY EA 2,365.0000 7,095.00 3.000 7,095.00 34 SPRINKLER (TYPE A-5) EA 20.0000 3,600.00 180.000 3,600.00 35 SPRINKLER (TYPE A-6) EA 41.0000 21,730.00 532.000 21,812.00 36 SPRINKLER (TYPE B-2) EA 34.0000 918.00 27.000 918.00 37 SPRINKLER (TYPE C-2) EA 20.0000 720.00 36.000 720.00 38 50 MM GATE VALVE EA 165.0000 2,475.00 20.000 3,300.00 39 75 MM GATE VALVE EA 170.0000 1,530.00 10.000 1,700.00 40 25 MM WYE STRAINER EA 425.0000 425.00 1.000 425.00 41 BOOSTER PUMP SYSTEM EA 28,000.0000 28,000.00 0.100 2,800.00 1.000 28,000.00 S) 42 ROCK SLOPE PROTECTION (LIGHT, METHOD B) M3 226.0000 3,842.00 0.000 0.00 43 1.8 M CHAIN LINK GATE (TYPE CL-1.8) EA 850.0000 8,500.00 10.000 8,500.00 44 IRRIGATION CONTROLLER ENCLOSURE CABINET EA 3,858.0000 11,574.00 3.000 11,574.00 S) 45 ELECTRIC SERVICE (IRRIGATION) LS 6,960.0000 6,960.00 0.900 6,264.00 S) 46 BOOSTER PUMP ELECTRICAL SYSTEM LS 15,560.0000 15,560.00 0.900 14,004.00 S) PROGRAM CAS145 PAGE 3 DATE 02/25/05 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 08-474204 TIME 09:25 AM ESTIMATE NO. 09 BID OPENING 03/25/04 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 02/18/05 R.E. NAME: SPRAY, MICHAEL DATE OF THIS ESTIMATE 02/25/05 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION 96,545.78 722,740.56 ADJUSTMENT OF COMPENSATION 1,701.90 1,701.90 EXTRA WORK 2,480.00 55,863.71 SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION 100,727.68 780,306.17 47 MOBILIZATION LS 78,000.0000 78,000.00 1.000 78,000.00 ORIGINAL CONTRACT AMOUNT 984,888.05 TOTAL WORK COMPLETED 100,727.68 858,306.17 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 100,727.68 858,306.17 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 04/22/04 940 05/07/04 05/07/04 03/27/08 181 17 12 0 81% 19% PROGRESS IS SATISFACTORY LANDSCAPE PROJECT W/PE SPRAY, MICHAEL RESIDENT ENGINEER PROGRAM CAS145 PAGE 3 DATE 02/25/05