PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 12/20/19 EST. NO. 006 TIME 03:52 PM R.E. NAME: PAWAN GARG 10-1H6404 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0001 1,009.90 E.W. @ F.A.(+) 070819 N 0001.0 0002 381.05 070919 N 0002.0 0003 691.65 071719 N 0003.0 0004 1,785.65 072419 N 0004.0 0005 612.90 072519 N 0005.0 0006 741.03 072919 N 0006.0 0007 792.11 072919 N 0007.0 0008 971.81 073019 N 0008.0 0009 575.21 073119 N 0009.0 0010 720.52 080619 N 0010.0 0011 720.52 080719 N 0011.0 0027 506.62 091119 N 0036.0 0028 506.62 091219 N 0037.0 0029 1,349.01 080619 N 0039.0 0030 1,490.48 080719 N 0040.0 0032 621.61 092019 N 0042.0 0033 1,573.74 092319 N 0043.0 0034 764.91 092319 N 0044.0 0035 764.91 092419 N 0045.0 0036 1,649.06 092419 N 0046.0 0037 1,649.06 092519 N 0047.0 0038 809.31 092619 N 0048.0 0039 8,072.09 100319 N 0049.0 0042 709.34 101719 N 0066.0 0044 458.15 100119 N 0069.0 0045 670.62 100219 N 0070.0 0047 762.19 100719 N 0072.0 0048 588.62 100819 N 0073.0 0049 590.11 100919 N 0074.0 0050 1,319.50 101219 N 0075.0 0051 547.62 101419 N 0076.0 0052 547.62 101519 N 0077.0 0053 670.62 101619 N 0078.0 0056 659.27 101719 N 0081.0 0057 554.30 101819 N 0082.0 002 0001 4,084.89 E.W. @ F.A.(+) 091719 N 0051.0 0002 8,469.02 091719 N 0052.0 0003 1,765.76 091719 N 0053.0 003 0001 2,015.52 E.W. @ F.A.(+) 081519 N 0017.0 0002 1,588.24 072919 N 0029.0 0003 7,538.14 090619 N 0030.0 0004 8,939.67 090919 N 0031.0 0005 9,912.90 091219 N 0034.0 0006 7,147.89 090419 N 0035.0 0007 8,436.36 091319 N 0038.0 0008 9,641.48 091019 N 0032.0 0009 9,698.99 091119 N 0033.0 0013 4,789.18 091919 N 0058.0 0014 3,487.17 092019 N 0059.0 0015 5,176.85 092319 N 0060.0 0016 5,652.25 092419 N 0061.0 PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 2 DATE 12/20/19 EST. NO. 006 TIME 03:52 PM R.E. NAME: PAWAN GARG 10-1H6404 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 0017 4,357.93 091819 N 0063.0 0018 3,789.00 092519 N 0062.0 0019 6,526.14 092319 N 0064.0 0022 1,420.79 081519 N 637163 0024 104,567.09 101019 N 0065.1 255,842.99 TOTAL THIS ESTIMATE 95,000.00 TOTAL PREVIOUS ESTIMATE 350,842.99 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 12/20/19 EST. NO. 006 TIME 03:52 PM R.E. NAME: PAWAN GARG 10-1H6404 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- ADMINISTRATIVE DEDUCT LCS NON COMPL -27,303.58 003 LCS 25% -200,578.78 005 RELEASE LCS 25% 227,882.36 006 WPCP ISSUES -25,000.00 006 202,882.36 -25,000.00 LABOR COMPLIANCE VIOLATION MISSING PAYROLLS -10,000.00 003 MISSING PAYROLS -10,000.00 004 MISSING PAYROLLS -10,000.00 005 MISSING PAYROLLS -10,000.00 006 -10,000.00 -40,000.00 TOTAL DEDUCTIONS 192,882.36 -65,000.00 PROGRAM CAS145 PAGE 1 DATE 12/20/19 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 10-1H6404 TIME 03:52 PM ESTIMATE NO. 006 BID OPENING 03/26/19 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/20/19 R.E. NAME: PAWAN GARG DATE OF THIS ESTIMATE 12/20/19 LOCATION RERUN PROGRESS ESTIMATE 10-AMA-49-R8.3/R10.5 ----------------------- 10-ALP-89-13.3/ .0 MYERS & SONS CONSTRUCTION, LLC IN AMADOR, ALPINE AND TUOLUMNE 10-TUO-49-13.5/ .0 4600 NORTHGATE BLVD, STE 100 COUNTIES AT VARIOUS LOCATIONS SACRAMENTO CA 95834 FED. AID NO. N O N E REPLACE JOINT SEALS AND APPROACH ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 LEAD COMPLIANCE PLAN LS 1,500.0000 1,500.00 1.000 1,500 002 CONSTRUCTION AREA SIGNS LS 14,500.0000 14,500.00 0.750 10,875 003 TRAFFIC CONTROL SYSTEM LS 370,000.0000 370,000.00 0.750 277,500 004 ALTERNATIVE TEMPORARY CRASH CUSHION EA 4,500.0000 18,000.00 0.000 0 005 TEMPORARY TRAFFIC STRIPE (TAPE) LF 5.6000 60,480.00 0.000 0 006 CHANNELIZER (SURFACE MOUNTED) EA 25.0000 2,725.00 40.000 1,000.00 40.000 1,000 007 PORTABLE CHANGEABLE MESSAGE SIGN (LS) LS 10,000.0000 10,000.00 0.750 7,500 008 TEMPORARY RAILING (TYPE K) LF 20.0000 191,600.00 560.000 11,200 009 TEMPORARY CRASH CUSHION MODULE EA 185.0000 42,550.00 56.000 10,360.00 112.000 20,720 010 JOB SITE MANAGEMENT LS 2,000.0000 2,000.00 0.750 1,500 011 PREPARE WATER POLLUTION CONTROL PROGRAM LS 1,500.0000 1,500.00 0.750 1,125 012 TEMPORARY CONCRETE WASHOUT LS 4,000.0000 4,000.00 1.000 4,000 013 REMOVE YELLOW THERMOPLASTIC TRAFFIC LF 0.6000 5,958.00 5,574.000 3,344 STRIPE (HAZARDOUS WASTE) 014 TREATED WOOD WASTE LB 0.1000 11,600.00 58,000.000 5,800 015 BAT EXCLUSION LS 3,500.0000 3,500.00 1.000 3,500 016 STRUCTURE EXCAVATION (BRIDGE) CY 225.0000 1,035.00 4.600 1,035 (F) 017 STRUCTURE BACKFILL (BRIDGE) CY 225.0000 967.50 4.300 967 (F) 018 EMBANKMENT CY 650.0000 17,550.00 0.000 0 019 DRY SEED (SQFT) SQFT 5.0000 1,000.00 0.000 0 020 FIBER ROLLS LF 65.0000 2,600.00 0.000 0 021 COMPOST (CY) CY 500.0000 350.00 0.000 0 022 HOT MIX ASPHALT (TYPE A) TON 400.0000 272,000.00 576.340 230,536 PROGRAM CAS145 PAGE 2 DATE 12/20/19 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 10-1H6404 TIME 03:52 PM ESTIMATE NO. 006 BID OPENING 03/26/19 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/20/19 R.E. NAME: PAWAN GARG DATE OF THIS ESTIMATE 12/20/19 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 023 PLACE HOT MIX ASPHALT DIKE (TYPE C) LF 5.0000 3,400.00 0.000 0 024 PLACE HOT MIX ASPHALT DIKE (TYPE F) LF 5.0000 18,650.00 0.000 0 025 TACK COAT TON 2,500.0000 3,250.00 1.000 2,500 026 REMOVE ASPHALT CONCRETE DIKE LF 2.0000 8,640.00 65.000 130 027 COLD PLANE ASPHALT CONCRETE PAVEMENT SQYD 20.0000 71,800.00 3,084.000 61,680 028 TEMPORARY DECKING LS 3,000.0000 3,000.00 0.000 0 029 STRUCTURAL CONCRETE, BRIDGE CY 1,490.0000 41,720.00 29.000 43,210 (F) 030 STRUCTURAL CONCRETE, BRIDGE (RSC) CY 6,300.0000 10,710.00 1.700 10,710 (F) 031 STRUCTURAL CONCRETE, APPROACH SLAB CY 1,800.0000 297,000.00 168.750 303,750 (TYPE R MODIFIED) 032 CLEAN EXPANSION JOINT LF 23.0000 13,708.00 210.000 4,830.00 606.000 13,938 033 JOINT SEAL (MR 1/2") LF 50.0000 6,400.00 128.000 6,400.00 128.000 6,400 034 JOINT SEAL (MR 1") LF 91.0000 14,014.00 161.000 14,651 035 JOINT SEAL ASSEMBLY (MR 4") LF 344.0000 56,416.00 164.000 56,416.00 164.000 56,416 036 JOINT SEAL (MR 2") LF 104.0000 8,632.00 86.000 8,944 037 BONDED JOINT SEAL (MR 1") LF 174.0000 11,658.00 67.000 11,658 038 BAR REINFORCING STEEL (EPOXY COATED) LB 1.7000 5,096.60 2,998.000 5,096 (F) (BRIDGE) 039 GALVANIC ANODE EA 160.0000 16,320.00 95.000 15,200 040 PUBLIC SAFETY PLAN LS 3,500.0000 3,500.00 1.000 3,500 041 RAPID SETTING CONCRETE (PATCH) CF 88.0000 31,064.00 288.000 25,344 042 REPAIR SPALLED SURFACE AREA SQFT 1,500.0000 3,450.00 2.300 3,450 043 REMOVE ASPHALT CONCRETE SURFACING SQFT 8.0000 30,920.00 3,776.000 30,208 044 REMOVE CONCRETE DECK SURFACE SQFT 35.0000 3,045.00 79.000 2,765 045 REMOVE POLYESTER CONCRETE OVERLAY SQFT 11.0000 15,312.00 1,392.000 15,312 046 REMOVE UNSOUND CONCRETE CF 108.0000 38,124.00 288.000 31,104 047 PREPARE CONCRETE BRIDGE DECK SURFACE SQFT 0.4500 45,323.10 6,029.000 2,713.05 100,718.000 45,323 048 FURNISH POLYESTER CONCRETE OVERLAY CF 66.0000 703,692.00 858.000 56,628.00 10,762.000 710,292 049 PLACE POLYESTER CONCRETE OVERLAY SQFT 4.5000 453,231.00 6,029.000 27,130.50 100,718.000 453,231 (F) PROGRAM CAS145 PAGE 3 DATE 12/20/19 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 10-1H6404 TIME 03:52 PM ESTIMATE NO. 006 BID OPENING 03/26/19 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/20/19 R.E. NAME: PAWAN GARG DATE OF THIS ESTIMATE 12/20/19 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 050 BRIDGE REMOVAL (PORTION), LOCATION A LS 26,000.0000 26,000.00 1.000 26,000 051 BRIDGE REMOVAL (PORTION), LOCATION B LS 39,000.0000 39,000.00 1.000 39,000 052 BRIDGE REMOVAL (PORTION), LOCATION C LS 29,000.0000 29,000.00 1.000 29,000 053 BRIDGE REMOVAL (PORTION), LOCATION D LS 17,000.0000 17,000.00 1.000 17,000 054 RECONSTRUCT STEEL COVER PLATE EA 3,200.0000 25,600.00 8.000 25,600.00 8.000 25,600 055 REMOVE PAVEMENT MARKER EA 1.0000 320.00 122.000 122 056 GUARD RAILING DELINEATOR EA 15.0000 5,250.00 0.000 0 057 PAVEMENT MARKER (RETROREFLECTIVE) EA 15.0000 4,800.00 0.000 0 058 PAVEMENT MARKER EA 350.0000 4,200.00 0.000 0 (RETROREFLECTIVE-RECESSED) 059 OBJECT MARKER (TYPE P) EA 95.0000 2,090.00 4.000 380 060 OBJECT MARKER (TYPE L-1) EA 50.0000 1,050.00 4.000 200 061 MIDWEST GUARDRAIL SYSTEM (STEEL POST) LF 25.0000 7,000.00 0.000 0 062 MIDWEST GUARDRAIL SYSTEM (WOOD POST) LF 32.5000 214,175.00 -125.000 -4,062.50 5,650.000 183,625 063 VEGETATION CONTROL (MINOR CONCRETE) SQYD 60.0000 232,200.00 823.000 49,380.00 823.000 49,380 064 TRANSITION RAILING (TYPE WB-31) EA 4,500.0000 94,500.00 2.000 9,000.00 8.000 36,000 065 END ANCHOR ASSEMBLY (TYPE SFT) EA 1,000.0000 1,000.00 0.000 0 066 ALTERNATIVE IN-LINE TERMINAL SYSTEM EA 3,500.0000 70,000.00 3.000 10,500.00 8.000 28,000 067 CONCRETE BARRIER (TYPE 736 MODIFIED) LF 415.0000 29,880.00 72.000 29,880 (F) 068 CONCRETE BARRIER TRANSITION LF 1,750.0000 87,500.00 50.000 87,500 (F) 069 REMOVE GUARDRAIL LF 4.0000 32,560.00 240.500 962.00 6,091.000 24,364 070 6" TWO-COMPONENT PAINT TRAFFIC STRIPE LF 3.8000 9,348.00 0.000 0 071 6" THERMOPLASTIC TRAFFIC STRIPE LF 3.5000 13,440.00 0.000 0 (ENHANCED WET NIGHT VISIBILITY) 072 6" AUDIBLE TRAFFIC STRIPE SYSTEMS LF 4.5000 52,650.00 0.000 0 073 REMOVE THERMOPLASTIC TRAFFIC STRIPE LF 0.4000 4,040.00 10,687.000 4,274 074 MAINTAINING EXISTING TRAFFIC MANAGEMENT LS 15,000.0000 15,000.00 0.750 11,250 SYSTEM ELEMENTS DURING CONSTRUCTION PROGRAM CAS145 PAGE 4 DATE 12/20/19 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 10-1H6404 TIME 03:52 PM ESTIMATE NO. 006 BID OPENING 03/26/19 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 12/20/19 R.E. NAME: PAWAN GARG DATE OF THIS ESTIMATE 12/20/19 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION 256,857.05 3,048,491.40 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 255,842.99 350,842.99 SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION 512,700.04 3,399,334.39 075 MOBILIZATION LS 441,000.0000 441,000.00 1.000 441,000 ORIGINAL CONTRACT AMOUNT 4,412,094.20 TOTAL WORK COMPLETED 512,700.04 3,840,334.39 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 192,882.36 -65,000.00 TOTAL 705,582.40 3,775,334.39 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 05/01/19 200 07/08/19 07/08/19 05/08/20 106 0 0 0 77% 53% PROGRESS IS SATISFACTORY PAWAN GARG RESIDENT ENGINEER PROGRAM CAS145 DATE 12/20/19