PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 11/20/25 EST. NO. 004 TIME 04:30 PM R.E. NAME: CHRIS HANSON 10-1U1004 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0061 9,375.47 E.W. @ F.A.(+) 060325 N 0061.0 0067 6,193.53 061225 N 0067.0 0073 1,459.98 061625 N 0073.0 0077 2,725.42 061225 N 0077.0 0081 4,067.46 073125 N 0081.0 0082 2,459.97 081025 N 0082.0 0083 12,779.92 080125 N 0083.0 0085 4,559.50 080125 N 338116 0086 1,089.00 083125 N 0085.0 0087 620.38 090925 N 0086.0 0088 3,961.35 050525 N 0087.0 0089 9,125.29 050825 N 0088.0 0090 8,162.70 051125 N 0089.0 0091 9,161.56 051225 N 0090.0 0092 13,673.04 051325 N 0091.0 0093 13,432.20 051425 N 0092.0 0094 17,565.19 051525 N 0093.0 0095 15,456.29 051725 N 0094.0 0096 3,265.06 053125 N 0095.0 0097 4,276.89 050625 N 0096.0 0098 256.96 040225 N 0097.0 0102 19,648.22 053025 N 0101.0 0103 1,722.15 060325 N 0102.0 0104 18,450.32 053125 N 0103.0 0107 4,671.81 091725 N 0106.0 0108 1,564.53 100225 N 0107.0 0109 87.99 100725 N 0108.0 0123 1,023.51 101025 N 0116.0 0124 1,429.36 101525 N 0117.0 0133 1,564.53 103025 N 0126.0 0134 7,755.18 102125 N 361556 201,584.76 TOTAL THIS ESTIMATE 446,540.67 TOTAL PREVIOUS ESTIMATE 648,125.43 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 11/20/25 EST. NO. 004 TIME 04:30 PM R.E. NAME: CHRIS HANSON 10-1U1004 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 11/20/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 10-1U1004 TIME 04:30 PM ESTIMATE NO. 004 BID OPENING 12/06/24 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 11/20/25 R.E. NAME: CHRIS HANSON DATE OF THIS ESTIMATE 11/20/25 LOCATION PROGRESS ESTIMATE 10-SJ-99-21.9/21.9 ----------------- VIKING CONSTRUCTION CO INC. REPAIR CALVARAS RIVER OC BRIDGE HIT 3835 SECURITY PARK DRIVE BRIDGE 290095 RANCHO CORDOVA, CA 95752 10A2779 DIRS EFA 101U1004 FED. AID NO. N O N E REPLACE DAMAGED GIRDER 1 AND DIAPHRAGM1 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 REPLACE DAMAGED GIRDER1& DIAPHRAGM1 LS 6,250.0000 6,250.00 0.000 0 PROGRAM CAS145 PAGE 2 DATE 11/20/25 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 10-1U1004 TIME 04:30 PM ESTIMATE NO. 004 BID OPENING 12/06/24 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 11/20/25 R.E. NAME: CHRIS HANSON DATE OF THIS ESTIMATE 11/20/25 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 201,584.76 648,125.43 SUBTOTAL AMOUNT EARNED 201,584.76 648,125.43 ORIGINAL CONTRACT AMOUNT 6,250.00 TOTAL WORK COMPLETED 201,584.76 648,125.43 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 201,584.76 648,125.43 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 02/20/25 100 12/18/24 12/18/24 12/31/25 222 0 0 0 52% 100% PROGRESS IS SATISFACTORY UNSATIS PROGRESS OVERRIDEN BECAU W H Y ... W H Y ... W H CHRIS HANSON RESIDENT ENGINEER