PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 10/25/11 EST. NO.06 TIME 07:28 AM R.E. NAME: OLSON, TED 11-091834 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0003 4,775.33 E.W. @ F.A.(+) 052311 N 0003.0 0004 195.43 060711 N 0005.0 0015 2,857.83 053111 N 0057.0 0019 564.89 070611 N 0082.0 007 0003 6,459.03 A.C. @ U.P.(+) 102011 N NA0003 008 0011 7,115.88 E.W. @ F.A.(+) 060111 N 0027.0 0012 36,290.49 060111 N 0075.0 009 0009 1,510.14 E.W. @ F.A.(+) 060711 N 0013.0 0020 11,363.48 061011 N 0058.0 0022 9,429.55 061411 N 0060.0 0024 364.32 071211 N 0029.1 0026 6,121.50 061011 N 0058.1 012 0001 -5,000.00 A.C. @ L.S.(-) 102011 N NA0001 013 0001 604.99 E.W. @ F.A.(+) 071211 N 0028.0 0002 1,873.95 072611 N 0046.0 0005 1,173.97 071811 N 0037.0 0006 584.52 071811 N 0039.0 0007 766.99 072511 N 0043.0 0011 2,271.31 072711 N 0086.0 014 0001 425.87 E.W. @ F.A.(+) 072811 N 0047.0 0003 703.32 080411 N 0062.0 0004 1,749.27 080311 N 0063.0 0006 1,296.00 081811 N 0065.0 0007 1,999.32 081911 N 0066.0 0008 2,471.00 082211 N 0067.0 0009 3,498.51 082311 N 0068.0 0010 3,498.51 082411 N 0069.0 0012 442.64 081111 N 0071.0 0013 1,117.55 081211 N 0072.0 0014 1,168.26 071511 N 0034.1 107,693.85 TOTAL THIS ESTIMATE 90,623.36 TOTAL PREVIOUS ESTIMATE 198,317.21 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 10/25/11 EST. NO.06 TIME 07:28 AM R.E. NAME: OLSON, TED 11-091834 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- ADMINISTRATIVE CONCRETE PAVEMNT DEF -2,532.60 03 FAILING CURE COMP TE -3,248.85 03 0.00 -5,781.45 LABOR COMPLIANCE VIOLATION DEL JUN 11 CPR -5,000.00 02 DEL JUL 2011 CPRS -10,000.00 03 PRTL JUNE 2011 CPRS 3,000.00 03 DEL AUGUST CPR -8,000.00 05 DEL SEPT 11 CPR -9,000.00 06 -9,000.00 -29,000.00 TOTAL DEDUCTIONS -9,000.00 -34,781.45 PROGRAM CAS145 PAGE 1 DATE 10/25/11 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 11-091834 TIME 07:28 AM ESTIMATE NO. 06 BID OPENING 01/20/11 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/11 R.E. NAME: OLSON, TED DATE OF THIS ESTIMATE 10/25/11 LOCATION PROGRESS ESTIMATE 11-SD-905-R5.2/R6.1 ----------------- FLATIRON CONSTRUCTION CORP IN SAN DIEGO COUNTY IN SAN DIEGO 1770 LA COSTA MEADOW DR ON RTE 905 FR 0.1 KM E TO 1.5 KM E SAN MARCOS, CA 92078 OF RTE 905/805 SEP AND ON RTE 805 FR 0.2 KM N OF RTE 905/805 SEP TO 0.5 KM S OF PALM AVE OC FED. AID NO. SRRA-A905(20)N CONSTRUCT NEW FREEWAY (PHASE 2) ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 001 PROGRESS SCHEDULE (CRITICAL PATH METHOD) LS 6,000.0000 6,000.00 0.250 1,500.00 0.750 4,500.00 002 TIME-RELATED OVERHEAD LS 420,000.0000 420,000.00 0.160 67,200.00 0.760 319,200.00 003 JACKING SUPERSTRUCTURE LS 36,000.0000 36,000.00 1.000 36,000.00 004 TEMPORARY FENCE (TYPE CL-1.8) M 30.0000 11,400.00 0.000 0.00 005 CONSTRUCTION SITE MANAGEMENT LS 23,000.0000 23,000.00 0.160 3,680.00 0.760 17,480.00 006 PREPARE STORM WATER POLLUTION LS 4,400.0000 4,400.00 0.160 704.00 0.900 3,960.00 PREVENTION PLAN 007 TEMPORARY FIBER ROLL M 7.0000 48,160.00 992.000 6,944.00 1,847.000 12,929.00 008 TEMPORARY CONCRETE WASHOUT FACILITY EA 2,000.0000 40,000.00 6.000 12,000.00 8.000 16,000.00 009 TEMPORARY CONSTRUCTION ENTRANCE EA 3,000.0000 51,000.00 1.000 3,000.00 7.000 21,000.00 010 TEMPORARY CHECK DAM M 13.0000 1,950.00 198.000 2,574.00 198.000 2,574.00 011 MOVE-IN/MOVE-OUT EA 500.0000 4,000.00 1.000 500.00 2.000 1,000.00 (TEMPORARY EROSION CONTROL) 012 TEMPORARY DRAINAGE INLET PROTECTION EA 350.0000 10,150.00 5.000 1,750.00 15.000 5,250.00 013 STREET SWEEPING LS 40,000.0000 40,000.00 0.160 6,400.00 0.760 30,400.00 014 TEMPORARY CONCRETE WASHOUT (PORTABLE) LS 5,000.0000 5,000.00 0.160 800.00 0.160 800.00 015 TEMPORARY HYDRAULIC MULCH M2 0.3000 33,600.00 47,000.000 14,100.00 016 RAIN EVENT ACTION PLAN EA 500.0000 14,000.00 1.000 500.00 1.000 500.00 017 STORM WATER ANNUAL REPORT EA 1,000.0000 2,000.00 0.000 0.00 018 STORM WATER SAMPLING AND ANALYSIS DAY EA 550.0000 4,950.00 0.000 0.00 019 CONSTRUCTION AREA SIGNS LS 14,000.0000 14,000.00 0.090 1,260.00 0.770 10,780.00 020 TRAFFIC CONTROL SYSTEM LS 100,000.0000 100,000.00 0.160 16,000.00 0.760 76,000.00 021 TYPE III BARRICADE EA 125.0000 375.00 3.000 375.00 022 TEMPORARY PAVEMENT MARKING (PAINT) M2 35.0000 2,065.00 64.350 2,252.25 PROGRAM CAS145 PAGE 2 DATE 10/25/11 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 11-091834 TIME 07:28 AM ESTIMATE NO. 06 BID OPENING 01/20/11 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/11 R.E. NAME: OLSON, TED DATE OF THIS ESTIMATE 10/25/11 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 023 TEMPORARY TRAFFIC STRIPE (PAINT) M 1.0000 34,200.00 19,716.000 19,716.00 024 TRAFFIC PLASTIC DRUM EA 10.0000 1,900.00 60.000 600.00 025 TEMPORARY PAVEMENT MARKER EA 4.0000 4,320.00 2,603.000 10,412.00 026 PORTABLE CHANGEABLE MESSAGE SIGN EA 2,000.0000 20,000.00 1.600 3,200.00 7.600 15,200.00 027 TEMPORARY RAILING (TYPE K) M 14.0000 127,260.00 5,650.000 79,100.00 028 TEMPORARY CRASH CUSHION MODULE EA 225.0000 54,000.00 114.000 25,650.00 029 REMOVE YELLOW PAINTED TRAFFIC STRIPE M 1.5000 4,920.00 0.000 0.00 (HAZARDOUS WASTE) 030 REMOVE FENCE M 15.0000 4,350.00 180.000 2,700.00 031 REMOVE METAL BEAM GUARD RAILING M 35.0000 1,995.00 11.400 399.00 11.400 399.00 032 REMOVE PAINTED TRAFFIC STRIPE M 1.2000 35,520.00 13,406.000 16,087.20 033 REMOVE PAINTED PAVEMENT MARKING M2 25.0000 1,475.00 0.000 0.00 034 REMOVE THERMOPLASTIC TRAFFIC STRIPE M 1.2000 1,476.00 0.000 0.00 035 REMOVE THERMOPLASTIC PAVEMENT MARKING M2 25.0000 600.00 17.550 438.75 036 REMOVE TRAFFIC STRIPE AND PAVEMENT M2 25.0000 6,500.00 0.000 0.00 MARKING 037 REMOVE CHANNELIZERS EA 5.0000 310.00 0.000 0.00 038 REMOVE ROADSIDE SIGN EA 200.0000 4,000.00 10.000 2,000.00 039 REMOVE SIGN STRUCTURE EA 3,500.0000 7,000.00 2.000 7,000.00 040 REMOVE CULVERT M 80.0000 1,440.00 6.000 480.00 041 REMOVE RISER M 105.0000 157.50 6.000 630.00 042 REMOVE INLET EA 700.0000 4,200.00 6.000 4,200.00 043 REMOVE HEADWALL EA 600.0000 1,200.00 2.000 1,200.00 044 REMOVE SLOPE PAVING LS 12,000.0000 12,000.00 1.000 12,000.00 1.000 12,000.00 045 REMOVE CONCRETE PAVEMENT M2 20.0000 160,200.00 4,429.400 88,588.00 046 RESET ROADSIDE SIGN EA 250.0000 250.00 0.000 0.00 047 ADJUST RISER EA 1,000.0000 5,000.00 3.000 3,000.00 048 MODIFY SIGN STRUCTURE EA 4,000.0000 8,000.00 0.000 0.00 049 COLD PLANE ASPHALT CONCRETE PAVEMENT M2 4.2000 28,476.00 0.000 0.00 PROGRAM CAS145 PAGE 3 DATE 10/25/11 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 11-091834 TIME 07:28 AM ESTIMATE NO. 06 BID OPENING 01/20/11 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/11 R.E. NAME: OLSON, TED DATE OF THIS ESTIMATE 10/25/11 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 050 REMOVE CONCRETE (MISCELLANEOUS) M3 68.0000 1,156.00 18.580 1,263.44 051 CAP RISER EA 1,200.0000 3,600.00 2.000 2,400.00 4.000 4,800.00 052 BRIDGE REMOVAL (PORTION) LS 20,000.0000 20,000.00 1.000 20,000.00 053 CLEARING AND GRUBBING LS 10,000.0000 10,000.00 0.700 7,000.00 054 DEVELOP WATER SUPPLY LS 21,000.0000 21,000.00 0.160 3,360.00 0.760 15,960.00 055 ROADWAY EXCAVATION M3 15.5000 733,150.00 37,049.680 574,270.04 056 LEAD COMPLIANCE PLAN LS 3,500.0000 3,500.00 1.000 3,500.00 057 SLOPE REPAIR M2 3.1000 31,930.00 0.000 0.00 058 STRUCTURE EXCAVATION (BRIDGE) M3 85.0000 6,800.00 80.000 6,800.00 (F) 059 STRUCTURE BACKFILL (BRIDGE) M3 150.0000 7,500.00 44.000 6,600.00 44.000 6,600.00 (F) 060 DITCH EXCAVATION M3 12.0000 2,760.00 0.000 0.00 061 HIGHWAY PLANTING LS 99,000.0000 99,000.00 0.000 0.00 062 IMPORTED TOPSOIL M3 5.0000 49,400.00 0.000 0.00 063 EROSION CONTROL (COMPOST BLANKET) M3 40.0000 44,800.00 0.000 0.00 064 CHECK DAM (EROSION CONTROL) M 12.0000 2,880.00 0.000 0.00 065 DRAINAGE INLET PROTECTION EA 375.0000 3,000.00 0.000 0.00 (EROSION CONTROL) 066 FIBER ROLLS M 6.5000 80,600.00 549.000 3,568.50 067 COMPOST (INCORPORATE) M2 0.7500 7,725.00 0.000 0.00 068 MOVE-IN/MOVE-OUT (EROSION CONTROL) EA 500.0000 4,000.00 -1.000 -500.00 0.000 0.00 069 EROSION CONTROL (HYDROSEED) M2 0.5000 5,150.00 0.000 0.00 070 ROLLED EROSION CONTROL PRODUCT M2 1.6000 20,000.00 0.000 0.00 (JUTE MESH) 071 EROSION CONTROL HA 8,000.0000 64,000.00 0.000 0.00 (POLYMER STABILIZED FIBER MATRIX) 072 PLANT ESTABLISHMENT WORK LS 12,000.0000 12,000.00 0.000 0.00 073 IRRIGATION SYSTEM LS 430,000.0000 430,000.00 0.033 14,190.00 0.373 160,390.00 074 WATER METER EA 35,000.0000 70,000.00 0.000 0.00 075 200 MM CORRUGATED HIGH DENSITY M 145.0000 11,310.00 78.000 11,310.00 78.000 11,310.00 POLYETHYLENE PIPE CONDUIT 076 EXTEND 200 MM CONDUIT M 725.0000 39,875.00 22.400 16,240.00 42.600 30,885.00 PROGRAM CAS145 PAGE 4 DATE 10/25/11 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 11-091834 TIME 07:28 AM ESTIMATE NO. 06 BID OPENING 01/20/11 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/11 R.E. NAME: OLSON, TED DATE OF THIS ESTIMATE 10/25/11 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 077 FINISHING ROADWAY LS 17,000.0000 17,000.00 0.000 0.00 078 CLASS 4 AGGREGATE SUBBASE M3 23.0000 109,020.00 8,370.300 192,516.90 079 CLASS 2 AGGREGATE BASE M3 40.0000 564,000.00 193.800 7,752.00 8,649.880 345,995.20 080 ASPHALTIC EMULSION (FOG SEAL COAT) TONN 1,300.0000 14,300.00 0.000 0.00 081 HOT MIX ASPHALT (TYPE A) TONN 82.0000 1,861,400.00 1,458.720 119,615.04 12,771.170 1,047,235.94 082 PLACE HOT MIX ASPHALT DIKE M 5.0000 18,750.00 0.000 0.00 083 PLACE HOT MIX ASPHALT M2 50.0000 10,500.00 0.000 0.00 (MISCELLANEOUS AREA) 084 TACK COAT TONN 550.0000 9,350.00 1.530 841.50 7.561 4,158.55 085 CONCRETE PAVEMENT M3 196.0000 2,136,400.00 4,367.000 855,932.00 6,299.000 1,234,604.00 086 REPLACE CONCRETE PAVEMENT M3 900.0000 63,900.00 0.000 0.00 (RAPID STRENGTH CONCRETE) 087 SEAL PAVEMENT JOINT M 7.5000 114,000.00 1,729.000 12,967.50 088 SEAL LONGITUDINAL ISOLATION JOINT M 60.0000 142,200.00 675.000 40,500.00 089 GRIND EXISTING CONCRETE M2 6.4000 63,168.00 3,363.000 21,523.20 PAVEMENT 090 PRESTRESSING CAST-IN-PLACE CONCRETE LS 24,000.0000 24,000.00 1.000 24,000.00 1.000 24,000.00 091 STRUCTURAL CONCRETE, BRIDGE FOOTING M3 550.0000 5,500.00 10.000 5,500.00 (F) 092 STRUCTURAL CONCRETE, BRIDGE M3 925.0000 129,500.00 8.200 7,585.00 117.100 108,317.50 (F) 093 STRUCTURAL CONCRETE, APPROACH SLAB M3 1,000.0000 20,000.00 0.000 0.00 (F) (TYPE N) 094 STRUCTURAL CONCRETE, APPROACH SLAB M3 1,000.0000 18,000.00 0.000 0.00 (TYPE R) 095 MINOR CONCRETE (MINOR STRUCTURE) M3 1,800.0000 70,200.00 39.500 71,100.00 (F) 096 EPOXY SEALANT (PIEZO SENSOR) LS 14,000.0000 14,000.00 0.000 0.00 097 JOINT SEAL (MR 15 MM) M 175.0000 2,625.00 0.000 0.00 098 BAR REINFORCING STEEL (BRIDGE) KG 2.2500 47,250.00 19,950.000 44,887.50 (F) 099 FURNISH SIGN STRUCTURE (TRUSS) KG 8.7000 410,596.50 0.000 0.00 (F) 100 INSTALL SIGN STRUCTURE (TRUSS) KG 0.3000 13,995.00 0.000 0.00 (F) 101 FURNISH LAMINATED PANEL SIGN M2 200.0000 36,000.00 0.000 0.00 (25.4 MM-TYPE A) 102 FURNISH SINGLE SHEET ALUMINUM SIGN M2 105.0000 1,155.00 0.000 0.00 (1.6 MM-UNFRAMED) 103 FURNISH SINGLE SHEET ALUMINUM SIGN M2 115.0000 1,955.00 0.000 0.00 (2.0 MM-UNFRAMED) PROGRAM CAS145 PAGE 5 DATE 10/25/11 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 11-091834 TIME 07:28 AM ESTIMATE NO. 06 BID OPENING 01/20/11 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/11 R.E. NAME: OLSON, TED DATE OF THIS ESTIMATE 10/25/11 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 104 1524 MM CAST-IN-DRILLED-HOLE M 2,100.0000 77,700.00 37.600 78,960.00 CONCRETE PILE (SIGN FOUNDATION) 105 ROADSIDE SIGN - ONE POST EA 445.0000 4,450.00 0.000 0.00 106 ROADSIDE SIGN ONE POST EA 525.0000 2,625.00 0.000 0.00 (WEED CONTROL MAT RUBBER) 107 INSTALL SIGN (STRAP AND SADDLE BRACKET EA 125.0000 875.00 0.000 0.00 METHOD) 108 INSTALL SIGN PANEL ON EXISTING STRUCTURE M2 90.0000 1,260.00 0.000 0.00 109 200 MM ALTERNATIVE PIPE CULVERT M 100.0000 7,600.00 0.500 50.00 76.000 7,600.00 110 600 MM REINFORCED CONCRETE PIPE M 265.0000 159,000.00 557.000 147,605.00 111 750 MM REINFORCED CONCRETE PIPE M 850.0000 2,380.00 2.800 2,380.00 112 450 MM CORRUGATED STEEL PIPE M 300.0000 300.00 0.000 0.00 (2.01 MM THICK) 113 750 MM CORRUGATED STEEL PIPE M 300.0000 900.00 0.000 0.00 (2.01 MM THICK) 114 900 MM CORRUGATED STEEL PIPE M 840.0000 3,696.00 4.400 3,696.00 (3.51 MM THICK) 115 1350 MM CORRUGATED STEEL PIPE M 900.0000 3,780.00 4.200 3,780.00 (2.01 MM THICK) 116 200 MM CORRUGATED STEEL PIPE DOWNDRAIN M 96.0000 3,840.00 0.000 0.00 (1.63 MM THICK) 117 450 MM ALTERNATIVE PIPE DOWNDRAIN M 250.0000 27,500.00 55.000 13,750.00 118 GRATED LINE DRAIN M 450.0000 14,850.00 0.000 0.00 119 600 MM CONCRETE FLARED END SECTION EA 1,200.0000 1,200.00 1.000 1,200.00 120 450 MM ALTERNATIVE FLARED END SECTION EA 620.0000 1,240.00 2.000 1,240.00 121 900 MM PRECAST CONCRETE PIPE INLET M 750.0000 7,500.00 6.050 4,537.50 122 ROCK SLOPE PROTECTION (LIGHT, METHOD B) M3 380.0000 6,460.00 7.200 2,736.00 123 CONCRETE (CONCRETE APRON) M3 385.0000 8,470.00 7.650 2,945.25 124 SLOPE PAVING (STAMPED CONCRETE) M2 76.0000 87,400.00 0.000 0.00 (F) 125 MINOR CONCRETE (DITCH LINING) M3 200.0000 26,000.00 0.000 0.00 126 ROCK SLOPE PROTECTION FABRIC M2 11.0000 682.00 0.000 0.00 127 MINOR CONCRETE (MISCELLANEOUS M3 370.0000 32,930.00 0.000 0.00 CONSTRUCTION) 128 MINOR CONCRETE (GUTTER) M 135.0000 17,550.00 0.000 0.00 129 MINOR CONCRETE (STAMPED CONCRETE) M2 75.0000 219,750.00 0.000 0.00 130 MISCELLANEOUS IRON AND STEEL KG 2.5000 7,835.00 0.000 0.00 (F) PROGRAM CAS145 PAGE 6 DATE 10/25/11 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 11-091834 TIME 07:28 AM ESTIMATE NO. 06 BID OPENING 01/20/11 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/11 R.E. NAME: OLSON, TED DATE OF THIS ESTIMATE 10/25/11 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 131 INLET GRATE (TYPE 36R) KG 5.0000 1,605.00 0.000 0.00 (F) 132 BRIDGE DECK DRAINAGE SYSTEM KG 48.0000 14,400.00 200.000 9,600.00 300.000 14,400.00 (F) 133 1.2 M CHAIN LINK GATE (TYPE CL-1.8) EA 850.0000 2,550.00 0.000 0.00 134 DELINEATOR (CLASS 1) EA 50.0000 4,850.00 0.000 0.00 135 MILEPOST MARKER EA 60.0000 840.00 0.000 0.00 136 GUARD RAILING DELINEATOR EA 20.0000 420.00 0.000 0.00 137 OBJECT MARKER EA 25.0000 250.00 0.000 0.00 138 METAL BEAM GUARD RAILING M 100.0000 7,600.00 0.000 0.00 139 DOUBLE METAL BEAM BARRIER M 150.0000 2,400.00 0.000 0.00 140 CABLE RAILING M 300.0000 2,700.00 0.000 0.00 141 TRANSITION RAILING (TYPE WB) EA 3,000.0000 3,000.00 0.000 0.00 142 RAIL TENSIONING ASSEMBLY EA 600.0000 1,200.00 0.000 0.00 143 END ANCHOR ASSEMBLY (TYPE SFT) EA 650.0000 3,900.00 0.000 0.00 144 ALTERNATIVE FLARED TERMINAL SYSTEM EA 2,500.0000 12,500.00 0.000 0.00 145 CRASH CUSHION (TYPE CAT) EA 6,000.0000 12,000.00 0.000 0.00 146 CRASH CUSHION (TYPE CAT) BACKUP EA 550.0000 1,100.00 0.000 0.00 147 CONCRETE BARRIER (TYPE 736) M 200.0000 10,800.00 0.000 0.00 (F) 148 CONCRETE BARRIER (TYPE 736 MODIFIED) M 225.0000 12,150.00 54.000 12,150.00 (F) 149 CONCRETE BARRIER (TYPE 736B) M 230.0000 1,610.00 7.000 1,610.00 7.000 1,610.00 150 THERMOPLASTIC PAVEMENT MARKING M2 45.0000 1,620.00 0.000 0.00 151 200 MM THERMOPLASTIC TRAFFIC STRIPE M 3.0000 4,200.00 0.000 0.00 152 200 MM THERMOPLASTIC TRAFFIC STRIPE M 2.0000 2,080.00 0.000 0.00 (BROKEN 3.66 M - 0.92 M) 153 100 MM THERMOPLASTIC TRAFFIC STRIPE M 1.0000 81.00 0.000 0.00 (BROKEN 5.18 M - 2.14 M) 154 PAINT TRAFFIC STRIPE (2-COAT) M 0.4000 9,160.00 0.000 0.00 155 PAVEMENT MARKER (NON-REFLECTIVE) EA 1.5000 4,965.00 0.000 0.00 156 PAVEMENT MARKER (RETROREFLECTIVE) EA 3.0000 6,330.00 0.000 0.00 157 MAINTAINING EXISTING TRAFFIC MANAGEMENT LS 2,000.0000 2,000.00 0.000 0.00 SYSTEM ELEMENTS DURING CONSTRUCTION PROGRAM CAS145 PAGE 7 DATE 10/25/11 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 11-091834 TIME 07:28 AM ESTIMATE NO. 06 BID OPENING 01/20/11 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/11 R.E. NAME: OLSON, TED DATE OF THIS ESTIMATE 10/25/11 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 158 LIGHTING AND SIGN ILLUMINATION LS 350,000.0000 350,000.00 0.319 111,650.00 0.416 145,600.00 159 PLANTING PLANT (GROUP R) LS 10.0000 10.00 0.000 0.00 160 TRAFFIC MONITORING STATION (LOCATION 1) LS 51,000.0000 51,000.00 0.208 10,608.00 0.208 10,608.00 161 TRAFFIC MONITORING STATION (LOCATION 2) LS 72,000.0000 72,000.00 0.056 4,032.00 162 TRAFFIC MONITORING STATION (LOCATION 3) LS 8,000.0000 8,000.00 0.000 0.00 163 ITEM DELETED PER ADDENDUM LS 0.0000 0.00 0.000 0.00 164 ITEM DELETED PER ADDENDUM LS 0.0000 0.00 0.000 0.00 165 FIBER OPTIC COMMUNICATION SYSTEM LS 678,000.0000 678,000.00 0.035 23,730.00 0.345 233,910.00 PROGRAM CAS145 PAGE 8 DATE 10/25/11 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 11-091834 TIME 07:28 AM ESTIMATE NO. 06 BID OPENING 01/20/11 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/11 R.E. NAME: OLSON, TED DATE OF THIS ESTIMATE 10/25/11 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION 1,366,984.54 5,556,894.22 ADJUSTMENT OF COMPENSATION 1,459.03 45,732.21 EXTRA WORK 106,234.82 152,585.00 SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION 1,474,678.39 5,755,211.43 166 MOBILIZATION LS 875,000.0000 875,000.00 0.950 831,250.00 ORIGINAL CONTRACT AMOUNT 11,994,794.00 TOTAL WORK COMPLETED 1,474,678.39 6,586,461.43 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS -9,000.00 -34,781.45 TOTAL 1,465,678.39 6,551,679.98 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 03/17/11 380 05/31/11 04/18/11 12/06/11 98 31 0 0 51% 26% PROGRESS IS SATISFACTORY OLSON, TED RESIDENT ENGINEER PROGRAM CAS145 DATE 10/25/11